Proposal:H.006338.6
Parish:Vernon
Description:HOLTON HARRIS ROAD BRIDGE
Type Construction:CLEARING AND GRUBBING, REMOVAL OF TIMBER BRIDGE,GRADING, CLASS II BASE COURSE, ASPHALT CONCRETE PAVEMENT, PRECAST CONCRETE PILES, CONCRETE SLAB SPAN BRIDGE, AND RELATED WORK.
Estimated Construction Cost:$1,405,409.00
| Rank | License | Bidder | Construction Bid |
| 1 | 55505 | MERRICK, LLC | $1,276,740.55 |
| 2 | 27239 | Apeck Construction, LLC | $1,348,646.64 |
| 3 | 00044 | Guinn Construction, LLC | $1,694,293.00 |
| 4 | 49239 | WL Bass Construction Inc. | $2,710,723.60 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - MERRICK, LLC | - 2 - Apeck Construction, LLC | - 3 - Guinn Construction, LLC | - 4 - WL Bass Construction Inc. | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 40,000.00 | 40,000.00 | 113,064.69 | 113,064.69 | 45,000.00 | 45,000.00 | 255,000.00 | 255,000.00 | | 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 10,000.00 | 10,000.00 | 6,985.36 | 6,985.36 | 20,000.00 | 20,000.00 | 10,000.00 | 10,000.00 | | 0003 | 202-02-03030 | Removal of Pavement Structure | 610 | SQYD | 17.00 | 10,370.00 | 13.90 | 8,479.00 | 10.00 | 6,100.00 | 6.00 | 3,660.00 | | 0004 | 202-02-04501 | Removal of Bridge (STA. 100+00, 12' W x 57.7' L, TIMBER BRIDGE) | 692.4 | LUMP | 50,000.00 | 50,000.00 | 23,867.15 | 23,867.15 | 30,000.00 | 30,000.00 | 100,000.00 | 100,000.00 | | 0005 | 203-02-00100 | Drainage Excavation | 411 | CUYD | 30.00 | 12,330.00 | 154.12 | 63,343.32 | 35.00 | 14,385.00 | 24.00 | 9,864.00 | | 0006 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 45,000.00 | 45,000.00 | 41,610.61 | 41,610.61 | 55,000.00 | 55,000.00 | 104,000.00 | 104,000.00 | | 0007 | 204-06-00100 | Temporary Silt Fencing | 715 | LNFT | 3.25 | 2,323.75 | 5.97 | 4,268.55 | 4.00 | 2,860.00 | 5.00 | 3,575.00 | | 0008 | 302-01-00300 | Class II Base Course (Crushed Stone) | 175.8 | CUYD | 215.00 | 37,797.00 | 233.00 | 40,961.40 | 250.00 | 43,950.00 | 300.00 | 52,740.00 | | 0009 | 302-03-00100 | Base Drain Outlet | 8 | EACH | 500.00 | 4,000.00 | 2,302.79 | 18,422.32 | 2,000.00 | 16,000.00 | 3,000.00 | 24,000.00 | | 0010 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 6 | CUYD | 170.00 | 1,020.00 | 240.27 | 1,441.62 | 500.00 | 3,000.00 | 150.00 | 900.00 | | 0011 | 402-01-00101 | Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) | 50 | CUYD | 180.00 | 9,000.00 | 159.15 | 7,957.50 | 100.00 | 5,000.00 | 150.00 | 7,500.00 | | 0012 | 502-01-00100 | Asphalt Concrete | 147.5 | TON | 360.00 | 53,100.00 | 312.64 | 46,114.40 | 400.00 | 59,000.00 | 310.00 | 45,725.00 | | 0013 | 704-03-00200 | Blocked Out Guard Rail - 31", (6'-3" Post Spacing) | 50 | LNFT | 30.00 | 1,500.00 | 40.02 | 2,001.00 | 45.00 | 2,250.00 | 25.00 | 1,250.00 | | 0014 | 704-07-00200 | Guard Rail Transitions (Double Thrie Beam) | 100 | LNFT | 112.00 | 11,200.00 | 161.26 | 16,126.00 | 165.00 | 16,500.00 | 95.00 | 9,500.00 | | 0015 | 704-10-00205 | Guard Rail End Treatment, MASH, (TL-3 Tangent) | 4 | EACH | 3,650.00 | 14,600.00 | 4,897.54 | 19,590.16 | 5,500.00 | 22,000.00 | 3,150.00 | 12,600.00 | | 0016 | 705-01-00100 | Barbed Wire Fence | 57 | LNFT | 75.00 | 4,275.00 | 41.81 | 2,383.17 | 50.00 | 2,850.00 | 35.00 | 1,995.00 | | 0017 | 711-01-04000 | Riprap (55 lb, 18" Thick) | 663 | SQYD | 112.00 | 74,256.00 | 114.67 | 76,026.21 | 200.00 | 132,600.00 | 120.00 | 79,560.00 | | 0018 | 711-04-00100 | Geotextile Fabric | 663 | SQYD | 7.00 | 4,641.00 | 7.17 | 4,753.71 | 10.00 | 6,630.00 | 5.00 | 3,315.00 | | 0019 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 18,000.00 | 18,000.00 | 42,898.26 | 42,898.26 | 30,000.00 | 30,000.00 | 55,000.00 | 55,000.00 | | 0020 | 716-01-00100 | Mulch (Vegetative) | 0.4 | TON | 2,100.00 | 840.00 | 6,569.88 | 2,627.95 | 10,000.00 | 4,000.00 | 5,500.00 | 2,200.00 | | 0021 | 717-01-00100 | Seeding | 10 | LB | 45.00 | 450.00 | 59.73 | 597.30 | 50.00 | 500.00 | 50.00 | 500.00 | | 0022 | 718-01-00100 | Fertilizer | 222 | LB | 2.25 | 499.50 | 5.97 | 1,325.34 | 2.00 | 444.00 | 5.30 | 1,176.60 | | 0023 | 727-01-00100 | Mobilization | 1 | LUMP | 120,000.00 | 120,000.00 | 80,042.16 | 80,042.16 | 300,000.00 | 300,000.00 | 271,000.00 | 271,000.00 | | 0024 | 729-01-00102 | Sign (Type A)(Furnish and Install) | 9 | SQFT | 175.00 | 1,575.00 | 53.75 | 483.75 | 100.00 | 900.00 | 45.00 | 405.00 | | 0025 | 729-16-00300 | Object Marker Assembly (Type 3) | 4 | EACH | 165.00 | 660.00 | 161.26 | 645.04 | 200.00 | 800.00 | 150.00 | 600.00 | | 0026 | 735-01-00100 | Mailboxes | 3 | EACH | 300.00 | 900.00 | 59.73 | 179.19 | 150.00 | 450.00 | 50.00 | 150.00 | | 0027 | 735-02-00100 | Mailbox Supports (Single) | 1 | EACH | 300.00 | 300.00 | 298.63 | 298.63 | 150.00 | 150.00 | 250.00 | 250.00 | | 0028 | 735-03-00100 | Mailbox Supports (Double) | 1 | EACH | 300.00 | 300.00 | 358.36 | 358.36 | 300.00 | 300.00 | 350.00 | 350.00 | | 0029 | 740-01-00100 | Construction Layout | 1 | LUMP | 25,000.00 | 25,000.00 | 11,390.19 | 11,390.19 | 20,000.00 | 20,000.00 | 75,000.00 | 75,000.00 | | 0030 | 804-01-00300 | Precast Concrete Piles (16") | 1,400 | LNFT | 165.00 | 231,000.00 | 126.81 | 177,534.00 | 200.00 | 280,000.00 | 500.00 | 700,000.00 | | 0031 | 804-17-00100 | Construction Site Survey | 1 | LUMP | 15,000.00 | 15,000.00 | 2,278.04 | 2,278.04 | 15,000.00 | 15,000.00 | 20,000.00 | 20,000.00 | | 0032 | 804-18-00100 | Vibration Monitoring | 10 | DAY | 1,125.00 | 11,250.00 | 477.81 | 4,778.10 | 2,000.00 | 20,000.00 | 400.00 | 4,000.00 | | 0033 | 805-12-00100 | Bridge Superstructure and Substructure (24' Roadway, 90 Degree Crossing) (CAST-IN-PLACE) | 1,920 | SQFT | 220.00 | 422,400.00 | 222.69 | 427,564.80 | 245.00 | 470,400.00 | 400.00 | 768,000.00 | | 0034 | 805-18-00100 | Concrete Finish (Class 2 Rubbed Finish) | 954 | SQFT | 4.00 | 3,816.00 | 7.67 | 7,317.18 | 3.00 | 2,862.00 | 1.00 | 954.00 | | 0035 | 805-18-00200 | Concrete Finish (Class 3 Special Finish) | 954 | SQFT | 2.45 | 2,337.30 | 7.67 | 7,317.18 | 3.00 | 2,862.00 | 1.00 | 954.00 | | 0036 | 813-01-00100 | Concrete Approach Slabs (Cast-in-Place) (24' Roadway; 90 Degree Crossing, Without Asphalt) (10' Long) | 500 | SQFT | 74.00 | 37,000.00 | 167.23 | 83,615.00 | 125.00 | 62,500.00 | 170.00 | 85,000.00 | | | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 1,276,740.55 | | 1,348,646.64 | | 1,694,293.00 | | 2,710,723.60 |
|