Proposal:H.013968.6
Parish:Iberville
Routes:LA 404
Description:LA 404: BAYOU AND CANAL BRIDGES
Type Construction:CLEARING AND GRUBBING, TEMPORARY DETOUR BRIDGE, REMOVAL OF BRIDGES, DRAINAGE STRUCTURES, PAVEMENT PATCHING, CLASS II BASE COURSE, LIME TREATMENT, ASPHALT CONCRETE PAVEMENT, PRECAST CONCRETE PILES, CONCRETE SLAB SPAN BRIDGES, AND RELATED WORK.
Estimated Construction Cost:$11,426,362.80
| Rank | License | Bidder | Construction Bid |
| 1 | 44187 | RNGD Infrastructure LLC | $10,464,380.10 |
| 2 | 55950 | Brown Industrial Construction, LLC | $11,454,008.70 |
| 3 | 00009 | Coastal Contractors, LLC | $12,747,975.30 |
| 4 | 56994 | Matt L. Guinn Construction, LLC | $13,086,967.40 |
| 5 | 39462 | JB JAMES CONSTRUCTION LLC | $14,285,186.60 |
| 6 | 55519 | Key, LLC Of Mississippi | $16,948,314.00 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - RNGD Infrastructure LLC | - 2 - Brown Industrial Construction, LLC | - 3 - Coastal Contractors, LLC | - 4 - Matt L. Guinn Construction, LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 201-01-00100 | Clearing and Grubbing | 3.59 | LUMP | 19,000.00 | 19,000.00 | 850,000.00 | 850,000.00 | 250,000.00 | 250,000.00 | 200,000.00 | 200,000.00 | | 0002 | 202-02-03030 | Removal of Pavement Structure | 4,584 | SQYD | 32.00 | 146,688.00 | 11.00 | 50,424.00 | 30.00 | 137,520.00 | 10.00 | 45,840.00 | | 0003 | 202-02-04501 | Removal of Bridge Str. No. 612404050103781, 27.2' x 126.0' Timber Trestle Bridge w/ I-beam Stringers | 3,427 | LUMP | 130,000.00 | 130,000.00 | 150,000.00 | 150,000.00 | 70,000.00 | 70,000.00 | 100,000.00 | 100,000.00 | | 0004 | 202-02-04501 | Removal of Bridge Str. No. 612404050104081, 28.3' x 152.0' Treated Timber Trestle Bridge | 4,302 | LUMP | 150,000.00 | 150,000.00 | 180,000.00 | 180,000.00 | 90,000.00 | 90,000.00 | 120,000.00 | 120,000.00 | | 0005 | 202-02-04501 | Removal of Bridge Str. No. 612404050106431, 28.0' x 38.0' Precast Concrete Slab Bridge | 1,064 | LUMP | 50,000.00 | 50,000.00 | 30,000.00 | 30,000.00 | 15,000.00 | 15,000.00 | 65,000.00 | 65,000.00 | | 0006 | 202-02-04501 | Removal of Bridge Str. No. 612404050107601, 28.5'X57', Lightweight Concrete Precast Slab Bridge | 1,625 | LUMP | 80,000.00 | 80,000.00 | 120,000.00 | 120,000.00 | 40,000.00 | 40,000.00 | 80,000.00 | 80,000.00 | | 0007 | 202-02-14500 | Removal of Guard Rail | 1,580.6 | LNFT | 9.00 | 14,225.40 | 10.00 | 15,806.00 | 11.00 | 17,386.60 | 9.00 | 14,225.40 | | 0008 | 202-02-32120 | Removal of Pipe (Side Drain) 15" RCP | 116 | LNFT | 1.00 | 116.00 | 30.00 | 3,480.00 | 25.00 | 2,900.00 | 40.00 | 4,640.00 | | 0009 | 202-02-32120 | Removal of Pipe (Side Drain) 15" STEEL | 28 | LNFT | 1.00 | 28.00 | 30.00 | 840.00 | 21.00 | 588.00 | 40.00 | 1,120.00 | | 0010 | 202-02-32120 | Removal of Pipe (Side Drain) 18" CMP | 40 | LNFT | 1.00 | 40.00 | 30.00 | 1,200.00 | 15.00 | 600.00 | 40.00 | 1,600.00 | | 0011 | 202-02-32120 | Removal of Pipe (Side Drain) 18" CPP | 82 | LNFT | 1.00 | 82.00 | 30.00 | 2,460.00 | 18.00 | 1,476.00 | 40.00 | 3,280.00 | | 0012 | 202-02-32120 | Removal of Pipe (Side Drain) 24" CMP | 92 | LNFT | 1.00 | 92.00 | 30.00 | 2,760.00 | 16.00 | 1,472.00 | 40.00 | 3,680.00 | | 0013 | 202-02-32120 | Removal of Pipe (Side Drain) 30" STEEL | 26 | LNFT | 1.00 | 26.00 | 30.00 | 780.00 | 35.00 | 910.00 | 40.00 | 1,040.00 | | 0014 | 203-02-00100 | Drainage Excavation | 989 | CUYD | 50.00 | 49,450.00 | 30.00 | 29,670.00 | 60.00 | 59,340.00 | 25.00 | 24,725.00 | | 0015 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 300,000.00 | 300,000.00 | 400,000.00 | 400,000.00 | 150,000.00 | 150,000.00 | 200,000.00 | 200,000.00 | | 0016 | 203-10-00100 | Cleaning Existing Ditches | 106 | LNFT | 26.00 | 2,756.00 | 35.00 | 3,710.00 | 35.00 | 3,710.00 | 15.00 | 1,590.00 | | 0017 | 204-02-00100 | Temporary Hay Bales | 36 | EACH | 33.00 | 1,188.00 | 35.00 | 1,260.00 | 35.00 | 1,260.00 | 30.00 | 1,080.00 | | 0018 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 44 | EACH | 233.00 | 10,252.00 | 150.00 | 6,600.00 | 200.00 | 8,800.00 | 300.00 | 13,200.00 | | 0019 | 204-06-00100 | Temporary Silt Fencing | 10,412 | LNFT | 2.50 | 26,030.00 | 2.50 | 26,030.00 | 2.75 | 28,633.00 | 3.50 | 36,442.00 | | 0020 | 302-02-08080 | Class II Base Course (8" Thick) (Asphalt Concrete Base) | 6,770.6 | SQYD | 83.00 | 561,959.80 | 50.00 | 338,530.00 | 75.00 | 507,795.00 | 112.00 | 758,307.20 | | 0021 | 304-01-00100 | Lime | 23.69 | TON | 900.00 | 21,321.00 | 320.00 | 7,580.80 | 650.00 | 15,398.50 | 600.00 | 14,214.00 | | 0022 | 304-05-00100 | Lime Treatment (Type E) | 1,693 | SQYD | 19.00 | 32,167.00 | 20.00 | 33,860.00 | 14.00 | 23,702.00 | 10.00 | 16,930.00 | | 0023 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 22 | CUYD | 200.00 | 4,400.00 | 150.00 | 3,300.00 | 300.00 | 6,600.00 | 165.00 | 3,630.00 | | 0024 | 402-01-00101 | Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) | 250 | CUYD | 184.00 | 46,000.00 | 160.00 | 40,000.00 | 220.00 | 55,000.00 | 165.00 | 41,250.00 | | 0025 | 402-02-00101 | Traffic Maintenance Surfacing (Hard) | 620 | SQYD | 196.00 | 121,520.00 | 90.00 | 55,800.00 | 95.00 | 58,900.00 | 200.00 | 124,000.00 | | 0026 | 502-01-00100 | Asphalt Concrete | 1,418.8 | TON | 248.00 | 351,862.40 | 150.00 | 212,820.00 | 220.00 | 312,136.00 | 240.00 | 340,512.00 | | 0027 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 345 | TON | 318.00 | 109,710.00 | 200.00 | 69,000.00 | 280.00 | 96,600.00 | 265.00 | 91,425.00 | | 0028 | 510-01-00001 | Pavement Patching 14.5" MINIMUM THICKNESS | 164 | SQYD | 262.00 | 42,968.00 | 220.00 | 36,080.00 | 235.00 | 38,540.00 | 200.00 | 32,800.00 | | 0029 | 701-05-01064 | Side Drain Pipe (24" RCP/RPVCP/CPEPDW) | 862 | LNFT | 125.00 | 107,750.00 | 120.00 | 103,440.00 | 140.00 | 120,680.00 | 120.00 | 103,440.00 | | 0030 | 701-05-02064 | Side Drain Pipe (Erosion) (24" RPVCP/CPEPDW) | 695 | LNFT | 160.00 | 111,200.00 | 120.00 | 83,400.00 | 135.00 | 93,825.00 | 120.00 | 83,400.00 | | 0031 | 702-03-00100 | Catch Basins (CB-01) | 13 | EACH | 4,225.00 | 54,925.00 | 5,000.00 | 65,000.00 | 7,800.00 | 101,400.00 | 5,000.00 | 65,000.00 | | 0032 | 704-03-00200 | Blocked Out Guard Rail - 31", (6'-3" Post Spacing) | 525 | LNFT | 34.00 | 17,850.00 | 28.00 | 14,700.00 | 34.00 | 17,850.00 | 48.00 | 25,200.00 | | 0033 | 704-07-00200 | Guard Rail Transitions (Double Thrie Beam) | 300 | LNFT | 141.00 | 42,300.00 | 115.00 | 34,500.00 | 140.00 | 42,000.00 | 150.00 | 45,000.00 | | 0034 | 704-10-00204 | Guard Rail End Treatment, MASH, (TL-2 Tangent) | 2 | EACH | 3,377.00 | 6,754.00 | 2,700.00 | 5,400.00 | 4,200.00 | 8,400.00 | 4,850.00 | 9,700.00 | | 0035 | 704-10-00205 | Guard Rail End Treatment, MASH, (TL-3 Tangent) | 4 | EACH | 4,315.00 | 17,260.00 | 3,500.00 | 14,000.00 | 3,800.00 | 15,200.00 | 4,850.00 | 19,400.00 | | 0036 | 704-10-00310 | Guard Rail End Treatment, NCHRP 350 - 31" (TL-3 Flared) | 10 | EACH | 3,877.00 | 38,770.00 | 3,100.00 | 31,000.00 | 3,300.00 | 33,000.00 | 4,500.00 | 45,000.00 | | 0037 | 706-02-00200 | Concrete Drive (6" Thick) | 62.2 | SQYD | 130.00 | 8,086.00 | 110.00 | 6,842.00 | 240.00 | 14,928.00 | 125.00 | 7,775.00 | | 0038 | 708-01-00100 | Right-of-Way Monument | 16 | EACH | 750.00 | 12,000.00 | 600.00 | 9,600.00 | 700.00 | 11,200.00 | 700.00 | 11,200.00 | | 0039 | 708-02-00100 | Right-of-Way Monument Witness Post | 16 | EACH | 250.00 | 4,000.00 | 200.00 | 3,200.00 | 250.00 | 4,000.00 | 500.00 | 8,000.00 | | 0040 | 711-03-00400 | Riprap (55 lb) | 2,677.8 | TON | 90.00 | 241,002.00 | 120.00 | 321,336.00 | 110.00 | 294,558.00 | 152.00 | 407,025.60 | | 0041 | 711-04-00100 | Geotextile Fabric | 2,614 | SQYD | 1.80 | 4,705.20 | 3.00 | 7,842.00 | 5.00 | 13,070.00 | 5.00 | 13,070.00 | | 0042 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 44,000.00 | 44,000.00 | 150,000.00 | 150,000.00 | 200,000.00 | 200,000.00 | 180,000.00 | 180,000.00 | | 0043 | 713-04-01020 | Temporary Pavement Markings (Solid Line) (4"Width) (Type 1 Removable) | 3.522 | MILE | 7,600.00 | 26,767.20 | 4,500.00 | 15,849.00 | 8,900.00 | 31,345.80 | 9,500.00 | 33,459.00 | | 0044 | 713-06-00100 | Temporary Reflectorized Raised Pavement Markers | 240 | EACH | 6.80 | 1,632.00 | 4.00 | 960.00 | 9.50 | 2,280.00 | 15.00 | 3,600.00 | | 0045 | 716-01-00100 | Mulch (Vegetative) | 0.2 | TON | 2,150.00 | 430.00 | 7,500.00 | 1,500.00 | 2,500.00 | 500.00 | 12,000.00 | 2,400.00 | | 0046 | 720-01-01000 | Erosion Control System (Slope Protection) (Type A) | 361 | SQYD | 3.00 | 1,083.00 | 2.00 | 722.00 | 2.50 | 902.50 | 7.00 | 2,527.00 | | 0047 | 720-01-02020 | Erosion Control System, Flexible (Channel Liner) (Type D) | 67 | SQYD | 8.00 | 536.00 | 5.00 | 335.00 | 8.00 | 536.00 | 7.00 | 469.00 | | 0048 | 725-01-00100 | Temporary Detour Roads | 3,852 | SQYD | 96.00 | 369,792.00 | 170.00 | 654,840.00 | 185.00 | 712,620.00 | 255.00 | 982,260.00 | | 0049 | 726-01-00100 | Bedding Material | 746.5 | CUYD | 136.00 | 101,524.00 | 125.00 | 93,312.50 | 170.00 | 126,905.00 | 130.00 | 97,045.00 | | 0050 | 727-01-00100 | Mobilization | 1 | LUMP | 1,025,000.00 | 1,025,000.00 | 1,140,000.00 | 1,140,000.00 | 1,100,000.00 | 1,100,000.00 | 1,150,000.00 | 1,150,000.00 | | 0051 | 729-16-00200 | Object Marker Assembly (Type 2) | 4 | EACH | 56.00 | 224.00 | 45.00 | 180.00 | 55.00 | 220.00 | 150.00 | 600.00 | | 0052 | 729-16-00300 | Object Marker Assembly (Type 3) | 12 | EACH | 106.00 | 1,272.00 | 85.00 | 1,020.00 | 100.00 | 1,200.00 | 150.00 | 1,800.00 | | 0053 | 731-02-00100 | Reflectorized Raised Pavement Markers | 66 | EACH | 7.00 | 462.00 | 4.00 | 264.00 | 10.00 | 660.00 | 25.00 | 1,650.00 | | 0054 | 732-01-01000 | Plastic Pavement Striping (4" Width) (Thermoplastic 90 mil) | 7,146 | LNFT | 3.00 | 21,438.00 | 1.50 | 10,719.00 | 1.20 | 8,575.20 | 6.50 | 46,449.00 | | 0055 | 735-01-00100 | Mailboxes | 4 | EACH | 47.00 | 188.00 | 1.00 | 4.00 | 50.00 | 200.00 | 150.00 | 600.00 | | 0056 | 735-03-00100 | Mailbox Supports (Double) | 2 | EACH | 583.00 | 1,166.00 | 300.00 | 600.00 | 300.00 | 600.00 | 150.00 | 300.00 | | 0057 | 739-01-00100 | Hydro-Seeding | 3.59 | ACRE | 3,300.00 | 11,847.00 | 2,800.00 | 10,052.00 | 3,500.00 | 12,565.00 | 4,000.00 | 14,360.00 | | 0058 | 740-01-00100 | Construction Layout | 1 | LUMP | 85,000.00 | 85,000.00 | 210,000.00 | 210,000.00 | 105,000.00 | 105,000.00 | 95,000.00 | 95,000.00 | | 0059 | 804-01-00300 | Precast Concrete Piles (16") | 2,050 | LNFT | 155.00 | 317,750.00 | 140.00 | 287,000.00 | 132.00 | 270,600.00 | 150.00 | 307,500.00 | | 0060 | 804-01-00600 | Precast Concrete Piles (24") | 5,076 | LNFT | 194.00 | 984,744.00 | 190.00 | 964,440.00 | 273.00 | 1,385,748.00 | 275.00 | 1,395,900.00 | | 0061 | 804-10-00300 | Precast Concrete Indicator Piles (16") | 1 | EACH | 26,900.00 | 26,900.00 | 70,000.00 | 70,000.00 | 17,000.00 | 17,000.00 | 85,000.00 | 85,000.00 | | 0062 | 804-10-00600 | Precast Concrete Indicator Piles (24") | 2 | EACH | 24,400.00 | 48,800.00 | 90,000.00 | 180,000.00 | 38,000.00 | 76,000.00 | 125,000.00 | 250,000.00 | | 0063 | 804-14-00100 | Dynamic Monitoring Assistance | 21 | EACH | 4,076.00 | 85,596.00 | 4,500.00 | 94,500.00 | 2,500.00 | 52,500.00 | 1,500.00 | 31,500.00 | | 0064 | 804-17-00100 | Construction Site Survey | 1 | LUMP | 60,000.00 | 60,000.00 | 15,000.00 | 15,000.00 | 55,000.00 | 55,000.00 | 45,000.00 | 45,000.00 | | 0065 | 804-18-00100 | Vibration Monitoring | 25 | DAY | 312.00 | 7,800.00 | 700.00 | 17,500.00 | 1,250.00 | 31,250.00 | 750.00 | 18,750.00 | | 0066 | 805-01-00100 | Class A1 Concrete (Slab Span) | 586.33 | CUYD | 1,800.00 | 1,055,394.00 | 1,500.00 | 879,495.00 | 2,800.00 | 1,641,724.00 | 2,000.00 | 1,172,660.00 | | 0067 | 805-01-00300 | Class A1 Concrete (Bent Cap) | 247.45 | CUYD | 1,950.00 | 482,527.50 | 2,600.00 | 643,370.00 | 3,000.00 | 742,350.00 | 3,150.00 | 779,467.50 | | 0068 | 805-15-02000 | Reinforced Concrete Box Culverts (Precast) (10' x 7') | 156 | LNFT | 2,000.00 | 312,000.00 | 2,200.00 | 343,200.00 | 2,475.00 | 386,100.00 | 2,550.00 | 397,800.00 | | 0069 | 805-17-00100 | Reinforced Concrete Box Culvert Headwall QTY OF STEEL = 1471 LBS, QTY OF CONCRETE = 19.81 CY | 2 | EACH | 39,000.00 | 78,000.00 | 50,000.00 | 100,000.00 | 70,000.00 | 140,000.00 | 88,000.00 | 176,000.00 | | 0070 | 805-18-00100 | Concrete Finish (Class 2 Rubbed Finish) | 4,986 | SQFT | 4.00 | 19,944.00 | 2.50 | 12,465.00 | 2.50 | 12,465.00 | 1.50 | 7,479.00 | | 0071 | 805-18-00200 | Concrete Finish (Class 3 Special Finish) | 4,986 | SQFT | 6.00 | 29,916.00 | 3.00 | 14,958.00 | 3.25 | 16,204.50 | 1.50 | 7,479.00 | | 0072 | 806-01-00100 | Deformed Reinforcing Steel | 165,034 | LB | 1.40 | 231,047.60 | 1.60 | 264,054.40 | 1.50 | 247,551.00 | 1.55 | 255,802.70 | | 0073 | 810-01-00110 | Concrete Bridge Railing (32 inch Height) | 160 | LNFT | 260.00 | 41,600.00 | 260.00 | 41,600.00 | 270.00 | 43,200.00 | 230.00 | 36,800.00 | | 0074 | 810-01-00120 | Concrete Bridge Railing (36 inch Height) | 600 | LNFT | 263.00 | 157,800.00 | 240.00 | 144,000.00 | 270.00 | 162,000.00 | 300.00 | 180,000.00 | | 0075 | 813-01-00100 | Concrete Approach Slabs (Cast-in-Place) | 3,140 | SQFT | 200.00 | 628,000.00 | 130.00 | 408,200.00 | 195.00 | 612,300.00 | 158.00 | 496,120.00 | | 0076 | 814-01-00100 | Elastomeric Bearing Pads (Non-Reinforced) | 455 | SFIN | 300.00 | 136,500.00 | 130.00 | 59,150.00 | 160.00 | 72,800.00 | 225.00 | 102,375.00 | | 0077 | 815-03-00300 | Joint Seal (Poured) | 876 | LNFT | 32.00 | 28,032.00 | 16.00 | 14,016.00 | 50.00 | 43,800.00 | 20.00 | 17,520.00 | | 0078 | 817-01-00100 | Temporary Detour Bridge (Concrete) | 5,334 | SQFT | 200.00 | 1,066,800.00 | 230.00 | 1,226,820.00 | 310.00 | 1,653,540.00 | 285.00 | 1,520,190.00 | | 0079 | NS-500-00240 | Sawing and Sealing Transverse Joints in Asphalt Concrete Overlay | 384 | LNFT | 46.00 | 17,664.00 | 18.00 | 6,912.00 | 17.80 | 6,835.20 | 3.50 | 1,344.00 | | 0080 | NS-500-00260 | Sawcuts in Asphalt Concrete Lifts | 640 | LNFT | 16.00 | 10,240.00 | 4.00 | 2,560.00 | 8.00 | 5,120.00 | 3.50 | 2,240.00 | | 0081 | NS-500-00340 | Saw Cutting Asphalt Concrete Pavement | 1,080 | INLF | 6.00 | 6,480.00 | 2.00 | 2,160.00 | 5.00 | 5,400.00 | 3.50 | 3,780.00 | | | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 10,464,380.10 | | 11,454,008.70 | | 12,747,975.30 | | 13,086,967.40 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 5 - JB JAMES CONSTRUCTION LLC | - 6 - Key, LLC Of Mississippi | | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 201-01-00100 | Clearing and Grubbing | 3.59 | LUMP | 1,000,000.00 | 1,000,000.00 | 255,000.00 | 255,000.00 | | 0002 | 202-02-03030 | Removal of Pavement Structure | 4,584 | SQYD | 20.00 | 91,680.00 | 16.00 | 73,344.00 | | 0003 | 202-02-04501 | Removal of Bridge Str. No. 612404050103781, 27.2' x 126.0' Timber Trestle Bridge w/ I-beam Stringers | 3,427 | LUMP | 300,000.00 | 300,000.00 | 250,000.00 | 250,000.00 | | 0004 | 202-02-04501 | Removal of Bridge Str. No. 612404050104081, 28.3' x 152.0' Treated Timber Trestle Bridge | 4,302 | LUMP | 200,000.00 | 200,000.00 | 250,000.00 | 250,000.00 | | 0005 | 202-02-04501 | Removal of Bridge Str. No. 612404050106431, 28.0' x 38.0' Precast Concrete Slab Bridge | 1,064 | LUMP | 100,000.00 | 100,000.00 | 250,000.00 | 250,000.00 | | 0006 | 202-02-04501 | Removal of Bridge Str. No. 612404050107601, 28.5'X57', Lightweight Concrete Precast Slab Bridge | 1,625 | LUMP | 200,000.00 | 200,000.00 | 250,000.00 | 250,000.00 | | 0007 | 202-02-14500 | Removal of Guard Rail | 1,580.6 | LNFT | 8.00 | 12,644.80 | 8.00 | 12,644.80 | | 0008 | 202-02-32120 | Removal of Pipe (Side Drain) 15" RCP | 116 | LNFT | 25.00 | 2,900.00 | 29.00 | 3,364.00 | | 0009 | 202-02-32120 | Removal of Pipe (Side Drain) 15" STEEL | 28 | LNFT | 25.00 | 700.00 | 33.00 | 924.00 | | 0010 | 202-02-32120 | Removal of Pipe (Side Drain) 18" CMP | 40 | LNFT | 25.00 | 1,000.00 | 30.00 | 1,200.00 | | 0011 | 202-02-32120 | Removal of Pipe (Side Drain) 18" CPP | 82 | LNFT | 25.00 | 2,050.00 | 29.00 | 2,378.00 | | 0012 | 202-02-32120 | Removal of Pipe (Side Drain) 24" CMP | 92 | LNFT | 25.00 | 2,300.00 | 26.00 | 2,392.00 | | 0013 | 202-02-32120 | Removal of Pipe (Side Drain) 30" STEEL | 26 | LNFT | 25.00 | 650.00 | 36.00 | 936.00 | | 0014 | 203-02-00100 | Drainage Excavation | 989 | CUYD | 40.00 | 39,560.00 | 64.00 | 63,296.00 | | 0015 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 245,000.00 | 245,000.00 | 350,000.00 | 350,000.00 | | 0016 | 203-10-00100 | Cleaning Existing Ditches | 106 | LNFT | 130.00 | 13,780.00 | 98.00 | 10,388.00 | | 0017 | 204-02-00100 | Temporary Hay Bales | 36 | EACH | 35.00 | 1,260.00 | 36.00 | 1,296.00 | | 0018 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 44 | EACH | 150.00 | 6,600.00 | 153.00 | 6,732.00 | | 0019 | 204-06-00100 | Temporary Silt Fencing | 10,412 | LNFT | 4.00 | 41,648.00 | 9.00 | 93,708.00 | | 0020 | 302-02-08080 | Class II Base Course (8" Thick) (Asphalt Concrete Base) | 6,770.6 | SQYD | 73.00 | 494,253.80 | 75.00 | 507,795.00 | | 0021 | 304-01-00100 | Lime | 23.69 | TON | 700.00 | 16,583.00 | 510.00 | 12,081.90 | | 0022 | 304-05-00100 | Lime Treatment (Type E) | 1,693 | SQYD | 15.00 | 25,395.00 | 35.70 | 60,440.10 | | 0023 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 22 | CUYD | 300.00 | 6,600.00 | 80.00 | 1,760.00 | | 0024 | 402-01-00101 | Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) | 250 | CUYD | 250.00 | 62,500.00 | 80.00 | 20,000.00 | | 0025 | 402-02-00101 | Traffic Maintenance Surfacing (Hard) | 620 | SQYD | 100.00 | 62,000.00 | 133.00 | 82,460.00 | | 0026 | 502-01-00100 | Asphalt Concrete | 1,418.8 | TON | 150.00 | 212,820.00 | 190.00 | 269,572.00 | | 0027 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 345 | TON | 200.00 | 69,000.00 | 359.00 | 123,855.00 | | 0028 | 510-01-00001 | Pavement Patching 14.5" MINIMUM THICKNESS | 164 | SQYD | 360.00 | 59,040.00 | 219.00 | 35,916.00 | | 0029 | 701-05-01064 | Side Drain Pipe (24" RCP/RPVCP/CPEPDW) | 862 | LNFT | 250.00 | 215,500.00 | 160.00 | 137,920.00 | | 0030 | 701-05-02064 | Side Drain Pipe (Erosion) (24" RPVCP/CPEPDW) | 695 | LNFT | 250.00 | 173,750.00 | 165.00 | 114,675.00 | | 0031 | 702-03-00100 | Catch Basins (CB-01) | 13 | EACH | 5,000.00 | 65,000.00 | 10,550.00 | 137,150.00 | | 0032 | 704-03-00200 | Blocked Out Guard Rail - 31", (6'-3" Post Spacing) | 525 | LNFT | 27.00 | 14,175.00 | 28.30 | 14,857.50 | | 0033 | 704-07-00200 | Guard Rail Transitions (Double Thrie Beam) | 300 | LNFT | 112.00 | 33,600.00 | 116.00 | 34,800.00 | | 0034 | 704-10-00204 | Guard Rail End Treatment, MASH, (TL-2 Tangent) | 2 | EACH | 3,400.00 | 6,800.00 | 3,520.00 | 7,040.00 | | 0035 | 704-10-00205 | Guard Rail End Treatment, MASH, (TL-3 Tangent) | 4 | EACH | 3,000.00 | 12,000.00 | 3,160.00 | 12,640.00 | | 0036 | 704-10-00310 | Guard Rail End Treatment, NCHRP 350 - 31" (TL-3 Flared) | 10 | EACH | 2,600.00 | 26,000.00 | 2,755.00 | 27,550.00 | | 0037 | 706-02-00200 | Concrete Drive (6" Thick) | 62.2 | SQYD | 200.00 | 12,440.00 | 255.00 | 15,861.00 | | 0038 | 708-01-00100 | Right-of-Way Monument | 16 | EACH | 600.00 | 9,600.00 | 1,310.00 | 20,960.00 | | 0039 | 708-02-00100 | Right-of-Way Monument Witness Post | 16 | EACH | 200.00 | 3,200.00 | 905.00 | 14,480.00 | | 0040 | 711-03-00400 | Riprap (55 lb) | 2,677.8 | TON | 160.00 | 428,448.00 | 132.00 | 353,469.60 | | 0041 | 711-04-00100 | Geotextile Fabric | 2,614 | SQYD | 3.00 | 7,842.00 | 5.00 | 13,070.00 | | 0042 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 143,000.00 | 143,000.00 | 350,000.00 | 350,000.00 | | 0043 | 713-04-01020 | Temporary Pavement Markings (Solid Line) (4"Width) (Type 1 Removable) | 3.522 | MILE | 7,500.00 | 26,415.00 | 7,650.00 | 26,943.30 | | 0044 | 713-06-00100 | Temporary Reflectorized Raised Pavement Markers | 240 | EACH | 8.00 | 1,920.00 | 8.00 | 1,920.00 | | 0045 | 716-01-00100 | Mulch (Vegetative) | 0.2 | TON | 7,500.00 | 1,500.00 | 86,000.00 | 17,200.00 | | 0046 | 720-01-01000 | Erosion Control System (Slope Protection) (Type A) | 361 | SQYD | 2.00 | 722.00 | 2.05 | 740.05 | | 0047 | 720-01-02020 | Erosion Control System, Flexible (Channel Liner) (Type D) | 67 | SQYD | 5.00 | 335.00 | 5.00 | 335.00 | | 0048 | 725-01-00100 | Temporary Detour Roads | 3,852 | SQYD | 200.00 | 770,400.00 | 225.00 | 866,700.00 | | 0049 | 726-01-00100 | Bedding Material | 746.5 | CUYD | 150.00 | 111,975.00 | 172.00 | 128,398.00 | | 0050 | 727-01-00100 | Mobilization | 1 | LUMP | 1,400,000.00 | 1,400,000.00 | 1,655,000.00 | 1,655,000.00 | | 0051 | 729-16-00200 | Object Marker Assembly (Type 2) | 4 | EACH | 45.00 | 180.00 | 45.00 | 180.00 | | 0052 | 729-16-00300 | Object Marker Assembly (Type 3) | 12 | EACH | 85.00 | 1,020.00 | 90.00 | 1,080.00 | | 0053 | 731-02-00100 | Reflectorized Raised Pavement Markers | 66 | EACH | 8.00 | 528.00 | 8.00 | 528.00 | | 0054 | 732-01-01000 | Plastic Pavement Striping (4" Width) (Thermoplastic 90 mil) | 7,146 | LNFT | 1.00 | 7,146.00 | 1.05 | 7,503.30 | | 0055 | 735-01-00100 | Mailboxes | 4 | EACH | 20.00 | 80.00 | 179.00 | 716.00 | | 0056 | 735-03-00100 | Mailbox Supports (Double) | 2 | EACH | 250.00 | 500.00 | 357.00 | 714.00 | | 0057 | 739-01-00100 | Hydro-Seeding | 3.59 | ACRE | 2,800.00 | 10,052.00 | 2,855.00 | 10,249.45 | | 0058 | 740-01-00100 | Construction Layout | 1 | LUMP | 140,000.00 | 140,000.00 | 350,000.00 | 350,000.00 | | 0059 | 804-01-00300 | Precast Concrete Piles (16") | 2,050 | LNFT | 130.00 | 266,500.00 | 125.00 | 256,250.00 | | 0060 | 804-01-00600 | Precast Concrete Piles (24") | 5,076 | LNFT | 200.00 | 1,015,200.00 | 200.00 | 1,015,200.00 | | 0061 | 804-10-00300 | Precast Concrete Indicator Piles (16") | 1 | EACH | 250,000.00 | 250,000.00 | 32,000.00 | 32,000.00 | | 0062 | 804-10-00600 | Precast Concrete Indicator Piles (24") | 2 | EACH | 300,000.00 | 600,000.00 | 44,740.00 | 89,480.00 | | 0063 | 804-14-00100 | Dynamic Monitoring Assistance | 21 | EACH | 1,000.00 | 21,000.00 | 4,625.00 | 97,125.00 | | 0064 | 804-17-00100 | Construction Site Survey | 1 | LUMP | 100,000.00 | 100,000.00 | 200,000.00 | 200,000.00 | | 0065 | 804-18-00100 | Vibration Monitoring | 25 | DAY | 1,000.00 | 25,000.00 | 1,530.00 | 38,250.00 | | 0066 | 805-01-00100 | Class A1 Concrete (Slab Span) | 586.33 | CUYD | 2,500.00 | 1,465,825.00 | 1,750.00 | 1,026,077.50 | | 0067 | 805-01-00300 | Class A1 Concrete (Bent Cap) | 247.45 | CUYD | 3,500.00 | 866,075.00 | 1,750.00 | 433,037.50 | | 0068 | 805-15-02000 | Reinforced Concrete Box Culverts (Precast) (10' x 7') | 156 | LNFT | 1,800.00 | 280,800.00 | 2,500.00 | 390,000.00 | | 0069 | 805-17-00100 | Reinforced Concrete Box Culvert Headwall QTY OF STEEL = 1471 LBS, QTY OF CONCRETE = 19.81 CY | 2 | EACH | 35,000.00 | 70,000.00 | 60,000.00 | 120,000.00 | | 0070 | 805-18-00100 | Concrete Finish (Class 2 Rubbed Finish) | 4,986 | SQFT | 2.00 | 9,972.00 | 4.00 | 19,944.00 | | 0071 | 805-18-00200 | Concrete Finish (Class 3 Special Finish) | 4,986 | SQFT | 4.00 | 19,944.00 | 4.00 | 19,944.00 | | 0072 | 806-01-00100 | Deformed Reinforcing Steel | 165,034 | LB | 2.00 | 330,068.00 | 3.00 | 495,102.00 | | 0073 | 810-01-00110 | Concrete Bridge Railing (32 inch Height) | 160 | LNFT | 160.00 | 25,600.00 | 305.00 | 48,800.00 | | 0074 | 810-01-00120 | Concrete Bridge Railing (36 inch Height) | 600 | LNFT | 170.00 | 102,000.00 | 285.00 | 171,000.00 | | 0075 | 813-01-00100 | Concrete Approach Slabs (Cast-in-Place) | 3,140 | SQFT | 160.00 | 502,400.00 | 215.00 | 675,100.00 | | 0076 | 814-01-00100 | Elastomeric Bearing Pads (Non-Reinforced) | 455 | SFIN | 150.00 | 68,250.00 | 415.00 | 188,825.00 | | 0077 | 815-03-00300 | Joint Seal (Poured) | 876 | LNFT | 30.00 | 26,280.00 | 46.00 | 40,296.00 | | 0078 | 817-01-00100 | Temporary Detour Bridge (Concrete) | 5,334 | SQFT | 250.00 | 1,333,500.00 | 800.00 | 4,267,200.00 | | 0079 | NS-500-00240 | Sawing and Sealing Transverse Joints in Asphalt Concrete Overlay | 384 | LNFT | 5.00 | 1,920.00 | 5.00 | 1,920.00 | | 0080 | NS-500-00260 | Sawcuts in Asphalt Concrete Lifts | 640 | LNFT | 5.00 | 3,200.00 | 5.00 | 3,200.00 | | 0081 | NS-500-00340 | Saw Cutting Asphalt Concrete Pavement | 1,080 | INLF | 7.00 | 7,560.00 | 5.00 | 5,400.00 | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 14,285,186.60 | | 16,948,314.00 |
|