Proposal:H.010155.6
Parish:Iberia
Routes:US 90
Description:US 90 RAILROAD OVERPASS SE OF LA 85
Type Construction:GRADING, CLEARING AND GRUBBING, REMOVAL OF ASPHALT PAVEMENT AND BASE, SUBGRADE TREATMENT, CLASS II BASE COURSE, DRAINAGE STRUCTURES, ASPHALT CONCRETE PAVEMENT, PORTLAND CEMENT CONCRETE, TEMPORARY DETOUR ROADS, MECHANICALLY STABILIZED EARTH WALL CONCRETE PANELS, PRECAST CONCRETE PILES, PRECAST-PRESTRESSED CONCRETE GIRDERS, CONCRETE GIRDER SPAN BRIDGE, SIGNAGE, AND RELATED WORK.
Estimated Construction Cost:$55,097,129.67
Maximum Number of Days Allowed for Construction:1275
Calculated Daily User Cost:$12,000.00
| Rank | License | Bidder | Construction Bid | Bidder's Proposed Contract Time | Total Bid |
| 1 | 39462 | JB JAMES CONSTRUCTION LLC | $41,423,840.37 | 720.00 | $50,063,840.37 |
| 2 | 12312 | GILCHRIST CONSTRUCTION COMPANY, LLC | $45,867,292.06 | 700.00 | $54,267,292.06 |
| 3 | 34567 | James Construction Group LLC | $46,702,783.20 | 808.00 | $56,398,783.20 |
| 4 | 02179 | Boh Bros. Construction Co., LLC. | $51,386,249.99 | 800.00 | $60,986,249.99 |
| 5 | 55505 | MERRICK, LLC | $50,323,411.37 | 1000.00 | $62,323,411.37 |
| 6 | 00060 | Orion Industrial Construction LLC | $65,255,520.85 | 1112.00 | $78,599,520.85 |
| 7 | 55519 | Key, LLC Of Mississippi | $76,570,058.68 | 1275.00 | $91,870,058.68 |
| 39613 | BAKER PILE DRIVING AND SITE WORK LLC | IRREGULAR | 1369.00 | IRREGULAR |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - JB JAMES CONSTRUCTION LLC | - 2 - GILCHRIST CONSTRUCTION COMPANY, LLC | - 3 - James Construction Group LLC | - 4 - Boh Bros. Construction Co., LLC. | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 109-01-10000 | Time Related Overhead | 1 | LUMP | 2,000,000.00 | 2,000,000.00 | 3,700,000.00 | 3,700,000.00 | 4,219,696.00 | 4,219,696.00 | 3,000,000.00 | 3,000,000.00 | | 0002 | 201-01-00100 | Clearing and Grubbing | 13.3 | LUMP | 1,600,000.00 | 1,600,000.00 | 250,000.00 | 250,000.00 | 100,000.00 | 100,000.00 | 25,000.00 | 25,000.00 | | 0003 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 198,000.00 | 198,000.00 | 35,000.00 | 35,000.00 | 40,000.00 | 40,000.00 | 14,000.00 | 14,000.00 | | 0004 | 202-02-00030 | Removal of Temporary Tape | 58,360 | LNFT | 1.00 | 58,360.00 | 1.00 | 58,360.00 | 1.00 | 58,360.00 | 1.15 | 67,114.00 | | 0005 | 202-02-02020 | Removal of Asphalt Pavement | 17,266.1 | SQYD | 9.00 | 155,394.90 | 7.75 | 133,812.28 | 8.40 | 145,035.24 | 8.00 | 138,128.80 | | 0006 | 202-02-03000 | Removal of Base – Soil Cement, Asphalt, or BCS | 38,766.1 | SQYD | 8.00 | 310,128.80 | 5.75 | 222,905.08 | 3.50 | 135,681.35 | 10.00 | 387,661.00 | | 0007 | 202-02-14500 | Removal of Guard Rail | 216 | LNFT | 17.00 | 3,672.00 | 32.00 | 6,912.00 | 85.00 | 18,360.00 | 15.00 | 3,240.00 | | 0008 | 202-02-32180 | Removal of Pipe Headwalls | 3 | EACH | 3,000.00 | 9,000.00 | 2,600.00 | 7,800.00 | 2,530.00 | 7,590.00 | 700.00 | 2,100.00 | | 0009 | 202-02-32500 | Removal of Portland Cement Concrete Pavement | 21,500 | SQYD | 10.00 | 215,000.00 | 11.00 | 236,500.00 | 14.00 | 301,000.00 | 13.00 | 279,500.00 | | 0010 | 202-02-38220 | Removal of Sign Supports | 2 | EACH | 25.00 | 50.00 | 800.00 | 1,600.00 | 25.00 | 50.00 | 800.00 | 1,600.00 | | 0011 | 202-02-38300 | Removal of Sign and U-Channel Post | 43 | EACH | 43.00 | 1,849.00 | 16.00 | 688.00 | 50.00 | 2,150.00 | 16.00 | 688.00 | | 0012 | 202-02-38360 | Removal of Sign Faces | 2 | EACH | 25.00 | 50.00 | 210.00 | 420.00 | 25.00 | 50.00 | 220.00 | 440.00 | | 0013 | 202-02-40100 | Removal of Traffic Signal Equipment | 1 | LUMP | 10,000.00 | 10,000.00 | 18,000.00 | 18,000.00 | 10,000.00 | 10,000.00 | 21,000.00 | 21,000.00 | | 0014 | 203-01-00100 | General Excavation | 13,133 | CUYD | 20.00 | 262,660.00 | 19.50 | 256,093.50 | 15.00 | 196,995.00 | 18.00 | 236,394.00 | | 0015 | 203-03-00100 | Embankment | 22,504 | CUYD | 55.00 | 1,237,720.00 | 49.00 | 1,102,696.00 | 43.00 | 967,672.00 | 35.00 | 787,640.00 | | 0016 | 203-04-00200 | Nonplastic Embankment (Sand) | 3,152 | CUYD | 100.00 | 315,200.00 | 62.50 | 197,000.00 | 240.00 | 756,480.00 | 43.00 | 135,536.00 | | 0017 | 203-11-00100 | Settlement Plate Installation and Monitoring | 12 | EACH | 2,000.00 | 24,000.00 | 2,100.00 | 25,200.00 | 2,200.00 | 26,400.00 | 1,300.00 | 15,600.00 | | 0018 | 204-04-00100 | Temporary Sediment Basins | 8 | EACH | 1,500.00 | 12,000.00 | 6,000.00 | 48,000.00 | 470.00 | 3,760.00 | 275.00 | 2,200.00 | | 0019 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 52 | EACH | 150.00 | 7,800.00 | 180.00 | 9,360.00 | 256.00 | 13,312.00 | 165.00 | 8,580.00 | | 0020 | 204-06-00100 | Temporary Silt Fencing | 9,390 | LNFT | 6.00 | 56,340.00 | 2.50 | 23,475.00 | 4.00 | 37,560.00 | 2.15 | 20,188.50 | | 0021 | 302-02-08010 | Class II Base Course (8" Thick) (Soil Cement) | 13,636.3 | SQYD | 26.00 | 354,543.80 | 33.00 | 449,997.90 | 21.00 | 286,362.30 | 23.00 | 313,634.90 | | 0022 | 302-02-08070 | Class II Base Course (8" Thick) (Crushed Stone or Recycled Portland Cement Concrete) | 3,097.8 | SQYD | 36.00 | 111,520.80 | 67.00 | 207,552.60 | 42.50 | 131,656.50 | 48.00 | 148,694.40 | | 0023 | 302-02-10010 | Class II Base Course (10" Thick) (Soil Cement) | 5,933.5 | SQYD | 30.00 | 178,005.00 | 33.00 | 195,805.50 | 31.70 | 188,091.95 | 28.00 | 166,138.00 | | 0024 | 305-01-03020 | Subgrade Layer (10" Thick) (Treated) | 19,574 | SQYD | 14.00 | 274,036.00 | 25.00 | 489,350.00 | 23.00 | 450,202.00 | 28.00 | 548,072.00 | | 0025 | 502-01-00100 | Asphalt Concrete | 3,357 | TON | 160.00 | 537,120.00 | 190.00 | 637,830.00 | 160.00 | 537,120.00 | 330.00 | 1,107,810.00 | | 0026 | 601-01-00700 | Portland Cement Concrete Pavement (11" Thick) | 10,060.6 | SQYD | 130.00 | 1,307,878.00 | 148.00 | 1,488,968.80 | 172.00 | 1,730,423.20 | 190.00 | 1,911,514.00 | | 0027 | 601-03-01300 | Portland Cement Concrete Shoulder (11" Thick) | 6,580.9 | SQYD | 130.00 | 855,517.00 | 148.00 | 973,973.20 | 125.00 | 822,612.50 | 140.00 | 921,326.00 | | 0028 | 601-04-00100 | Portland Cement Concrete Pavement Coring | 25 | EACH | 125.00 | 3,125.00 | 700.00 | 17,500.00 | 185.00 | 4,625.00 | 200.00 | 5,000.00 | | 0029 | 701-01-01001 | Cross Drain Pipe (24" RCP) | 316 | LNFT | 200.00 | 63,200.00 | 200.00 | 63,200.00 | 243.00 | 76,788.00 | 250.00 | 79,000.00 | | 0030 | 701-03-01110 | Storm Drain Pipe (24" RCP) | 36 | LNFT | 260.00 | 9,360.00 | 210.00 | 7,560.00 | 243.00 | 8,748.00 | 250.00 | 9,000.00 | | 0031 | 702-03-00100 | Catch Basins (CB-01) | 6 | EACH | 12,000.00 | 72,000.00 | 6,000.00 | 36,000.00 | 10,100.00 | 60,600.00 | 7,000.00 | 42,000.00 | | 0032 | 704-03-00200 | Blocked Out Guard Rail - 31", (6'-3" Post Spacing) | 1,687.5 | LNFT | 29.50 | 49,781.25 | 30.00 | 50,625.00 | 29.50 | 49,781.25 | 35.00 | 59,062.50 | | 0033 | 704-05-00300 | Guard Rail Anchor Sections - 31", (Trailing End) | 19.8 | LNFT | 165.00 | 3,267.00 | 170.00 | 3,366.00 | 165.00 | 3,267.00 | 190.00 | 3,762.00 | | 0034 | 704-07-00200 | Guard Rail Transitions (Double Thrie Beam) | 150 | LNFT | 116.50 | 17,475.00 | 118.00 | 17,700.00 | 116.50 | 17,475.00 | 130.00 | 19,500.00 | | 0035 | 704-10-00205 | Guard Rail End Treatment, MASH, (TL-3 Tangent) | 4 | EACH | 3,600.00 | 14,400.00 | 3,800.00 | 15,200.00 | 3,600.00 | 14,400.00 | 4,200.00 | 16,800.00 | | 0036 | 705-06-00400 | Chain Link Fence (7 Foot Height) | 320 | LNFT | 180.00 | 57,600.00 | 190.00 | 60,800.00 | 180.00 | 57,600.00 | 135.00 | 43,200.00 | | 0037 | 706-03-00100 | Incidental Concrete Paving (4" Thick) | 625.1 | SQYD | 79.65 | 49,789.22 | 225.00 | 140,647.50 | 125.00 | 78,137.50 | 140.00 | 87,514.00 | | 0038 | 712-01-00100 | Concrete Cast-in-Place Revetment (4" Thick) | 542 | SQYD | 120.00 | 65,040.00 | 275.00 | 149,050.00 | 290.00 | 157,180.00 | 150.00 | 81,300.00 | | 0039 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 550,000.00 | 550,000.00 | 135,000.00 | 135,000.00 | 260,000.00 | 260,000.00 | 300,000.00 | 300,000.00 | | 0040 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 1,060 | LNFT | 0.25 | 265.00 | 0.27 | 286.20 | 0.25 | 265.00 | 0.25 | 265.00 | | 0041 | 713-03-01020 | Temporary Pavement Markings (Broken Line) (4" W) (4' L) (Type 1 Removable) | 0.084 | MILE | 3,800.00 | 319.20 | 5,000.00 | 420.00 | 3,810.00 | 320.04 | 4,000.00 | 336.00 | | 0042 | 713-04-01020 | Temporary Pavement Markings (Solid Line) (4"Width) (Type 1 Removable) | 11.053 | MILE | 6,000.00 | 66,318.00 | 6,200.00 | 68,528.60 | 6,000.00 | 66,318.00 | 6,500.00 | 71,844.50 | | 0043 | 713-05-00400 | Temporary Pavement Legends & Symbols (RR Crossing) | 2 | EACH | 50.00 | 100.00 | 60.00 | 120.00 | 50.00 | 100.00 | 55.00 | 110.00 | | 0044 | 713-06-00100 | Temporary Reflectorized Raised Pavement Markers | 1,622 | EACH | 4.00 | 6,488.00 | 5.00 | 8,110.00 | 4.00 | 6,488.00 | 4.50 | 7,299.00 | | 0045 | 713-07-00100 | Temporary Precast Concrete Barrier (Contractor Furnished) | 339 | EACH | 700.00 | 237,300.00 | 650.00 | 220,350.00 | 900.00 | 305,100.00 | 2,800.00 | 949,200.00 | | 0046 | 713-10-00100 | Temporary Precast Concrete Barrier Movement | 359 | EACH | 100.00 | 35,900.00 | 200.00 | 71,800.00 | 200.00 | 71,800.00 | 125.00 | 44,875.00 | | 0047 | 713-11-00100 | Portable Changeable Message Signs | 2 | EACH | 25,000.00 | 50,000.00 | 25,000.00 | 50,000.00 | 21,000.00 | 42,000.00 | 21,000.00 | 42,000.00 | | 0048 | 720-01-01000 | Erosion Control System (Slope Protection) (Type A) | 244 | SQYD | 3.00 | 732.00 | 3.20 | 780.80 | 4.00 | 976.00 | 3.00 | 732.00 | | 0049 | 720-01-02000 | Erosion Control System, Flexible (Channel Liner) (Type C) | 333 | SQYD | 3.00 | 999.00 | 3.20 | 1,065.60 | 3.00 | 999.00 | 3.00 | 999.00 | | 0050 | 720-01-02020 | Erosion Control System, Flexible (Channel Liner) (Type D) | 162 | SQYD | 3.00 | 486.00 | 3.20 | 518.40 | 3.00 | 486.00 | 3.00 | 486.00 | | 0051 | 722-02-00100 | Project Site Laboratory (Equipped) | 1 | EACH | 60,000.00 | 60,000.00 | 40,000.00 | 40,000.00 | 83,100.00 | 83,100.00 | 30,000.00 | 30,000.00 | | 0052 | 724-02-00100 | Rumble Strips (Shoulder/Edge) | 1.43 | MILE | 280.00 | 400.40 | 1,100.00 | 1,573.00 | 2,104.00 | 3,008.72 | 3,700.00 | 5,291.00 | | 0053 | 725-01-00100 | Temporary Detour Roads | 3,289.7 | SQYD | 220.00 | 723,734.00 | 210.00 | 690,837.00 | 215.00 | 707,285.50 | 300.00 | 986,910.00 | | 0054 | 726-01-00100 | Bedding Material | 83.6 | CUYD | 140.00 | 11,704.00 | 140.00 | 11,704.00 | 180.84 | 15,118.22 | 160.00 | 13,376.00 | | 0055 | 727-01-00100 | Mobilization | 1 | LUMP | 4,100,000.00 | 4,100,000.00 | 3,725,000.00 | 3,725,000.00 | 4,700,000.00 | 4,700,000.00 | 5,000,000.00 | 5,000,000.00 | | 0056 | 729-01-00100 | Sign (Type A) | 53.5 | SQFT | 25.00 | 1,337.50 | 37.00 | 1,979.50 | 25.00 | 1,337.50 | 38.00 | 2,033.00 | | 0057 | 729-04-00100 | Sign (Type D) | 77 | SQFT | 31.00 | 2,387.00 | 48.00 | 3,696.00 | 31.00 | 2,387.00 | 50.00 | 3,850.00 | | 0058 | 729-05-00100 | Sign (Type E) | 27.5 | SQFT | 45.00 | 1,237.50 | 45.00 | 1,237.50 | 45.00 | 1,237.50 | 48.00 | 1,320.00 | | 0059 | 729-08-00200 | Mounting (3 1/2" Size Post) | 1 | EACH | 2,250.00 | 2,250.00 | 2,300.00 | 2,300.00 | 2,250.00 | 2,250.00 | 2,400.00 | 2,400.00 | | 0060 | 729-08-00310 | Mounting (5" Size Post)(Structure Mount) | 2 | EACH | 8,000.00 | 16,000.00 | 6,200.00 | 12,400.00 | 8,000.00 | 16,000.00 | 6,500.00 | 13,000.00 | | 0061 | 729-08-00700 | Mounting (W8 x 18 Size Post) | 2 | EACH | 2,500.00 | 5,000.00 | 10,000.00 | 20,000.00 | 2,500.00 | 5,000.00 | 10,000.00 | 20,000.00 | | 0062 | 729-16-00300 | Object Marker Assembly (Type 3) | 4 | EACH | 85.00 | 340.00 | 90.00 | 360.00 | 85.00 | 340.00 | 90.00 | 360.00 | | 0063 | 729-18-00100 | Milepost Assembly (Structure Mounted) | 2 | EACH | 300.00 | 600.00 | 310.00 | 620.00 | 250.00 | 500.00 | 325.00 | 650.00 | | 0064 | 731-02-00100 | Reflectorized Raised Pavement Markers | 813 | EACH | 4.00 | 3,252.00 | 5.00 | 4,065.00 | 4.00 | 3,252.00 | 4.50 | 3,658.50 | | 0065 | 731-03-00100 | Removal of Raised Pavement Markers | 2.659 | MILE | 100.00 | 265.90 | 105.00 | 279.20 | 100.00 | 265.90 | 110.00 | 292.49 | | 0066 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 1,466 | LNFT | 3.00 | 4,398.00 | 3.00 | 4,398.00 | 2.75 | 4,031.50 | 3.00 | 4,398.00 | | 0067 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 372 | LNFT | 14.00 | 5,208.00 | 15.00 | 5,580.00 | 14.00 | 5,208.00 | 15.00 | 5,580.00 | | 0068 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 5.318 | MILE | 4,000.00 | 21,272.00 | 4,100.00 | 21,803.80 | 3,994.00 | 21,240.09 | 4,200.00 | 22,335.60 | | 0069 | 732-03-02040 | Plastic Pavement Striping (Dotted Line)(8" W)(3' L)(Thermo 90 mil) | 0.136 | MILE | 2,400.00 | 326.40 | 2,400.00 | 326.40 | 2,574.00 | 350.06 | 2,500.00 | 340.00 | | 0070 | 732-03-02102 | Plastic Pav't Striping (Broken) (4" W) (Preformed Tape Retroreflectivity I or Thermo 90 mil)(Black and White Contrast) | 2.659 | MILE | 3,500.00 | 9,306.50 | 3,500.00 | 9,306.50 | 3,502.00 | 9,311.82 | 3,600.00 | 9,572.40 | | 0071 | 732-05-00100 | Removal of Existing Markings | 2.659 | MILE | 3,000.00 | 7,977.00 | 3,100.00 | 8,242.90 | 3,013.00 | 8,011.57 | 3,000.00 | 7,977.00 | | 0072 | 739-01-00100 | Hydro-Seeding | 13.33 | ACRE | 2,750.00 | 36,657.50 | 2,800.00 | 37,324.00 | 2,643.00 | 35,231.19 | 3,000.00 | 39,990.00 | | 0073 | 740-01-00100 | Construction Layout | 1 | LUMP | 660,000.00 | 660,000.00 | 50,000.00 | 50,000.00 | 850,000.00 | 850,000.00 | 75,000.00 | 75,000.00 | | 0074 | 802-04-00100 | Mechanically Stabilized Earth Wall Concrete Panels | 6,506 | SQFT | 110.00 | 715,660.00 | 110.00 | 715,660.00 | 130.00 | 845,780.00 | 170.00 | 1,106,020.00 | | 0075 | 802-05-00100 | MSEW Structural Excavation and Backfill | 1 | LUMP | 100,000.00 | 100,000.00 | 225,000.00 | 225,000.00 | 270,000.00 | 270,000.00 | 400,000.00 | 400,000.00 | | 0076 | 804-01-00300 | Precast Concrete Piles (16") | 266 | LNFT | 140.00 | 37,240.00 | 180.00 | 47,880.00 | 561.00 | 149,226.00 | 136.00 | 36,176.00 | | 0077 | 804-01-00400 | Precast Concrete Piles (18") | 4,488 | LNFT | 100.00 | 448,800.00 | 150.00 | 673,200.00 | 145.00 | 650,760.00 | 139.00 | 623,832.00 | | 0078 | 804-01-00700 | Precast Concrete Piles (30") | 26,790 | LNFT | 200.00 | 5,358,000.00 | 250.00 | 6,697,500.00 | 229.00 | 6,134,910.00 | 261.00 | 6,992,190.00 | | 0079 | 804-05-00700 | Precast Concrete Test Piles (30") | 2 | EACH | 120,000.00 | 240,000.00 | 60,000.00 | 120,000.00 | 90,000.00 | 180,000.00 | 230,000.00 | 460,000.00 | | 0080 | 804-09-00700 | Static Load Test (Precast Concrete Piles (30")) | 2 | EACH | 180,000.00 | 360,000.00 | 135,000.00 | 270,000.00 | 230,000.00 | 460,000.00 | 325,000.00 | 650,000.00 | | 0081 | 804-14-00100 | Dynamic Monitoring Assistance | 40 | EACH | 2,100.00 | 84,000.00 | 8,000.00 | 320,000.00 | 3,500.00 | 140,000.00 | 5,750.00 | 230,000.00 | | 0082 | 804-17-00100 | Construction Site Survey | 1 | LUMP | 50,000.00 | 50,000.00 | 40,000.00 | 40,000.00 | 58,000.00 | 58,000.00 | 40,000.00 | 40,000.00 | | 0083 | 804-18-00100 | Vibration Monitoring | 100 | DAY | 765.00 | 76,500.00 | 200.00 | 20,000.00 | 765.00 | 76,500.00 | 1,000.00 | 100,000.00 | | 0084 | 805-01-00200 | Class A1 Concrete (Deck) | 4,878.12 | CUYD | 950.00 | 4,634,214.00 | 1,400.00 | 6,829,368.00 | 1,350.00 | 6,585,462.00 | 1,700.00 | 8,292,804.00 | | 0085 | 805-01-00300 | Class A1 Concrete (Bent Cap) | 899.86 | CUYD | 1,500.00 | 1,349,790.00 | 2,200.00 | 1,979,692.00 | 1,800.00 | 1,619,748.00 | 2,900.00 | 2,609,594.00 | | 0086 | 805-08-01200 | Precast-Prestressed Concrete Girders (Type LG-36) | 20,670 | LNFT | 320.00 | 6,614,400.00 | 320.00 | 6,614,400.00 | 290.00 | 5,994,300.00 | 345.00 | 7,131,150.00 | | 0087 | 805-18-00100 | Concrete Finish (Class 2 Rubbed Finish) | 55,530 | SQFT | 1.00 | 55,530.00 | 3.00 | 166,590.00 | 2.00 | 111,060.00 | 1.00 | 55,530.00 | | 0088 | 805-18-00200 | Concrete Finish (Class 3 Special Finish) | 218,658 | SQFT | 1.20 | 262,389.60 | 1.50 | 327,987.00 | 1.00 | 218,658.00 | 1.30 | 284,255.40 | | 0089 | 806-01-00100 | Deformed Reinforcing Steel | 1,582,808 | LB | 1.20 | 1,899,369.60 | 1.35 | 2,136,790.80 | 1.30 | 2,057,650.40 | 1.15 | 1,820,229.20 | | 0090 | 807-01-00100 | Structural Metalwork (Grade 36) | 1,768 | LUMP | 40,000.00 | 40,000.00 | 12,000.00 | 12,000.00 | 30,000.00 | 30,000.00 | 15,000.00 | 15,000.00 | | 0091 | 807-02-00100 | Structural Metalwork (Anchor Bolts) | 100 | LUMP | 12,000.00 | 12,000.00 | 14,000.00 | 14,000.00 | 16,000.00 | 16,000.00 | 5,000.00 | 5,000.00 | | 0092 | 810-01-00120 | Concrete Bridge Railing (36 inch Height) | 8,320 | LNFT | 100.00 | 832,000.00 | 100.00 | 832,000.00 | 105.00 | 873,600.00 | 100.00 | 832,000.00 | | 0093 | 813-01-00100 | Concrete Approach Slabs (Cast-in-Place) | 6,400 | SQFT | 100.00 | 640,000.00 | 125.00 | 800,000.00 | 120.00 | 768,000.00 | 125.00 | 800,000.00 | | 0094 | 814-02-00100 | Elastomeric Bearing Pads (Reinforced) | 2,072.86 | SFIN | 85.00 | 176,193.10 | 85.00 | 176,193.10 | 100.00 | 207,286.00 | 100.00 | 207,286.00 | | 0095 | 815-02-00100 | Sealed Expansion Joint (End Dams and Preformed Neoprene Seal) | 640 | LNFT | 370.00 | 236,800.00 | 350.00 | 224,000.00 | 400.00 | 256,000.00 | 400.00 | 256,000.00 | | 0096 | NS-500-00340 | Saw Cutting Asphalt Concrete Pavement | 29,248 | INLF | 1.10 | 32,172.80 | 0.30 | 8,774.40 | 0.55 | 16,086.40 | 0.60 | 17,548.80 | | 0097 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 1,216 | INLF | 1.10 | 1,337.60 | 6.00 | 7,296.00 | 1.00 | 1,216.00 | 1.00 | 1,216.00 | | 0098 | NS-700-00810 | Impact Attenuator (Construction Zone)(Test Level 3) | 4 | EACH | 11,000.00 | 44,000.00 | 15,000.00 | 60,000.00 | 9,500.00 | 38,000.00 | 11,000.00 | 44,000.00 | | | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 41,423,840.37 | | 45,867,292.06 | | 46,702,783.20 | | 51,386,249.99 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 5 - MERRICK, LLC | - 6 - Orion Industrial Construction LLC | - 7 - Key, LLC Of Mississippi | BAKER PILE DRIVING AND SITE WORK LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 109-01-10000 | Time Related Overhead | 1 | LUMP | 2,000,000.00 | 2,000,000.00 | 3,800,000.00 | 3,800,000.00 | 0.00 | 0.00 | 6,300,000.00 | 6,300,000.00 | | 0002 | 201-01-00100 | Clearing and Grubbing | 13.3 | LUMP | 300,000.00 | 300,000.00 | 27,000.00 | 27,000.00 | 2,578,000.00 | 2,578,000.00 | 367,009.54 | 367,009.54 | | 0003 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 100,000.00 | 100,000.00 | 16,000.00 | 16,000.00 | 650,000.00 | 650,000.00 | 157,014.51 | 157,014.51 | | 0004 | 202-02-00030 | Removal of Temporary Tape | 58,360 | LNFT | 0.80 | 46,688.00 | 1.30 | 75,868.00 | 3.10 | 180,916.00 | 0.75 | 43,770.00 | | 0005 | 202-02-02020 | Removal of Asphalt Pavement | 17,266.1 | SQYD | 15.00 | 258,991.50 | 17.00 | 293,523.70 | 12.50 | 215,826.25 | 16.00 | 276,257.60 | | 0006 | 202-02-03000 | Removal of Base – Soil Cement, Asphalt, or BCS | 38,766.1 | SQYD | 15.00 | 581,491.50 | 13.00 | 503,959.30 | 9.00 | 348,894.90 | 8.00 | 310,128.80 | | 0007 | 202-02-14500 | Removal of Guard Rail | 216 | LNFT | 20.00 | 4,320.00 | 38.00 | 8,208.00 | 15.00 | 3,240.00 | 16.40 | 3,542.40 | | 0008 | 202-02-32180 | Removal of Pipe Headwalls | 3 | EACH | 1,500.00 | 4,500.00 | 2,800.00 | 8,400.00 | 540.00 | 1,620.00 | 2,854.59 | 8,563.77 | | 0009 | 202-02-32500 | Removal of Portland Cement Concrete Pavement | 21,500 | SQYD | 6.00 | 129,000.00 | 27.00 | 580,500.00 | 12.00 | 258,000.00 | 61.48 | 1,321,820.00 | | 0010 | 202-02-38220 | Removal of Sign Supports | 2 | EACH | 980.00 | 1,960.00 | 970.00 | 1,940.00 | 25.00 | 50.00 | 379.87 | 759.74 | | 0011 | 202-02-38300 | Removal of Sign and U-Channel Post | 43 | EACH | 20.00 | 860.00 | 19.50 | 838.50 | 50.00 | 2,150.00 | 80.57 | 3,464.51 | | 0012 | 202-02-38360 | Removal of Sign Faces | 2 | EACH | 250.00 | 500.00 | 260.00 | 520.00 | 25.00 | 50.00 | 517.87 | 1,035.74 | | 0013 | 202-02-40100 | Removal of Traffic Signal Equipment | 1 | LUMP | 25,000.00 | 25,000.00 | 26,000.00 | 26,000.00 | 25,500.00 | 25,500.00 | 38,068.66 | 38,068.66 | | 0014 | 203-01-00100 | General Excavation | 13,133 | CUYD | 11.00 | 144,463.00 | 25.00 | 328,325.00 | 17.00 | 223,261.00 | 19.25 | 252,810.25 | | 0015 | 203-03-00100 | Embankment | 22,504 | CUYD | 34.00 | 765,136.00 | 34.00 | 765,136.00 | 33.50 | 753,884.00 | 37.52 | 844,350.08 | | 0016 | 203-04-00200 | Nonplastic Embankment (Sand) | 3,152 | CUYD | 45.00 | 141,840.00 | 42.00 | 132,384.00 | 92.00 | 289,984.00 | 42.66 | 134,464.32 | | 0017 | 203-11-00100 | Settlement Plate Installation and Monitoring | 12 | EACH | 2,800.00 | 33,600.00 | 515.00 | 6,180.00 | 5,900.00 | 70,800.00 | 6,327.44 | 75,929.28 | | 0018 | 204-04-00100 | Temporary Sediment Basins | 8 | EACH | 350.00 | 2,800.00 | 220.00 | 1,760.00 | 23,000.00 | 184,000.00 | 12,692.29 | 101,538.32 | | 0019 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 52 | EACH | 30.00 | 1,560.00 | 260.00 | 13,520.00 | 155.00 | 8,060.00 | 369.73 | 19,225.96 | | 0020 | 204-06-00100 | Temporary Silt Fencing | 9,390 | LNFT | 2.50 | 23,475.00 | 2.60 | 24,414.00 | 6.00 | 56,340.00 | 7.30 | 68,547.00 | | 0021 | 302-02-08010 | Class II Base Course (8" Thick) (Soil Cement) | 13,636.3 | SQYD | 24.35 | 332,043.91 | 100.00 | 1,363,630.00 | 22.00 | 299,998.60 | 23.00 | 313,634.90 | | 0022 | 302-02-08070 | Class II Base Course (8" Thick) (Crushed Stone or Recycled Portland Cement Concrete) | 3,097.8 | SQYD | 58.00 | 179,672.40 | 67.00 | 207,552.60 | 44.00 | 136,303.20 | 42.00 | 130,107.60 | | 0023 | 302-02-10010 | Class II Base Course (10" Thick) (Soil Cement) | 5,933.5 | SQYD | 30.00 | 178,005.00 | 33.00 | 195,805.50 | 26.00 | 154,271.00 | 26.72 | 158,543.12 | | 0024 | 305-01-03020 | Subgrade Layer (10" Thick) (Treated) | 19,574 | SQYD | 16.00 | 313,184.00 | 27.00 | 528,498.00 | 26.00 | 508,924.00 | 26.64 | 521,451.36 | | 0025 | 502-01-00100 | Asphalt Concrete | 3,357 | TON | 200.00 | 671,400.00 | 375.00 | 1,258,875.00 | 346.00 | 1,161,522.00 | 519.71 | 1,744,666.47 | | 0026 | 601-01-00700 | Portland Cement Concrete Pavement (11" Thick) | 10,060.6 | SQYD | 120.00 | 1,207,272.00 | 215.00 | 2,163,029.00 | 176.00 | 1,770,665.60 | 214.00 | 2,152,968.40 | | 0027 | 601-03-01300 | Portland Cement Concrete Shoulder (11" Thick) | 6,580.9 | SQYD | 125.00 | 822,612.50 | 220.00 | 1,447,798.00 | 128.00 | 842,355.20 | 201.00 | 1,322,760.90 | | 0028 | 601-04-00100 | Portland Cement Concrete Pavement Coring | 25 | EACH | 200.00 | 5,000.00 | 135.00 | 3,375.00 | 190.00 | 4,750.00 | 575.00 | 14,375.00 | | 0029 | 701-01-01001 | Cross Drain Pipe (24" RCP) | 316 | LNFT | 280.00 | 88,480.00 | 285.00 | 90,060.00 | 240.00 | 75,840.00 | 305.89 | 96,661.24 | | 0030 | 701-03-01110 | Storm Drain Pipe (24" RCP) | 36 | LNFT | 275.00 | 9,900.00 | 292.00 | 10,512.00 | 240.00 | 8,640.00 | 260.69 | 9,384.84 | | 0031 | 702-03-00100 | Catch Basins (CB-01) | 6 | EACH | 8,000.00 | 48,000.00 | 8,500.00 | 51,000.00 | 7,645.00 | 45,870.00 | 8,947.98 | 53,687.88 | | 0032 | 704-03-00200 | Blocked Out Guard Rail - 31", (6'-3" Post Spacing) | 1,687.5 | LNFT | 35.00 | 59,062.50 | 40.00 | 67,500.00 | 31.00 | 52,312.50 | 50.36 | 84,982.50 | | 0033 | 704-05-00300 | Guard Rail Anchor Sections - 31", (Trailing End) | 19.8 | LNFT | 215.00 | 4,257.00 | 235.00 | 4,653.00 | 170.00 | 3,366.00 | 199.25 | 3,945.15 | | 0034 | 704-07-00200 | Guard Rail Transitions (Double Thrie Beam) | 150 | LNFT | 150.00 | 22,500.00 | 155.00 | 23,250.00 | 120.00 | 18,000.00 | 115.00 | 17,250.00 | | 0035 | 704-10-00205 | Guard Rail End Treatment, MASH, (TL-3 Tangent) | 4 | EACH | 4,500.00 | 18,000.00 | 4,800.00 | 19,200.00 | 3,670.00 | 14,680.00 | 4,433.62 | 17,734.48 | | 0036 | 705-06-00400 | Chain Link Fence (7 Foot Height) | 320 | LNFT | 235.00 | 75,200.00 | 165.00 | 52,800.00 | 185.00 | 59,200.00 | 132.97 | 42,550.40 | | 0037 | 706-03-00100 | Incidental Concrete Paving (4" Thick) | 625.1 | SQYD | 165.00 | 103,141.50 | 430.00 | 268,793.00 | 130.00 | 81,263.00 | 238.00 | 148,773.80 | | 0038 | 712-01-00100 | Concrete Cast-in-Place Revetment (4" Thick) | 542 | SQYD | 200.00 | 108,400.00 | 113.00 | 61,246.00 | 450.00 | 243,900.00 | 180.89 | 98,042.38 | | 0039 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 1,000,000.00 | 1,000,000.00 | 200,000.00 | 200,000.00 | 2,405,000.00 | 2,405,000.00 | 515,026.25 | 515,026.25 | | 0040 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 1,060 | LNFT | 1.00 | 1,060.00 | 0.35 | 371.00 | 0.50 | 530.00 | 0.79 | 837.40 | | 0041 | 713-03-01020 | Temporary Pavement Markings (Broken Line) (4" W) (4' L) (Type 1 Removable) | 0.084 | MILE | 12,000.00 | 1,008.00 | 5,000.00 | 420.00 | 20,000.00 | 1,680.00 | 20,000.00 | 1,680.00 | | 0042 | 713-04-01020 | Temporary Pavement Markings (Solid Line) (4"Width) (Type 1 Removable) | 11.053 | MILE | 10,000.00 | 110,530.00 | 8,000.00 | 88,424.00 | 10,800.00 | 119,372.40 | 9,170.00 | 101,356.01 | | 0043 | 713-05-00400 | Temporary Pavement Legends & Symbols (RR Crossing) | 2 | EACH | 130.00 | 260.00 | 65.00 | 130.00 | 50.00 | 100.00 | 379.87 | 759.74 | | 0044 | 713-06-00100 | Temporary Reflectorized Raised Pavement Markers | 1,622 | EACH | 10.00 | 16,220.00 | 5.25 | 8,515.50 | 5.50 | 8,921.00 | 10.20 | 16,544.40 | | 0045 | 713-07-00100 | Temporary Precast Concrete Barrier (Contractor Furnished) | 339 | EACH | 2,600.00 | 881,400.00 | 1,800.00 | 610,200.00 | 3,750.00 | 1,271,250.00 | 1,184.38 | 401,504.82 | | 0046 | 713-10-00100 | Temporary Precast Concrete Barrier Movement | 359 | EACH | 190.00 | 68,210.00 | 775.00 | 278,225.00 | 910.00 | 326,690.00 | 517.50 | 185,782.50 | | 0047 | 713-11-00100 | Portable Changeable Message Signs | 2 | EACH | 30,000.00 | 60,000.00 | 28,000.00 | 56,000.00 | 21,500.00 | 43,000.00 | 24,414.87 | 48,829.74 | | 0048 | 720-01-01000 | Erosion Control System (Slope Protection) (Type A) | 244 | SQYD | 3.50 | 854.00 | 4.75 | 1,159.00 | 3.00 | 732.00 | 3.45 | 841.80 | | 0049 | 720-01-02000 | Erosion Control System, Flexible (Channel Liner) (Type C) | 333 | SQYD | 3.50 | 1,165.50 | 3.75 | 1,248.75 | 3.00 | 999.00 | 5.04 | 1,678.32 | | 0050 | 720-01-02020 | Erosion Control System, Flexible (Channel Liner) (Type D) | 162 | SQYD | 3.50 | 567.00 | 3.75 | 607.50 | 3.00 | 486.00 | 6.72 | 1,088.64 | | 0051 | 722-02-00100 | Project Site Laboratory (Equipped) | 1 | EACH | 215,000.00 | 215,000.00 | 50,000.00 | 50,000.00 | 357,000.00 | 357,000.00 | 575,529.74 | 575,529.74 | | 0052 | 724-02-00100 | Rumble Strips (Shoulder/Edge) | 1.43 | MILE | 1,400.00 | 2,002.00 | 3,500.00 | 5,005.00 | 1,100.00 | 1,573.00 | 3,828.00 | 5,474.04 | | 0053 | 725-01-00100 | Temporary Detour Roads | 3,289.7 | SQYD | 265.00 | 871,770.50 | 500.00 | 1,644,850.00 | 265.00 | 871,770.50 | 548.00 | 1,802,755.60 | | 0054 | 726-01-00100 | Bedding Material | 83.6 | CUYD | 183.97 | 15,379.89 | 190.00 | 15,884.00 | 360.00 | 30,096.00 | 164.00 | 13,710.40 | | 0055 | 727-01-00100 | Mobilization | 1 | LUMP | 4,950,000.00 | 4,950,000.00 | 6,500,000.00 | 6,500,000.00 | 7,595,000.00 | 7,595,000.00 | 6,114,166.66 | 6,114,166.66 | | 0056 | 729-01-00100 | Sign (Type A) | 53.5 | SQFT | 45.00 | 2,407.50 | 46.00 | 2,461.00 | 25.00 | 1,337.50 | 44.40 | 2,375.40 | | 0057 | 729-04-00100 | Sign (Type D) | 77 | SQFT | 60.00 | 4,620.00 | 61.00 | 4,697.00 | 31.00 | 2,387.00 | 55.14 | 4,245.78 | | 0058 | 729-05-00100 | Sign (Type E) | 27.5 | SQFT | 55.00 | 1,512.50 | 57.00 | 1,567.50 | 45.00 | 1,237.50 | 73.00 | 2,007.50 | | 0059 | 729-08-00200 | Mounting (3 1/2" Size Post) | 1 | EACH | 2,800.00 | 2,800.00 | 3,000.00 | 3,000.00 | 2,250.00 | 2,250.00 | 3,128.74 | 3,128.74 | | 0060 | 729-08-00310 | Mounting (5" Size Post)(Structure Mount) | 2 | EACH | 7,500.00 | 15,000.00 | 8,000.00 | 16,000.00 | 8,160.00 | 16,320.00 | 6,911.50 | 13,823.00 | | 0061 | 729-08-00700 | Mounting (W8 x 18 Size Post) | 2 | EACH | 12,000.00 | 24,000.00 | 12,500.00 | 25,000.00 | 2,550.00 | 5,100.00 | 12,064.60 | 24,129.20 | | 0062 | 729-16-00300 | Object Marker Assembly (Type 3) | 4 | EACH | 110.00 | 440.00 | 110.00 | 440.00 | 85.00 | 340.00 | 419.93 | 1,679.72 | | 0063 | 729-18-00100 | Milepost Assembly (Structure Mounted) | 2 | EACH | 390.00 | 780.00 | 390.00 | 780.00 | 5,100.00 | 10,200.00 | 609.87 | 1,219.74 | | 0064 | 731-02-00100 | Reflectorized Raised Pavement Markers | 813 | EACH | 9.00 | 7,317.00 | 5.25 | 4,268.25 | 6.00 | 4,878.00 | 11.32 | 9,203.16 | | 0065 | 731-03-00100 | Removal of Raised Pavement Markers | 2.659 | MILE | 130.00 | 345.67 | 130.00 | 345.67 | 900.00 | 2,393.10 | 120.00 | 319.08 | | 0066 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 1,466 | LNFT | 3.50 | 5,131.00 | 3.55 | 5,204.30 | 5.50 | 8,063.00 | 3.81 | 5,585.46 | | 0067 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 372 | LNFT | 14.00 | 5,208.00 | 18.00 | 6,696.00 | 19.00 | 7,068.00 | 14.10 | 5,245.20 | | 0068 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 5.318 | MILE | 6,900.00 | 36,694.20 | 5,100.00 | 27,121.80 | 5,610.00 | 29,833.98 | 6,830.00 | 36,321.94 | | 0069 | 732-03-02040 | Plastic Pavement Striping (Dotted Line)(8" W)(3' L)(Thermo 90 mil) | 0.136 | MILE | 16,000.00 | 2,176.00 | 3,100.00 | 421.60 | 15,000.00 | 2,040.00 | 19,970.00 | 2,715.92 | | 0070 | 732-03-02102 | Plastic Pav't Striping (Broken) (4" W) (Preformed Tape Retroreflectivity I or Thermo 90 mil)(Black and White Contrast) | 2.659 | MILE | 3,000.00 | 7,977.00 | 4,500.00 | 11,965.50 | 3,570.00 | 9,492.63 | 3,170.00 | 8,429.03 | | 0071 | 732-05-00100 | Removal of Existing Markings | 2.659 | MILE | 12,000.00 | 31,908.00 | 3,900.00 | 10,370.10 | 10,200.00 | 27,121.80 | 11,940.00 | 31,748.46 | | 0072 | 739-01-00100 | Hydro-Seeding | 13.33 | ACRE | 3,400.00 | 45,322.00 | 3,500.00 | 46,655.00 | 2,810.00 | 37,457.30 | 3,159.00 | 42,109.47 | | 0073 | 740-01-00100 | Construction Layout | 1 | LUMP | 700,000.00 | 700,000.00 | 1,350,000.00 | 1,350,000.00 | 960,000.00 | 960,000.00 | 629,583.20 | 629,583.20 | | 0074 | 802-04-00100 | Mechanically Stabilized Earth Wall Concrete Panels | 6,506 | SQFT | 88.00 | 572,528.00 | 110.00 | 715,660.00 | 250.00 | 1,626,500.00 | 86.00 | 559,516.00 | | 0075 | 802-05-00100 | MSEW Structural Excavation and Backfill | 1 | LUMP | 400,000.00 | 400,000.00 | 265,000.00 | 265,000.00 | 800,000.00 | 800,000.00 | 339,494.64 | 339,494.64 | | 0076 | 804-01-00300 | Precast Concrete Piles (16") | 266 | LNFT | 350.00 | 93,100.00 | 350.00 | 93,100.00 | 510.00 | 135,660.00 | 461.27 | 122,697.82 | | 0077 | 804-01-00400 | Precast Concrete Piles (18") | 4,488 | LNFT | 190.00 | 852,720.00 | 160.00 | 718,080.00 | 270.00 | 1,211,760.00 | 172.98 | 776,334.24 | | 0078 | 804-01-00700 | Precast Concrete Piles (30") | 26,790 | LNFT | 225.00 | 6,027,750.00 | 450.00 | 12,055,500.00 | 588.00 | 15,752,520.00 | 342.40 | 9,172,896.00 | | 0079 | 804-05-00700 | Precast Concrete Test Piles (30") | 2 | EACH | 250,000.00 | 500,000.00 | 55,000.00 | 110,000.00 | 975,000.00 | 1,950,000.00 | 204,315.02 | 408,630.04 | | 0080 | 804-09-00700 | Static Load Test (Precast Concrete Piles (30")) | 2 | EACH | 150,000.00 | 300,000.00 | 185,000.00 | 370,000.00 | 478,000.00 | 956,000.00 | 51,691.25 | 103,382.50 | | 0081 | 804-14-00100 | Dynamic Monitoring Assistance | 40 | EACH | 2,300.00 | 92,000.00 | 8,600.00 | 344,000.00 | 8,880.00 | 355,200.00 | 3,664.43 | 146,577.20 | | 0082 | 804-17-00100 | Construction Site Survey | 1 | LUMP | 50,000.00 | 50,000.00 | 48,000.00 | 48,000.00 | 169,000.00 | 169,000.00 | 44,229.74 | 44,229.74 | | 0083 | 804-18-00100 | Vibration Monitoring | 100 | DAY | 1,000.00 | 100,000.00 | 850.00 | 85,000.00 | 1,500.00 | 150,000.00 | 1,426.73 | 142,673.00 | | 0084 | 805-01-00200 | Class A1 Concrete (Deck) | 4,878.12 | CUYD | 1,530.00 | 7,463,523.60 | 1,560.00 | 7,609,867.20 | 1,500.00 | 7,317,180.00 | 1,584.00 | 7,726,942.08 | | 0085 | 805-01-00300 | Class A1 Concrete (Bent Cap) | 899.86 | CUYD | 3,300.00 | 2,969,538.00 | 3,400.00 | 3,059,524.00 | 1,500.00 | 1,349,790.00 | 2,761.00 | 2,484,513.46 | | 0086 | 805-08-01200 | Precast-Prestressed Concrete Girders (Type LG-36) | 20,670 | LNFT | 362.00 | 7,482,540.00 | 350.00 | 7,234,500.00 | 593.00 | 12,257,310.00 | 381.62 | 7,888,085.40 | | 0087 | 805-18-00100 | Concrete Finish (Class 2 Rubbed Finish) | 55,530 | SQFT | 3.00 | 166,590.00 | 10.00 | 555,300.00 | 5.00 | 277,650.00 | 4.46 | 247,663.80 | | 0088 | 805-18-00200 | Concrete Finish (Class 3 Special Finish) | 218,658 | SQFT | 1.70 | 371,718.60 | 1.55 | 338,919.90 | 5.00 | 1,093,290.00 | 2.55 | 557,577.90 | | 0089 | 806-01-00100 | Deformed Reinforcing Steel | 1,582,808 | LB | 1.50 | 2,374,212.00 | 1.80 | 2,849,054.40 | 1.70 | 2,690,773.60 | 1.40 | 2,215,931.20 | | 0090 | 807-01-00100 | Structural Metalwork (Grade 36) | 1,768 | LUMP | 50,000.00 | 50,000.00 | 750,000.00 | 750,000.00 | 10,600.00 | 10,600.00 | 82,749.58 | 82,749.58 | | 0091 | 807-02-00100 | Structural Metalwork (Anchor Bolts) | 100 | LUMP | 15,000.00 | 15,000.00 | 70,000.00 | 70,000.00 | 1,650.00 | 1,650.00 | 10,274.27 | 10,274.27 | | 0092 | 810-01-00120 | Concrete Bridge Railing (36 inch Height) | 8,320 | LNFT | 130.00 | 1,081,600.00 | 190.00 | 1,580,800.00 | 155.00 | 1,289,600.00 | 170.45 | 1,418,144.00 | | 0093 | 813-01-00100 | Concrete Approach Slabs (Cast-in-Place) | 6,400 | SQFT | 100.00 | 640,000.00 | 71.00 | 454,400.00 | 150.00 | 960,000.00 | 112.14 | 717,696.00 | | 0094 | 814-02-00100 | Elastomeric Bearing Pads (Reinforced) | 2,072.86 | SFIN | 160.00 | 331,657.60 | 122.00 | 252,888.92 | 142.00 | 294,346.12 | 121.00 | 250,816.06 | | 0095 | 815-02-00100 | Sealed Expansion Joint (End Dams and Preformed Neoprene Seal) | 640 | LNFT | 590.00 | 377,600.00 | 330.00 | 211,200.00 | 400.00 | 256,000.00 | 368.84 | 236,057.60 | | 0096 | NS-500-00340 | Saw Cutting Asphalt Concrete Pavement | 29,248 | INLF | 1.50 | 43,872.00 | 0.72 | 21,058.56 | 4.00 | 116,992.00 | 1.33 | 38,899.84 | | 0097 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 1,216 | INLF | 5.00 | 6,080.00 | 1.30 | 1,580.80 | 5.00 | 6,080.00 | 3.18 | 3,866.88 | | 0098 | NS-700-00810 | Impact Attenuator (Construction Zone)(Test Level 3) | 4 | EACH | 15,000.00 | 60,000.00 | 13,000.00 | 52,000.00 | 12,000.00 | 48,000.00 | 11,632.43 | 46,529.72 | | | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 50,323,411.37 | | 65,255,520.85 | | 76,570,058.68 | | IRREGULAR |
|