Proposal:H.014109.6
Parish:St. John the Baptist
Routes:US 61
Description:US 61: WILDCAT DR - AIRPORT RD
Type Construction:MILLING ASPHALT CONCRETE, PAVEMENT PATCHING, CLEANING AND SEALING CONCRETE JOINTS, ASPHALT CONCRETE OVERLAY, AND RELATED WORK.
Estimated Construction Cost:$6,888,053.01
| Rank | License | Bidder | Construction Bid |
| 1 | 00046 | Barber Bros. Contracting Co., L.L.C | $5,162,154.67 |
| 2 | 06276 | Barriere Construction Co., LLC | $5,196,717.01 |
| 3 | 73475 | Madden Gulf Coast, LLC | $5,690,252.82 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Barber Bros. Contracting Co., L.L.C | - 2 - Barriere Construction Co., LLC | - 3 - Madden Gulf Coast, LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0002 | 203-07-00100 | Borrow (Vehicular Measurement) | 740.1 | CUYD | 55.00 | 40,705.50 | 108.00 | 79,930.80 | 150.00 | 111,015.00 | | 0003 | 502-01-00100 | Asphalt Concrete | 28,024.5 | TON | 114.00 | 3,194,793.00 | 115.25 | 3,229,823.63 | 115.00 | 3,222,817.50 | | 0004 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 213.2 | TON | 235.00 | 50,102.00 | 260.00 | 55,432.00 | 392.00 | 83,574.40 | | 0005 | 509-01-00100 | Milling Asphalt Pavement | 145,147 | SQYD | 3.00 | 435,441.00 | 2.75 | 399,154.25 | 2.45 | 355,610.15 | | 0006 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -6,145 | CUYD | 0.00 | 0.00 | 0.10 | -614.50 | 0.01 | -61.45 | | 0007 | 510-01-00250 | Pavement Patching (14 inch Minimum Thickness) | 1,665 | SQYD | 125.00 | 208,125.00 | 110.00 | 183,150.00 | 146.00 | 243,090.00 | | 0009 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 170,000.00 | 170,000.00 | 305,500.00 | 305,500.00 | 450,000.00 | 450,000.00 | | 0010 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 6,879 | LNFT | 0.35 | 2,407.65 | 0.35 | 2,407.65 | 0.35 | 2,407.65 | | 0011 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 765 | LNFT | 0.50 | 382.50 | 0.50 | 382.50 | 0.50 | 382.50 | | 0012 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 29.706 | MILE | 300.00 | 8,911.80 | 336.00 | 9,981.22 | 400.00 | 11,882.40 | | 0013 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 31.165 | MILE | 900.00 | 28,048.50 | 900.00 | 28,048.50 | 900.00 | 28,048.50 | | 0014 | 713-05-00220 | Temporary Pavement Legends & Symbols (Arrow - Left Turn) | 192 | EACH | 25.00 | 4,800.00 | 25.00 | 4,800.00 | 25.00 | 4,800.00 | | 0015 | 713-05-00230 | Temporary Pavement Legends & Symbols (Arrow - Right Turn) | 18 | EACH | 25.00 | 450.00 | 25.00 | 450.00 | 25.00 | 450.00 | | 0016 | 713-05-00300 | Temporary Pavement Legends & Symbols (ONLY) | 57 | EACH | 25.00 | 1,425.00 | 25.00 | 1,425.00 | 25.00 | 1,425.00 | | 0017 | 724-02-00100 | Rumble Strips (Shoulder/Edge) | 5.87 | MILE | 325.00 | 1,907.75 | 275.00 | 1,614.25 | 1,000.00 | 5,870.00 | | 0018 | 727-01-00100 | Mobilization | 1 | LUMP | 375,000.00 | 375,000.00 | 166,025.59 | 166,025.59 | 492,000.00 | 492,000.00 | | 0019 | 731-02-00100 | Reflectorized Raised Pavement Markers | 514 | EACH | 6.75 | 3,469.50 | 6.50 | 3,341.00 | 6.50 | 3,341.00 | | 0020 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 2,293 | LNFT | 2.60 | 5,961.80 | 2.50 | 5,732.50 | 2.50 | 5,732.50 | | 0021 | 732-01-01080 | Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) | 255 | LNFT | 13.00 | 3,315.00 | 12.00 | 3,060.00 | 12.00 | 3,060.00 | | 0022 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 10.388 | MILE | 4,200.00 | 43,629.60 | 4,000.00 | 41,552.00 | 4,000.00 | 41,552.00 | | 0023 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 9.902 | MILE | 1,300.00 | 12,872.60 | 1,250.00 | 12,377.50 | 1,250.00 | 12,377.50 | | 0024 | 732-03-02010 | Plastic Pavement Striping (Dotted Line)(4" W)(2' L)(Thermo 90 mil) | 0.08 | MILE | 4,200.00 | 336.00 | 4,000.00 | 320.00 | 4,000.00 | 320.00 | | 0025 | 732-03-02030 | Plastic Pavement Striping (Dotted Line)(8" W)(2' L)(Thermo 90 mil) | 0.369 | MILE | 6,100.00 | 2,250.90 | 6,000.00 | 2,214.00 | 6,000.00 | 2,214.00 | | 0026 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 64 | EACH | 315.00 | 20,160.00 | 300.00 | 19,200.00 | 300.00 | 19,200.00 | | 0027 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 6 | EACH | 315.00 | 1,890.00 | 300.00 | 1,800.00 | 300.00 | 1,800.00 | | 0028 | 735-01-00100 | Mailboxes | 25 | EACH | 21.00 | 525.00 | 35.00 | 875.00 | 35.00 | 875.00 | | 0029 | 735-02-00100 | Mailbox Supports (Single) | 25 | EACH | 260.00 | 6,500.00 | 225.00 | 5,625.00 | 225.00 | 5,625.00 | | 0030 | 736-01-00100 | Trenching and Backfilling | 55 | LNFT | 13.00 | 715.00 | 12.11 | 666.05 | 12.11 | 666.05 | | 0031 | 736-09-00100 | Loop Detector | 1,500 | LNFT | 34.00 | 51,000.00 | 33.12 | 49,680.00 | 33.12 | 49,680.00 | | 0032 | 736-10-00200 | Underground Junction Box (Type E) | 2 | EACH | 1,450.00 | 2,900.00 | 1,378.00 | 2,756.00 | 1,377.83 | 2,755.66 | | 0033 | 736-11-00050 | Conduit (1/2" HDPE, Schedule 80) | 55 | LNFT | 14.00 | 770.00 | 13.78 | 757.90 | 13.78 | 757.90 | | 0034 | 740-01-00100 | Construction Layout | 1 | LUMP | 15,000.00 | 15,000.00 | 8,500.00 | 8,500.00 | 10,000.00 | 10,000.00 | | 0035 | NS-500-00340 | Saw Cutting Asphalt Concrete Pavement LOOP WIRE | 1,500 | INLF | 1.00 | 1,500.00 | 1.00 | 1,500.00 | 1.00 | 1,500.00 | | 0036 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 1,710 | INLF | 15.00 | 25,650.00 | 18.00 | 30,780.00 | 4.00 | 6,840.00 | | 0037 | NS-602-00010 | Cleaning and Sealing Vertical Concrete Joints | 489.57 | LNFT | 1.00 | 489.57 | 15.42 | 7,549.17 | 8.00 | 3,916.56 | | 0038 | NS-713-00009 | Portable Changeable Message Sign (with communications) | 2 | EACH | 7,000.00 | 14,000.00 | 14,000.00 | 28,000.00 | 7,000.00 | 14,000.00 | | 0039 | 510-01-00250 | Pavement Patching (14 inch Minimum Thickness) Blow Up Repair Patching | 3,048 | SQYD | 140.00 | 426,720.00 | 165.00 | 502,920.00 | 161.00 | 490,728.00 | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 5,162,154.67 | | 5,196,717.01 | | 5,690,252.82 |
|