Proposal:H.015613.6
Parish:LaSalle
Routes:US 84
Description:US 84: UP RR OVERPASS REPLACEMENT (HBI)
Type Construction:CLEARING AND GRUBBING, REMOVAL OF BRIDGES, GRADING, DRAINAGE STRUCTURES, CLASS II BASE COURSE, LIME TREATMENT, MILLING ASPHALT CONCRETE, PAVEMENT PATCHING, ASPHALT CONCRETE, DRILLED SHAFTS, DETOUR ROAD, STEEL GIRDER BRIDGE, AND RELATED WORK.
Estimated Construction Cost:$14,974,673.07
Maximum Number of Days Allowed for Construction:999
Calculated Daily User Cost:$4,500.00
| Rank | License | Bidder | Construction Bid | Bidder's Proposed Contract Time | Total Bid |
| 1 | 79463 | Denley Brown Contractors, LLC | $11,191,024.10 | 300.00 | $12,541,024.10 |
| 2 | 49239 | WL Bass Construction Inc. | $11,547,058.60 | 500.00 | $13,797,058.60 |
| 3 | 55505 | MERRICK, LLC | $12,331,203.10 | 600.00 | $15,031,203.10 |
| 4 | 39462 | JB JAMES CONSTRUCTION LLC | $13,191,769.00 | 480.00 | $15,351,769.00 |
| 5 | 12312 | GILCHRIST CONSTRUCTION COMPANY, LLC | $22,825,912.55 | 500.00 | $25,075,912.55 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Denley Brown Contractors, LLC | - 2 - WL Bass Construction Inc. | - 3 - MERRICK, LLC | - 4 - JB JAMES CONSTRUCTION LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 201-01-00100 | Clearing and Grubbing | 12.51 | LUMP | 525,000.00 | 525,000.00 | 107,000.00 | 107,000.00 | 35,000.00 | 35,000.00 | 1,100,000.00 | 1,100,000.00 | | 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 5,000.00 | 5,000.00 | 6,800.00 | 6,800.00 | 10,000.00 | 10,000.00 | 28,000.00 | 28,000.00 | | 0003 | 202-02-00010 | Removal of Impact Attenuators | 6 | EACH | 1,000.00 | 6,000.00 | 2,000.00 | 12,000.00 | 2,000.00 | 12,000.00 | 4,000.00 | 24,000.00 | | 0004 | 202-02-00010 | Removal of Temporary Precast Barriers | 152 | EACH | 150.00 | 22,800.00 | 230.00 | 34,960.00 | 350.00 | 53,200.00 | 264.00 | 40,128.00 | | 0007 | 202-02-02000 | Removal of Asphalt Drives | 579 | SQYD | 8.00 | 4,632.00 | 3.00 | 1,737.00 | 15.00 | 8,685.00 | 8.00 | 4,632.00 | | 0008 | 202-02-03030 | Removal of Pavement Structure | 8,162 | SQYD | 10.00 | 81,620.00 | 22.00 | 179,564.00 | 9.00 | 73,458.00 | 5.00 | 40,810.00 | | 0009 | 202-02-04501 | Removal of Bridge (28' x 240', Temporary Detour Bridge (Steel Truss)) | 6,720 | LUMP | 105,000.00 | 105,000.00 | 200,000.00 | 200,000.00 | 450,000.00 | 450,000.00 | 130,000.00 | 130,000.00 | | 0010 | 202-02-04501 | Removal of Bridge (28.6' x 160', Concrete Deck Girder Bridge) | 4,576 | LUMP | 350,000.00 | 350,000.00 | 350,000.00 | 350,000.00 | 450,000.00 | 450,000.00 | 600,000.00 | 600,000.00 | | 0011 | 202-02-06100 | Removal of Concrete Walks and Drives | 93 | SQYD | 8.00 | 744.00 | 8.00 | 744.00 | 30.00 | 2,790.00 | 8.00 | 744.00 | | 0012 | 202-02-12020 | Removal of Fence (Chain Link) | 720 | LNFT | 9.00 | 6,480.00 | 3.00 | 2,160.00 | 1.30 | 936.00 | 12.00 | 8,640.00 | | 0013 | 202-02-14500 | Removal of Guard Rail | 502.7 | LNFT | 10.00 | 5,027.00 | 7.00 | 3,518.90 | 10.00 | 5,027.00 | 12.00 | 6,032.40 | | 0014 | 203-01-00100 | General Excavation | 17,547 | CUYD | 10.00 | 175,470.00 | 9.00 | 157,923.00 | 5.00 | 87,735.00 | 26.00 | 456,222.00 | | 0015 | 203-03-00100 | Embankment | 44,348 | CUYD | 18.00 | 798,264.00 | 25.00 | 1,108,700.00 | 22.00 | 975,656.00 | 21.00 | 931,308.00 | | 0016 | 203-08-00100 | Geotextile Fabric | 87,085 | SQYD | 3.00 | 261,255.00 | 3.00 | 261,255.00 | 1.50 | 130,627.50 | 3.00 | 261,255.00 | | 0017 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 18 | EACH | 150.00 | 2,700.00 | 150.00 | 2,700.00 | 180.00 | 3,240.00 | 150.00 | 2,700.00 | | 0018 | 204-06-00100 | Temporary Silt Fencing | 3,294 | LNFT | 2.30 | 7,576.20 | 4.00 | 13,176.00 | 2.50 | 8,235.00 | 8.00 | 26,352.00 | | 0019 | 302-02-10000 | Class II Base Course (10" Thick) | 7,231.9 | SQYD | 46.00 | 332,667.40 | 32.00 | 231,420.80 | 24.00 | 173,565.60 | 26.00 | 188,029.40 | | 0020 | 302-03-00100 | Base Drain Outlet | 2 | EACH | 2,000.00 | 4,000.00 | 2,500.00 | 5,000.00 | 700.00 | 1,400.00 | 2,900.00 | 5,800.00 | | 0021 | 304-01-00100 | Lime | 102.52 | TON | 310.00 | 31,781.20 | 315.00 | 32,293.80 | 300.00 | 30,756.00 | 400.00 | 41,008.00 | | 0022 | 304-05-00100 | Lime Treatment (Type E) | 7,231 | SQYD | 4.00 | 28,924.00 | 7.00 | 50,617.00 | 1.50 | 10,846.50 | 9.00 | 65,079.00 | | 0023 | 402-01-00101 | Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) | 348.2 | CUYD | 150.00 | 52,230.00 | 150.00 | 52,230.00 | 120.00 | 41,784.00 | 200.00 | 69,640.00 | | 0024 | 502-01-00100 | Asphalt Concrete | 2,219.1 | TON | 200.00 | 443,820.00 | 200.00 | 443,820.00 | 260.00 | 576,966.00 | 200.00 | 443,820.00 | | 0025 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 253.6 | TON | 310.00 | 78,616.00 | 303.00 | 76,840.80 | 310.00 | 78,616.00 | 300.00 | 76,080.00 | | 0026 | 509-01-00100 | Milling Asphalt Pavement | 2,168 | SQYD | 22.00 | 47,696.00 | 26.00 | 56,368.00 | 15.00 | 32,520.00 | 30.00 | 65,040.00 | | 0027 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -120 | CUYD | 0.01 | -1.20 | 1.00 | -120.00 | 0.01 | -1.20 | 0.01 | -1.20 | | 0028 | 510-01-00001 | Pavement Patching 13.5" Minimum Thickness | 102 | SQYD | 205.00 | 20,910.00 | 285.00 | 29,070.00 | 215.00 | 21,930.00 | 200.00 | 20,400.00 | | 0029 | 701-05-01049 | Side Drain Pipe (18" RCP/RPVCP/CPEPDW/CPPPDW) | 78 | LNFT | 110.00 | 8,580.00 | 120.00 | 9,360.00 | 55.00 | 4,290.00 | 250.00 | 19,500.00 | | 0030 | 702-08-00100 | Side Drain Safety End (Type 1) | 10 | EACH | 4,000.00 | 40,000.00 | 2,500.00 | 25,000.00 | 1,800.00 | 18,000.00 | 6,000.00 | 60,000.00 | | 0031 | 704-03-00200 | Blocked Out Guard Rail - 31", (6'-3" Post Spacing) | 37.5 | LNFT | 32.00 | 1,200.00 | 32.00 | 1,200.00 | 30.00 | 1,125.00 | 32.00 | 1,200.00 | | 0032 | 704-07-00200 | Guard Rail Transitions (Double Thrie Beam) | 100 | LNFT | 125.00 | 12,500.00 | 122.00 | 12,200.00 | 160.00 | 16,000.00 | 123.00 | 12,300.00 | | 0033 | 704-10-00205 | Guard Rail End Treatment, MASH, (TL-3 Tangent) | 4 | EACH | 4,000.00 | 16,000.00 | 3,875.00 | 15,500.00 | 5,000.00 | 20,000.00 | 3,900.00 | 15,600.00 | | 0034 | 705-06-00200 | Chain Link Fence (5-Foot Height) | 720 | LNFT | 66.00 | 47,520.00 | 50.00 | 36,000.00 | 85.00 | 61,200.00 | 65.00 | 46,800.00 | | 0035 | 705-06-00440 | Chain Link Fence (7 Foot 4 Inch Height) | 330 | LNFT | 120.00 | 39,600.00 | 130.00 | 42,900.00 | 155.00 | 51,150.00 | 115.00 | 37,950.00 | | 0036 | 706-02-00200 | Concrete Drive (6" Thick) | 95 | SQYD | 110.00 | 10,450.00 | 170.00 | 16,150.00 | 125.00 | 11,875.00 | 175.00 | 16,625.00 | | 0037 | 708-01-00100 | Right-of-Way Monument | 13 | EACH | 600.00 | 7,800.00 | 200.00 | 2,600.00 | 780.00 | 10,140.00 | 600.00 | 7,800.00 | | 0038 | 708-02-00100 | Right-of-Way Monument Witness Post | 13 | EACH | 200.00 | 2,600.00 | 200.00 | 2,600.00 | 260.00 | 3,380.00 | 200.00 | 2,600.00 | | 0039 | 712-01-00100 | Concrete Cast-in-Place Revetment (4" Thick) | 1,028 | SQYD | 125.00 | 128,500.00 | 145.00 | 149,060.00 | 160.00 | 164,480.00 | 200.00 | 205,600.00 | | 0040 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 120,000.00 | 120,000.00 | 235,000.00 | 235,000.00 | 100,000.00 | 100,000.00 | 150,000.00 | 150,000.00 | | 0041 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 1.984 | MILE | 1,200.00 | 2,380.80 | 1,200.00 | 2,380.80 | 1,600.00 | 3,174.40 | 1,200.00 | 2,380.80 | | 0042 | 713-06-00100 | Temporary Reflectorized Raised Pavement Markers | 131 | EACH | 6.00 | 786.00 | 6.00 | 786.00 | 8.00 | 1,048.00 | 6.00 | 786.00 | | 0043 | 713-10-00100 | Temporary Precast Concrete Barrier Movement | 150 | EACH | 70.00 | 10,500.00 | 188.00 | 28,200.00 | 50.00 | 7,500.00 | 225.00 | 33,750.00 | | 0044 | 716-01-00100 | Mulch (Vegetative) | 9.4 | TON | 1,000.00 | 9,400.00 | 850.00 | 7,990.00 | 1,200.00 | 11,280.00 | 850.00 | 7,990.00 | | 0045 | 717-01-00100 | Seeding | 187 | LB | 25.00 | 4,675.00 | 20.00 | 3,740.00 | 15.00 | 2,805.00 | 20.00 | 3,740.00 | | 0046 | 718-01-00100 | Fertilizer | 4,682 | LB | 0.65 | 3,043.30 | 0.65 | 3,043.30 | 1.00 | 4,682.00 | 0.65 | 3,043.30 | | 0047 | 720-01-01000 | Erosion Control System (Slope Protection) (Type A) | 1,140 | SQYD | 2.00 | 2,280.00 | 3.00 | 3,420.00 | 4.00 | 4,560.00 | 2.00 | 2,280.00 | | 0048 | 720-01-02000 | Erosion Control System, Flexible (Channel Liner) (Type C) | 594 | SQYD | 3.00 | 1,782.00 | 4.00 | 2,376.00 | 4.00 | 2,376.00 | 3.00 | 1,782.00 | | 0049 | 722-02-00100 | Project Site Laboratory (Equipped) | 1 | EACH | 50,000.00 | 50,000.00 | 10,000.00 | 10,000.00 | 75,000.00 | 75,000.00 | 25,000.00 | 25,000.00 | | 0050 | 724-01-00100 | Rumble Strips (Centerline) | 0.425 | MILE | 500.00 | 212.50 | 300.00 | 127.50 | 1,200.00 | 510.00 | 1,000.00 | 425.00 | | 0051 | 724-02-00100 | Rumble Strips (Shoulder/Edge) | 0.849 | MILE | 500.00 | 424.50 | 300.00 | 254.70 | 1,300.00 | 1,103.70 | 1,000.00 | 849.00 | | 0052 | 725-01-00100 | Temporary Detour Roads | 7,392.3 | SQYD | 70.00 | 517,461.00 | 90.00 | 665,307.00 | 12.00 | 88,707.60 | 45.00 | 332,653.50 | | 0053 | 727-01-00100 | Mobilization | 1 | LUMP | 1,000,000.00 | 1,000,000.00 | 1,154,000.00 | 1,154,000.00 | 1,125,000.00 | 1,125,000.00 | 1,300,000.00 | 1,300,000.00 | | 0054 | 729-16-00300 | Object Marker Assembly (Type 3) | 4 | EACH | 90.00 | 360.00 | 90.00 | 360.00 | 130.00 | 520.00 | 90.00 | 360.00 | | 0055 | 731-01-00100 | Nonreflectorized Raised Pavement Markers | 964 | EACH | 12.00 | 11,568.00 | 12.00 | 11,568.00 | 15.00 | 14,460.00 | 12.00 | 11,568.00 | | 0056 | 731-02-00100 | Reflectorized Raised Pavement Markers | 131 | EACH | 6.00 | 786.00 | 6.00 | 786.00 | 8.00 | 1,048.00 | 6.00 | 786.00 | | 0057 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 1.982 | MILE | 5,500.00 | 10,901.00 | 5,500.00 | 10,901.00 | 7,000.00 | 13,874.00 | 5,500.00 | 10,901.00 | | 0058 | 732-05-00100 | Removal of Existing Markings | 0.128 | MILE | 4,200.00 | 537.60 | 4,000.00 | 512.00 | 5,000.00 | 640.00 | 4,000.00 | 512.00 | | 0059 | 740-01-00100 | Construction Layout | 1 | LUMP | 100,000.00 | 100,000.00 | 120,000.00 | 120,000.00 | 100,000.00 | 100,000.00 | 200,000.00 | 200,000.00 | | 0060 | 803-01-00200 | Drilled Shaft (24" Diameter) | 72 | LNFT | 750.00 | 54,000.00 | 890.00 | 64,080.00 | 1,000.00 | 72,000.00 | 800.00 | 57,600.00 | | 0061 | 803-01-00800 | Drilled Shaft (60" Diameter) | 930 | LNFT | 1,850.00 | 1,720,500.00 | 2,200.00 | 2,046,000.00 | 2,000.00 | 1,860,000.00 | 1,900.00 | 1,767,000.00 | | 0062 | 803-02-00800 | Test Shaft (60" Diameter) | 85 | LNFT | 2,000.00 | 170,000.00 | 2,600.00 | 221,000.00 | 2,500.00 | 212,500.00 | 2,000.00 | 170,000.00 | | 0063 | 803-07-00800 | Bi-Directional Load Cell Test (60" Diameter) | 1 | EACH | 250,000.00 | 250,000.00 | 200,000.00 | 200,000.00 | 180,000.00 | 180,000.00 | 130,000.00 | 130,000.00 | | 0064 | 803-08-00800 | Crosshole Sonic Log Test (60" Diameter) | 15 | EACH | 4,000.00 | 60,000.00 | 12,000.00 | 180,000.00 | 3,800.00 | 57,000.00 | 10,000.00 | 150,000.00 | | 0065 | 803-09-00800 | Non-Destructive Test (60" Diameter) (Thermal Integrity Profiling) | 15 | EACH | 4,500.00 | 67,500.00 | 5,500.00 | 82,500.00 | 5,200.00 | 78,000.00 | 4,000.00 | 60,000.00 | | 0066 | 805-01-00200 | Class A1 Concrete (Deck) | 348.71 | CUYD | 1,330.00 | 463,784.30 | 350.00 | 122,048.50 | 1,800.00 | 627,678.00 | 1,500.00 | 523,065.00 | | 0067 | 805-01-00300 | Class A1 Concrete (Bent Cap) | 142.34 | CUYD | 1,800.00 | 256,212.00 | 350.00 | 49,819.00 | 2,200.00 | 313,148.00 | 2,200.00 | 313,148.00 | | 0068 | 805-01-00400 | Class A1 Concrete (Column) | 69.24 | CUYD | 1,350.00 | 93,474.00 | 350.00 | 24,234.00 | 1,800.00 | 124,632.00 | 2,000.00 | 138,480.00 | | 0069 | 805-18-00100 | Concrete Finish (Class 2 Rubbed Finish) | 3,948 | SQFT | 2.50 | 9,870.00 | 1.00 | 3,948.00 | 2.00 | 7,896.00 | 1.50 | 5,922.00 | | 0070 | 805-18-00200 | Concrete Finish (Class 3 Special Finish) | 9,478 | SQFT | 3.00 | 28,434.00 | 1.00 | 9,478.00 | 3.00 | 28,434.00 | 2.00 | 18,956.00 | | 0071 | 806-01-00100 | Deformed Reinforcing Steel | 158,827 | LB | 1.50 | 238,240.50 | 1.50 | 238,240.50 | 2.00 | 317,654.00 | 1.40 | 222,357.80 | | 0072 | 807-01-00400 | Structural Metalwork (Grade 50W) | 9,067 | LUMP | 80,000.00 | 80,000.00 | 70,000.00 | 70,000.00 | 110,000.00 | 110,000.00 | 30,000.00 | 30,000.00 | | 0073 | 807-01-00400 | Structural Metalwork (Grade 50W) (Department Furnished) | 639,852 | LUMP | 950,000.00 | 950,000.00 | 700,000.00 | 700,000.00 | 1,000,000.00 | 1,000,000.00 | 550,000.00 | 550,000.00 | | 0074 | 807-02-00100 | Structural Metalwork (Anchor Bolts) | 568 | LUMP | 24,000.00 | 24,000.00 | 19,000.00 | 19,000.00 | 35,000.00 | 35,000.00 | 15,000.00 | 15,000.00 | | 0075 | 810-01-00100 | Concrete Bridge Railing (Standard) | 658 | LNFT | 210.00 | 138,180.00 | 180.00 | 118,440.00 | 190.00 | 125,020.00 | 150.00 | 98,700.00 | | 0076 | 811-01-00100 | Cleaning and Painting (Structural Metalwork (Grade 50W) (Department Furnished)) | 5,277 | LUMP | 180,000.00 | 180,000.00 | 100,000.00 | 100,000.00 | 215,000.00 | 215,000.00 | 335,000.00 | 335,000.00 | | 0077 | 813-01-00100 | Concrete Approach Slabs (Cast-in-Place) | 3,200 | SQFT | 120.00 | 384,000.00 | 100.00 | 320,000.00 | 85.00 | 272,000.00 | 120.00 | 384,000.00 | | 0078 | 814-02-00100 | Elastomeric Bearing Pads (Reinforced) | 96 | SFIN | 400.00 | 38,400.00 | 700.00 | 67,200.00 | 1,100.00 | 105,600.00 | 900.00 | 86,400.00 | | 0079 | 815-02-00200 | Sealed Expansion Joint (End Dams and Preformed Silicone Seal) | 80 | LNFT | 270.00 | 21,600.00 | 280.00 | 22,400.00 | 775.00 | 62,000.00 | 320.00 | 25,600.00 | | 0080 | 816-02-00100 | Bridge End Drain System (Open Drain) | 4 | EACH | 8,000.00 | 32,000.00 | 15,000.00 | 60,000.00 | 10,000.00 | 40,000.00 | 15,000.00 | 60,000.00 | | 0081 | NS-500-00240 | Sawing and Sealing Transverse Joints in Asphalt Concrete Overlay | 240 | LNFT | 22.00 | 5,280.00 | 35.00 | 8,400.00 | 6.00 | 1,440.00 | 23.00 | 5,520.00 | | 0082 | NS-500-00260 | Sawcuts in Asphalt Concrete Lifts | 400 | LNFT | 1.00 | 400.00 | 1.00 | 400.00 | 4.00 | 1,600.00 | 3.00 | 1,200.00 | | 0083 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 1,000 | INLF | 1.50 | 1,500.00 | 1.00 | 1,000.00 | 3.00 | 3,000.00 | 3.00 | 3,000.00 | | 0084 | NS-700-00820 | Impact Attenuator Relocation (Construction Zone) | 4 | EACH | 1,600.00 | 6,400.00 | 10,000.00 | 40,000.00 | 2,000.00 | 8,000.00 | 2,000.00 | 8,000.00 | | 0085 | 109-01-10000 | Time Related Overhead | 1 | LUMP | 200,000.00 | 200,000.00 | 600,000.00 | 600,000.00 | 850,000.00 | 850,000.00 | 768,000.00 | 768,000.00 | | 0086 | 202-02-00030 | Removal of Temporary Sheeting | 1,429 | LNFT | 110.00 | 157,190.00 | 130.00 | 185,770.00 | 300.00 | 428,700.00 | 80.00 | 114,320.00 | | | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 11,191,024.10 | | 11,547,058.60 | | 12,331,203.10 | | 13,191,769.00 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 5 - GILCHRIST CONSTRUCTION COMPANY, LLC | | Unit Price | Total Amount | | 0001 | 201-01-00100 | Clearing and Grubbing | 12.51 | LUMP | 500,000.00 | 500,000.00 | | 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 30,000.00 | 30,000.00 | | 0003 | 202-02-00010 | Removal of Impact Attenuators | 6 | EACH | 4,000.00 | 24,000.00 | | 0004 | 202-02-00010 | Removal of Temporary Precast Barriers | 152 | EACH | 500.00 | 76,000.00 | | 0007 | 202-02-02000 | Removal of Asphalt Drives | 579 | SQYD | 35.00 | 20,265.00 | | 0008 | 202-02-03030 | Removal of Pavement Structure | 8,162 | SQYD | 26.00 | 212,212.00 | | 0009 | 202-02-04501 | Removal of Bridge (28' x 240', Temporary Detour Bridge (Steel Truss)) | 6,720 | LUMP | 400,000.00 | 400,000.00 | | 0010 | 202-02-04501 | Removal of Bridge (28.6' x 160', Concrete Deck Girder Bridge) | 4,576 | LUMP | 1,000,000.00 | 1,000,000.00 | | 0011 | 202-02-06100 | Removal of Concrete Walks and Drives | 93 | SQYD | 100.00 | 9,300.00 | | 0012 | 202-02-12020 | Removal of Fence (Chain Link) | 720 | LNFT | 10.00 | 7,200.00 | | 0013 | 202-02-14500 | Removal of Guard Rail | 502.7 | LNFT | 20.00 | 10,054.00 | | 0014 | 203-01-00100 | General Excavation | 17,547 | CUYD | 30.00 | 526,410.00 | | 0015 | 203-03-00100 | Embankment | 44,348 | CUYD | 60.00 | 2,660,880.00 | | 0016 | 203-08-00100 | Geotextile Fabric | 87,085 | SQYD | 3.00 | 261,255.00 | | 0017 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 18 | EACH | 500.00 | 9,000.00 | | 0018 | 204-06-00100 | Temporary Silt Fencing | 3,294 | LNFT | 5.00 | 16,470.00 | | 0019 | 302-02-10000 | Class II Base Course (10" Thick) | 7,231.9 | SQYD | 70.00 | 506,233.00 | | 0020 | 302-03-00100 | Base Drain Outlet | 2 | EACH | 6,000.00 | 12,000.00 | | 0021 | 304-01-00100 | Lime | 102.52 | TON | 400.00 | 41,008.00 | | 0022 | 304-05-00100 | Lime Treatment (Type E) | 7,231 | SQYD | 6.00 | 43,386.00 | | 0023 | 402-01-00101 | Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) | 348.2 | CUYD | 200.00 | 69,640.00 | | 0024 | 502-01-00100 | Asphalt Concrete | 2,219.1 | TON | 325.00 | 721,207.50 | | 0025 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 253.6 | TON | 325.00 | 82,420.00 | | 0026 | 509-01-00100 | Milling Asphalt Pavement | 2,168 | SQYD | 13.00 | 28,184.00 | | 0027 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -120 | CUYD | 1.00 | -120.00 | | 0028 | 510-01-00001 | Pavement Patching 13.5" Minimum Thickness | 102 | SQYD | 250.00 | 25,500.00 | | 0029 | 701-05-01049 | Side Drain Pipe (18" RCP/RPVCP/CPEPDW/CPPPDW) | 78 | LNFT | 300.00 | 23,400.00 | | 0030 | 702-08-00100 | Side Drain Safety End (Type 1) | 10 | EACH | 16,000.00 | 160,000.00 | | 0031 | 704-03-00200 | Blocked Out Guard Rail - 31", (6'-3" Post Spacing) | 37.5 | LNFT | 40.00 | 1,500.00 | | 0032 | 704-07-00200 | Guard Rail Transitions (Double Thrie Beam) | 100 | LNFT | 125.00 | 12,500.00 | | 0033 | 704-10-00205 | Guard Rail End Treatment, MASH, (TL-3 Tangent) | 4 | EACH | 4,000.00 | 16,000.00 | | 0034 | 705-06-00200 | Chain Link Fence (5-Foot Height) | 720 | LNFT | 75.00 | 54,000.00 | | 0035 | 705-06-00440 | Chain Link Fence (7 Foot 4 Inch Height) | 330 | LNFT | 125.00 | 41,250.00 | | 0036 | 706-02-00200 | Concrete Drive (6" Thick) | 95 | SQYD | 300.00 | 28,500.00 | | 0037 | 708-01-00100 | Right-of-Way Monument | 13 | EACH | 700.00 | 9,100.00 | | 0038 | 708-02-00100 | Right-of-Way Monument Witness Post | 13 | EACH | 250.00 | 3,250.00 | | 0039 | 712-01-00100 | Concrete Cast-in-Place Revetment (4" Thick) | 1,028 | SQYD | 300.00 | 308,400.00 | | 0040 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 500,000.00 | 500,000.00 | | 0041 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 1.984 | MILE | 1,200.00 | 2,380.80 | | 0042 | 713-06-00100 | Temporary Reflectorized Raised Pavement Markers | 131 | EACH | 7.00 | 917.00 | | 0043 | 713-10-00100 | Temporary Precast Concrete Barrier Movement | 150 | EACH | 250.00 | 37,500.00 | | 0044 | 716-01-00100 | Mulch (Vegetative) | 9.4 | TON | 500.00 | 4,700.00 | | 0045 | 717-01-00100 | Seeding | 187 | LB | 18.00 | 3,366.00 | | 0046 | 718-01-00100 | Fertilizer | 4,682 | LB | 1.30 | 6,086.60 | | 0047 | 720-01-01000 | Erosion Control System (Slope Protection) (Type A) | 1,140 | SQYD | 2.50 | 2,850.00 | | 0048 | 720-01-02000 | Erosion Control System, Flexible (Channel Liner) (Type C) | 594 | SQYD | 4.00 | 2,376.00 | | 0049 | 722-02-00100 | Project Site Laboratory (Equipped) | 1 | EACH | 75,000.00 | 75,000.00 | | 0050 | 724-01-00100 | Rumble Strips (Centerline) | 0.425 | MILE | 1,000.00 | 425.00 | | 0051 | 724-02-00100 | Rumble Strips (Shoulder/Edge) | 0.849 | MILE | 1,000.00 | 849.00 | | 0052 | 725-01-00100 | Temporary Detour Roads | 7,392.3 | SQYD | 150.00 | 1,108,845.00 | | 0053 | 727-01-00100 | Mobilization | 1 | LUMP | 2,280,000.00 | 2,280,000.00 | | 0054 | 729-16-00300 | Object Marker Assembly (Type 3) | 4 | EACH | 100.00 | 400.00 | | 0055 | 731-01-00100 | Nonreflectorized Raised Pavement Markers | 964 | EACH | 13.00 | 12,532.00 | | 0056 | 731-02-00100 | Reflectorized Raised Pavement Markers | 131 | EACH | 7.00 | 917.00 | | 0057 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 1.982 | MILE | 5,700.00 | 11,297.40 | | 0058 | 732-05-00100 | Removal of Existing Markings | 0.128 | MILE | 5,000.00 | 640.00 | | 0059 | 740-01-00100 | Construction Layout | 1 | LUMP | 250,000.00 | 250,000.00 | | 0060 | 803-01-00200 | Drilled Shaft (24" Diameter) | 72 | LNFT | 725.00 | 52,200.00 | | 0061 | 803-01-00800 | Drilled Shaft (60" Diameter) | 930 | LNFT | 1,600.00 | 1,488,000.00 | | 0062 | 803-02-00800 | Test Shaft (60" Diameter) | 85 | LNFT | 6,000.00 | 510,000.00 | | 0063 | 803-07-00800 | Bi-Directional Load Cell Test (60" Diameter) | 1 | EACH | 400,000.00 | 400,000.00 | | 0064 | 803-08-00800 | Crosshole Sonic Log Test (60" Diameter) | 15 | EACH | 12,500.00 | 187,500.00 | | 0065 | 803-09-00800 | Non-Destructive Test (60" Diameter) (Thermal Integrity Profiling) | 15 | EACH | 5,000.00 | 75,000.00 | | 0066 | 805-01-00200 | Class A1 Concrete (Deck) | 348.71 | CUYD | 1,800.00 | 627,678.00 | | 0067 | 805-01-00300 | Class A1 Concrete (Bent Cap) | 142.34 | CUYD | 3,000.00 | 427,020.00 | | 0068 | 805-01-00400 | Class A1 Concrete (Column) | 69.24 | CUYD | 2,500.00 | 173,100.00 | | 0069 | 805-18-00100 | Concrete Finish (Class 2 Rubbed Finish) | 3,948 | SQFT | 3.00 | 11,844.00 | | 0070 | 805-18-00200 | Concrete Finish (Class 3 Special Finish) | 9,478 | SQFT | 4.00 | 37,912.00 | | 0071 | 806-01-00100 | Deformed Reinforcing Steel | 158,827 | LB | 1.75 | 277,947.25 | | 0072 | 807-01-00400 | Structural Metalwork (Grade 50W) | 9,067 | LUMP | 158,000.00 | 158,000.00 | | 0073 | 807-01-00400 | Structural Metalwork (Grade 50W) (Department Furnished) | 639,852 | LUMP | 2,100,000.00 | 2,100,000.00 | | 0074 | 807-02-00100 | Structural Metalwork (Anchor Bolts) | 568 | LUMP | 50,000.00 | 50,000.00 | | 0075 | 810-01-00100 | Concrete Bridge Railing (Standard) | 658 | LNFT | 300.00 | 197,400.00 | | 0076 | 811-01-00100 | Cleaning and Painting (Structural Metalwork (Grade 50W) (Department Furnished)) | 5,277 | LUMP | 300,000.00 | 300,000.00 | | 0077 | 813-01-00100 | Concrete Approach Slabs (Cast-in-Place) | 3,200 | SQFT | 150.00 | 480,000.00 | | 0078 | 814-02-00100 | Elastomeric Bearing Pads (Reinforced) | 96 | SFIN | 1,200.00 | 115,200.00 | | 0079 | 815-02-00200 | Sealed Expansion Joint (End Dams and Preformed Silicone Seal) | 80 | LNFT | 800.00 | 64,000.00 | | 0080 | 816-02-00100 | Bridge End Drain System (Open Drain) | 4 | EACH | 25,000.00 | 100,000.00 | | 0081 | NS-500-00240 | Sawing and Sealing Transverse Joints in Asphalt Concrete Overlay | 240 | LNFT | 30.00 | 7,200.00 | | 0082 | NS-500-00260 | Sawcuts in Asphalt Concrete Lifts | 400 | LNFT | 10.00 | 4,000.00 | | 0083 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 1,000 | INLF | 6.00 | 6,000.00 | | 0084 | NS-700-00820 | Impact Attenuator Relocation (Construction Zone) | 4 | EACH | 2,500.00 | 10,000.00 | | 0085 | 109-01-10000 | Time Related Overhead | 1 | LUMP | 2,250,000.00 | 2,250,000.00 | | 0086 | 202-02-00030 | Removal of Temporary Sheeting | 1,429 | LNFT | 325.00 | 464,425.00 | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 22,825,912.55 |
|