Proposal:H.010359.6
Parish:Natchitoches
Routes:LA 9
Description:LA 9: US 71 - LA 156
Type Construction:DRAINAGE STRUCTURES, MILLING ASPHALT CONCRETE, PAVEMENT PATCHING, ASPHALT CONCRETE OVERLAY, AND RELATED WORK.
Estimated Construction Cost:$7,308,177.00
| Rank | License | Bidder | Construction Bid |
| 1 | 08584 | Madden Contracting Co., LLC | $7,333,269.40 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Madden Contracting Co., LLC | | Unit Price | Total Amount | | 0001 | 202-02-14500 | Removal of Guard Rail | 747 | LNFT | 14.00 | 10,458.00 | | 0002 | 202-02-32100 | Removal of Pipe (Cross Drain) (18" RCP) | 4 | LNFT | 25.00 | 100.00 | | 0003 | 202-02-32100 | Removal of Pipe (Cross Drain) (24" RCP) | 38 | LNFT | 25.00 | 950.00 | | 0004 | 203-07-00100 | Borrow (Vehicular Measurement) | 600 | CUYD | 125.00 | 75,000.00 | | 0005 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 265 | CUYD | 63.00 | 16,695.00 | | 0006 | 502-01-00100 | Asphalt Concrete | 21,017.8 | TON | 147.85 | 3,107,481.73 | | 0007 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 1,113.1 | TON | 108.05 | 120,270.46 | | 0008 | 509-01-00100 | Milling Asphalt Pavement | 104,926 | SQYD | 4.23 | 443,836.98 | | 0009 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -4,867 | CUYD | 0.10 | -486.70 | | 0010 | 510-01-00100 | Pavement Patching (6" Minimum Thickness) | 76 | SQYD | 83.95 | 6,380.20 | | 0011 | 510-01-00260 | Pavement Patching (16 inch Minimum Thickness) | 12,690 | SQYD | 174.50 | 2,214,405.00 | | 0012 | 701-01-01003 | Cross Drain Pipe (24" RCP/RPVCP/CPEPDW) | 40 | LNFT | 398.00 | 15,920.00 | | 0013 | 701-10-01040 | Reinforced Concrete Pipe (Extension) (18") | 8 | LNFT | 295.00 | 2,360.00 | | 0014 | 701-15-00100 | Concrete Collar | 1 | EACH | 2,450.00 | 2,450.00 | | 0015 | 701-17-00100 | Trench Excavation Safety Protection (Depth >5 feet) | 42 | LNFT | 5.00 | 210.00 | | 0016 | 704-03-00200 | Blocked Out Guard Rail - 31", (6'-3" Post Spacing) | 262.5 | LNFT | 34.00 | 8,925.00 | | 0017 | 704-07-00200 | Guard Rail Transitions (Double Thrie Beam) | 100 | LNFT | 134.00 | 13,400.00 | | 0018 | 704-10-00205 | Guard Rail End Treatment, MASH, (TL-3 Tangent) | 4 | EACH | 4,150.00 | 16,600.00 | | 0019 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 431,500.00 | 431,500.00 | | 0020 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 17.767 | MILE | 300.00 | 5,330.10 | | 0021 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 4.645 | MILE | 500.00 | 2,322.50 | | 0022 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 68.014 | MILE | 900.00 | 61,212.60 | | 0023 | 724-02-00100 | Rumble Strips (Shoulder/Edge) | 11.814 | MILE | 1,000.00 | 11,814.00 | | 0024 | 726-01-00100 | Bedding Material | 10.8 | CUYD | 158.00 | 1,706.40 | | 0025 | 727-01-00100 | Mobilization | 1 | LUMP | 431,500.00 | 431,500.00 | | 0026 | 729-16-00200 | Object Marker Assembly (Type 2) | 3 | EACH | 100.00 | 300.00 | | 0027 | 729-16-00300 | Object Marker Assembly (Type 3) | 4 | EACH | 130.00 | 520.00 | | 0028 | 731-02-00100 | Reflectorized Raised Pavement Markers | 3,896 | EACH | 7.00 | 27,272.00 | | 0029 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 880 | LNFT | 3.00 | 2,640.00 | | 0030 | 732-01-01080 | Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) | 2,625 | LNFT | 12.00 | 31,500.00 | | 0031 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 20.867 | MILE | 5,500.00 | 114,768.50 | | 0032 | 732-02-03000 | Plastic Pavement Striping (Solid Line) (4" Width) (Preformed Tape) (Retroreflectivity Level I) | 3.583 | MILE | 15,375.00 | 55,088.63 | | 0033 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 1.548 | MILE | 2,500.00 | 3,870.00 | | 0034 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 6 | EACH | 300.00 | 1,800.00 | | 0035 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 4 | EACH | 300.00 | 1,200.00 | | 0036 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 4 | EACH | 350.00 | 1,400.00 | | 0037 | 732-05-00100 | Removal of Existing Markings | 0.896 | MILE | 11,500.00 | 10,304.00 | | 0038 | 735-01-00100 | Mailboxes | 66 | EACH | 20.00 | 1,320.00 | | 0039 | 735-02-00100 | Mailbox Supports (Single) | 60 | EACH | 290.00 | 17,400.00 | | 0040 | 735-03-00100 | Mailbox Supports (Double) | 3 | EACH | 390.00 | 1,170.00 | | 0041 | 739-01-00100 | Hydro-Seeding | 3.3 | ACRE | 3,750.00 | 12,375.00 | | 0042 | 740-01-00100 | Construction Layout | 1 | LUMP | 50,000.00 | 50,000.00 | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 7,333,269.40 |
|