Proposal:H.014881.6
Parish:Franklin
Routes:US 425
Description:US 425: WINNSBORO - BASKIN
Type Construction:GRADING, MILLING ASPHALT CONCRETE, PAVEMENT PATCHING, CLASS II BASE COURSE, ASPHALT SURFACE TREATMENT, ASPHALT CONCRETE OVERLAY, AND RELATED WORK.
Estimated Construction Cost:$4,173,540.69
| Rank | License | Bidder | Construction Bid |
| 1 | 12487 | Diamond B Construction Co., L.L.C. | $4,049,455.63 |
| 2 | 12312 | GILCHRIST CONSTRUCTION COMPANY, LLC | $4,764,955.80 |
| 3 | 05789 | D & J CONSTRUCTION CO., LLC | $5,207,015.15 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Diamond B Construction Co., L.L.C. | - 2 - GILCHRIST CONSTRUCTION COMPANY, LLC | - 3 - D & J CONSTRUCTION CO., LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 202-02-00020 | Removal of GUARD RAIL PAD | 1,623 | SQYD | 14.00 | 22,722.00 | 12.00 | 19,476.00 | 20.00 | 32,460.00 | | 0002 | 202-02-02020 | Removal of Asphalt Pavement | 125 | SQYD | 180.00 | 22,500.00 | 82.00 | 10,250.00 | 15.00 | 1,875.00 | | 0003 | 202-02-14500 | Removal of Guard Rail | 1,596 | LNFT | 14.00 | 22,344.00 | 7.00 | 11,172.00 | 25.00 | 39,900.00 | | 0004 | 203-03-00100 | Embankment | 250 | CUYD | 140.00 | 35,000.00 | 60.00 | 15,000.00 | 75.00 | 18,750.00 | | 0005 | 203-07-00100 | Borrow (Vehicular Measurement) | 100 | CUYD | 10.00 | 1,000.00 | 60.00 | 6,000.00 | 75.00 | 7,500.00 | | 0006 | 204-06-00100 | Temporary Silt Fencing | 1,500 | LNFT | 3.55 | 5,325.00 | 2.50 | 3,750.00 | 6.00 | 9,000.00 | | 0007 | 302-02-06030 | Class II Base Course (6" Thick) (Asphalt Concrete Base) | 502.3 | SQYD | 85.00 | 42,695.50 | 95.00 | 47,718.50 | 90.00 | 45,207.00 | | 0008 | 502-01-00100 | Asphalt Concrete | 12,926.9 | TON | 150.00 | 1,939,035.00 | 180.00 | 2,326,842.00 | 195.00 | 2,520,745.50 | | 0009 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 543.7 | TON | 250.00 | 135,925.00 | 250.00 | 135,925.00 | 250.00 | 135,925.00 | | 0010 | 507-01-00100 | Asphalt Material (CRS-2P Emulsion) | 52,786 | GAL | 4.00 | 211,144.00 | 4.25 | 224,340.50 | 4.50 | 237,537.00 | | 0011 | 507-02-00300 | Aggregate (S3) | 170,281 | SQYD | 1.55 | 263,935.55 | 1.75 | 297,991.75 | 2.25 | 383,132.25 | | 0012 | 509-01-00100 | Milling Asphalt Pavement | 115,282 | SQYD | 3.00 | 345,846.00 | 4.25 | 489,948.50 | 4.50 | 518,769.00 | | 0013 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -4,803 | CUYD | 1.00 | -4,803.00 | 1.00 | -4,803.00 | 1.00 | -4,803.00 | | 0014 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 300 | SQYD | 225.00 | 67,500.00 | 230.00 | 69,000.00 | 260.00 | 78,000.00 | | 0015 | 704-03-00200 | Blocked Out Guard Rail - 31", (6'-3" Post Spacing) | 1,137.5 | LNFT | 35.00 | 39,812.50 | 32.00 | 36,400.00 | 40.00 | 45,500.00 | | 0016 | 704-06-00200 | Guard Rail Bridge Attachments (Single Thrie Beam) | 100 | LNFT | 85.00 | 8,500.00 | 67.00 | 6,700.00 | 115.00 | 11,500.00 | | 0017 | 704-07-00200 | Guard Rail Transitions (Double Thrie Beam) | 200 | LNFT | 135.00 | 27,000.00 | 122.00 | 24,400.00 | 140.00 | 28,000.00 | | 0018 | 704-10-00310 | Guard Rail End Treatment, NCHRP 350 - 31" (TL-3 Flared) | 8 | EACH | 4,000.00 | 32,000.00 | 3,600.00 | 28,800.00 | 5,000.00 | 40,000.00 | | 0019 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 124,000.00 | 124,000.00 | 100,000.00 | 100,000.00 | 100,000.00 | 100,000.00 | | 0020 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 396 | LNFT | 1.00 | 396.00 | 0.40 | 158.40 | 0.75 | 297.00 | | 0021 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 569 | LNFT | 1.00 | 569.00 | 0.80 | 455.20 | 1.00 | 569.00 | | 0022 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 23.57 | MILE | 154.00 | 3,629.78 | 230.00 | 5,421.10 | 300.00 | 7,071.00 | | 0023 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 23.57 | MILE | 600.00 | 14,142.00 | 100.00 | 2,357.00 | 600.00 | 14,142.00 | | 0024 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 47.141 | MILE | 900.00 | 42,426.90 | 100.00 | 4,714.10 | 900.00 | 42,426.90 | | 0025 | 713-05-00220 | Temporary Pavement Legends & Symbols (Arrow - Left Turn) | 8 | EACH | 25.00 | 200.00 | 32.00 | 256.00 | 25.00 | 200.00 | | 0026 | 713-05-00230 | Temporary Pavement Legends & Symbols (Arrow - Right Turn) | 2 | EACH | 25.00 | 50.00 | 32.00 | 64.00 | 25.00 | 50.00 | | 0027 | 713-06-00200 | Temporary Reflectorized Raised Pavement Markers (Tabs) | 2,075 | EACH | 2.00 | 4,150.00 | 2.75 | 5,706.25 | 2.00 | 4,150.00 | | 0028 | 727-01-00100 | Mobilization | 1 | LUMP | 289,000.00 | 289,000.00 | 470,000.00 | 470,000.00 | 390,000.00 | 390,000.00 | | 0029 | 729-16-00300 | Object Marker Assembly (Type 3) | 8 | EACH | 130.00 | 1,040.00 | 92.00 | 736.00 | 150.00 | 1,200.00 | | 0030 | 731-01-00100 | Nonreflectorized Raised Pavement Markers | 1,648 | EACH | 10.00 | 16,480.00 | 11.00 | 18,128.00 | 12.00 | 19,776.00 | | 0031 | 731-02-00100 | Reflectorized Raised Pavement Markers | 2,302 | EACH | 4.00 | 9,208.00 | 5.00 | 11,510.00 | 7.00 | 16,114.00 | | 0032 | 732-01-02040 | Plastic Pavement Striping (8" Width) (Thermoplastic 125 mil) | 396 | LNFT | 4.00 | 1,584.00 | 5.00 | 1,980.00 | 7.00 | 2,772.00 | | 0033 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 569 | LNFT | 12.00 | 6,828.00 | 13.00 | 7,397.00 | 14.00 | 7,966.00 | | 0034 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 15.714 | MILE | 4,500.00 | 70,713.00 | 4,300.00 | 67,570.20 | 6,500.00 | 102,141.00 | | 0035 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 7.857 | MILE | 1,200.00 | 9,428.40 | 1,700.00 | 13,356.90 | 2,000.00 | 15,714.00 | | 0036 | 732-03-02010 | Plastic Pavement Striping (Dotted Line)(4" W)(2' L)(Thermo 90 mil) | 0.134 | MILE | 6,000.00 | 804.00 | 2,000.00 | 268.00 | 6,000.00 | 804.00 | | 0037 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 8 | EACH | 350.00 | 2,800.00 | 300.00 | 2,400.00 | 900.00 | 7,200.00 | | 0038 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 2 | EACH | 350.00 | 700.00 | 300.00 | 600.00 | 900.00 | 1,800.00 | | 0039 | 732-05-00100 | Removal of Existing Markings | 0.091 | MILE | 10,000.00 | 910.00 | 50,000.00 | 4,550.00 | 25,000.00 | 2,275.00 | | 0040 | 739-01-00100 | Hydro-Seeding | 0.25 | ACRE | 12,500.00 | 3,125.00 | 10,500.00 | 2,625.00 | 8,000.00 | 2,000.00 | | 0041 | 740-01-00100 | Construction Layout | 1 | LUMP | 12,000.00 | 12,000.00 | 50,000.00 | 50,000.00 | 30,000.00 | 30,000.00 | | 0042 | NS-500-00220 | Sawing and Sealing Longitudinal Joints in Asphalt Concrete Overlay | 62,226 | LNFT | 2.50 | 155,565.00 | 2.65 | 164,898.90 | 3.25 | 202,234.50 | | 0043 | NS-500-00240 | Sawing and Sealing Transverse Joints in Asphalt Concrete Overlay | 24,890 | LNFT | 2.50 | 62,225.00 | 3.25 | 80,892.50 | 3.50 | 87,115.00 | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 4,049,455.63 | | 4,764,955.80 | | 5,207,015.15 |
|