Proposal:H.015784.6
Parish:Avoyelles
Routes:LA 1181, LA 1182
Description: LA 1181 & LA 1182: ASPHALT OVERLAYS
Type Construction:DRAINAGE STRUCTURES, MILLING ASPHALT PAVEMENT, LIME TREATMENT, IN-PLACE CEMENT TREATED BASE COURSE, PAVEMENT WIDENING, ASPHALT CONCRETE OVERLAY, AND RELATED WORK.
Estimated Construction Cost:$2,634,611.77
| Rank | License | Bidder | Construction Bid |
| 1 | 12312 | GILCHRIST CONSTRUCTION COMPANY, LLC | $2,937,497.95 |
| 2 | 12487 | Diamond B Construction Co., L.L.C. | $2,983,086.61 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - GILCHRIST CONSTRUCTION COMPANY, LLC | - 2 - Diamond B Construction Co., L.L.C. | | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 202-02-04560 | Removal of Bridge Joint (POURED JOINT SEAL) | 350 | LNFT | 55.00 | 19,250.00 | 30.00 | 10,500.00 | | 0002 | 202-02-06100 | Removal of Concrete Walks and Drives | 509 | SQYD | 25.00 | 12,725.00 | 21.00 | 10,689.00 | | 0003 | 202-02-14500 | Removal of Guard Rail | 214.6 | LNFT | 15.00 | 3,219.00 | 15.00 | 3,219.00 | | 0004 | 202-02-32100 | Removal of Pipe (Cross Drain) (18"RCP) | 291 | LNFT | 45.00 | 13,095.00 | 15.00 | 4,365.00 | | 0005 | 202-02-32100 | Removal of Pipe (Cross Drain) (24" EQUIV. CMPA) | 37 | LNFT | 45.00 | 1,665.00 | 15.00 | 555.00 | | 0006 | 202-02-32100 | Removal of Pipe (Cross Drain) (24" RCP) | 33 | LNFT | 45.00 | 1,485.00 | 15.00 | 495.00 | | 0007 | 202-02-32100 | Removal of Pipe (Cross Drain) (36" RCP) | 4 | LNFT | 85.00 | 340.00 | 15.00 | 60.00 | | 0008 | 202-02-32180 | Removal of Pipe Headwalls | 1 | EACH | 3,000.00 | 3,000.00 | 1,200.00 | 1,200.00 | | 0009 | 203-07-00100 | Borrow (Vehicular Measurement) | 1,057 | CUYD | 80.00 | 84,560.00 | 20.00 | 21,140.00 | | 0010 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 52 | EACH | 175.00 | 9,100.00 | 150.00 | 7,800.00 | | 0011 | 204-06-00100 | Temporary Silt Fencing | 700 | LNFT | 2.25 | 1,575.00 | 2.00 | 1,400.00 | | 0012 | 303-03-00400 | In-Place Cement Treated Base Course (12" Thick) | 39,632.6 | SQYD | 12.00 | 475,591.20 | 16.00 | 634,121.60 | | 0013 | 304-01-00100 | Lime | 99.33 | TON | 400.00 | 39,732.00 | 430.00 | 42,711.90 | | 0014 | 304-03-00400 | Lime Treatment (Type C) (12" Thick) | 10,511.1 | SQYD | 9.00 | 94,599.90 | 11.00 | 115,622.10 | | 0015 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 536 | CUYD | 90.00 | 48,240.00 | 55.00 | 29,480.00 | | 0016 | 502-01-00100 | Asphalt Concrete | 7,439.8 | TON | 150.00 | 1,115,970.00 | 135.00 | 1,004,373.00 | | 0017 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 973.1 | TON | 150.00 | 145,965.00 | 255.00 | 248,140.50 | | 0018 | 509-01-00100 | Milling Asphalt Pavement | 34,195 | SQYD | 5.00 | 170,975.00 | 3.00 | 102,585.00 | | 0019 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -2,535 | CUYD | 1.00 | -2,535.00 | 1.00 | -2,535.00 | | 0020 | 510-02-00100 | Pavement Widening (16" THICKNESS) | 23 | SQYD | 800.00 | 18,400.00 | 800.00 | 18,400.00 | | 0021 | 701-02-02000 | Cross Drain Pipe Arch (24" Equiv. RCPA or 30" Equiv. CMPA) | 40 | LNFT | 280.00 | 11,200.00 | 275.00 | 11,000.00 | | 0022 | 701-02-02001 | Cross Drain Pipe Arch (24" Equiv. RCPA or 24" Equiv. CMPA) | 388 | LNFT | 280.00 | 108,640.00 | 275.00 | 106,700.00 | | 0023 | 701-04-01040 | Storm Drain Pipe Arch (24" Equiv. RCPA) | 32 | LNFT | 300.00 | 9,600.00 | 265.00 | 8,480.00 | | 0024 | 701-10-01100 | Reinforced Concrete Pipe (Extension) (36") | 32 | LNFT | 220.00 | 7,040.00 | 300.00 | 9,600.00 | | 0025 | 701-15-00100 | Concrete Collar | 2 | EACH | 2,300.00 | 4,600.00 | 1,950.00 | 3,900.00 | | 0026 | 701-17-00100 | Trench Excavation Safety Protection (Depth >5 feet) | 171 | LNFT | 3.00 | 513.00 | 15.00 | 2,565.00 | | 0027 | 702-03-00100 | Catch Basins (CB-01) | 1 | EACH | 6,000.00 | 6,000.00 | 7,000.00 | 7,000.00 | | 0028 | 704-01-01020 | Guard Rail (Single Thrie Beam) (6'-3" post spacing) | 76 | LNFT | 60.00 | 4,560.00 | 110.00 | 8,360.00 | | 0029 | 704-03-00200 | Blocked Out Guard Rail - 31", (6'-3" Post Spacing) | 187.5 | LNFT | 32.00 | 6,000.00 | 33.00 | 6,187.50 | | 0030 | 704-07-00200 | Guard Rail Transitions (Double Thrie Beam) | 100 | LNFT | 125.00 | 12,500.00 | 133.00 | 13,300.00 | | 0031 | 704-10-00205 | Guard Rail End Treatment, MASH, (TL-3 Tangent) | 4 | EACH | 3,400.00 | 13,600.00 | 4,200.00 | 16,800.00 | | 0032 | 707-04-00100 | Asphalt Curb | 54 | LNFT | 70.00 | 3,780.00 | 80.00 | 4,320.00 | | 0033 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 60,000.00 | 60,000.00 | 78,000.00 | 78,000.00 | | 0034 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 9.111 | MILE | 250.00 | 2,277.75 | 160.00 | 1,457.76 | | 0035 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 5.749 | MILE | 100.00 | 574.90 | 500.00 | 2,874.50 | | 0036 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 26.704 | MILE | 100.00 | 2,670.40 | 900.00 | 24,033.60 | | 0037 | 722-02-00100 | Project Site Laboratory (Equipped) | 1 | EACH | 11,000.00 | 11,000.00 | 12,000.00 | 12,000.00 | | 0038 | 726-01-00100 | Bedding Material | 112.3 | CUYD | 210.00 | 23,583.00 | 180.00 | 20,214.00 | | 0039 | 727-01-00100 | Mobilization | 1 | LUMP | 240,000.00 | 240,000.00 | 260,000.00 | 260,000.00 | | 0040 | 729-16-00200 | Object Marker Assembly (Type 2) | 28 | EACH | 80.00 | 2,240.00 | 120.00 | 3,360.00 | | 0041 | 729-16-00300 | Object Marker Assembly (Type 3) | 4 | EACH | 90.00 | 360.00 | 130.00 | 520.00 | | 0042 | 731-02-00100 | Reflectorized Raised Pavement Markers | 550 | EACH | 4.25 | 2,337.50 | 9.00 | 4,950.00 | | 0043 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 35 | LNFT | 13.00 | 455.00 | 15.00 | 525.00 | | 0044 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 8.901 | MILE | 4,100.00 | 36,494.10 | 5,550.00 | 49,400.55 | | 0045 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 1.907 | MILE | 1,600.00 | 3,051.20 | 2,800.00 | 5,339.60 | | 0046 | 735-01-00100 | Mailboxes | 59 | EACH | 27.00 | 1,593.00 | 25.00 | 1,475.00 | | 0047 | 735-02-00100 | Mailbox Supports (Single) | 59 | EACH | 210.00 | 12,390.00 | 200.00 | 11,800.00 | | 0048 | 739-01-00100 | Hydro-Seeding | 3.68 | ACRE | 2,700.00 | 9,936.00 | 2,650.00 | 9,752.00 | | 0049 | 740-01-00100 | Construction Layout | 1 | LUMP | 25,000.00 | 25,000.00 | 21,000.00 | 21,000.00 | | 0050 | 815-03-00300 | Joint Seal (Poured) | 350 | LNFT | 100.00 | 35,000.00 | 42.00 | 14,700.00 | | 0051 | NS-500-00260 | Sawcuts in Asphalt Concrete Lifts | 350 | LNFT | 21.00 | 7,350.00 | 3.00 | 1,050.00 | | 0052 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 4,050 | INLF | 4.00 | 16,200.00 | 2.00 | 8,100.00 | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 2,937,497.95 | | 2,983,086.61 |
|