Proposal:H.015285.6
Parish:Acadia, St. Landry
Routes:LA 755
Description:LA 755: LA 368 - LA 91
Type Construction:DRAINAGE STRUCTURES, MILLING ASPHALT PAVEMENT, LIME TREATMENT, IN-PLACE CEMENT TREATED SUBGRADE, IN-PLACE CEMENT STABILIZED BASE COURSE, PAVEMENT PATCHING, ASPHALT CONCRETE OVERLAY, AND RELATED WORK.
Estimated Construction Cost:$5,884,924.88
| Rank | License | Bidder | Construction Bid |
| 1 | 34356 | Prairie Contractors LLC | $5,630,554.33 |
| 2 | 51821 | Elliott Construction, LLC | $6,020,997.03 |
| 3 | 12312 | GILCHRIST CONSTRUCTION COMPANY, LLC | $6,891,176.30 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Prairie Contractors LLC | - 2 - Elliott Construction, LLC | - 3 - GILCHRIST CONSTRUCTION COMPANY, LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 202-02-02000 | Removal of Asphalt Drives | 588 | SQYD | 35.00 | 20,580.00 | 35.00 | 20,580.00 | 70.00 | 41,160.00 | | 0002 | 202-02-06100 | Removal of Concrete Walks and Drives | 524 | SQYD | 35.00 | 18,340.00 | 50.00 | 26,200.00 | 60.00 | 31,440.00 | | 0003 | 202-02-32100 | Removal of Pipe (Cross Drain) (24" RCP, 30" CMPA) | 34 | LNFT | 20.00 | 680.00 | 55.00 | 1,870.00 | 100.00 | 3,400.00 | | 0004 | 202-02-32100 | Removal of Pipe (Cross Drain) (24" RCP, 30" CMPA, 36" CMPA) | 112 | LNFT | 20.00 | 2,240.00 | 60.00 | 6,720.00 | 100.00 | 11,200.00 | | 0005 | 202-02-32100 | Removal of Pipe (Cross Drain) (42" RCP) | 12 | LNFT | 25.00 | 300.00 | 125.00 | 1,500.00 | 100.00 | 1,200.00 | | 0006 | 203-07-00100 | Borrow (Vehicular Measurement) | 500 | CUYD | 50.00 | 25,000.00 | 50.00 | 25,000.00 | 70.00 | 35,000.00 | | 0007 | 204-02-00100 | Temporary Hay Bales | 8 | EACH | 40.00 | 320.00 | 30.00 | 240.00 | 37.00 | 296.00 | | 0008 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 56 | EACH | 160.00 | 8,960.00 | 155.00 | 8,680.00 | 160.00 | 8,960.00 | | 0009 | 303-01-00300 | In-Place Cement Stabilized Base Course (10" Thick) | 55,531 | SQYD | 11.00 | 610,841.00 | 13.00 | 721,903.00 | 13.00 | 721,903.00 | | 0010 | 303-02-00100 | Removal of Existing Patches | 2,100 | SQYD | 15.00 | 31,500.00 | 15.00 | 31,500.00 | 30.00 | 63,000.00 | | 0011 | 304-01-00100 | Lime | 109 | TON | 550.00 | 59,950.00 | 400.00 | 43,600.00 | 325.00 | 35,425.00 | | 0012 | 304-05-00100 | Lime Treatment (Type E) | 13,883 | SQYD | 3.75 | 52,061.25 | 4.00 | 55,532.00 | 8.00 | 111,064.00 | | 0013 | 309-01-10000 | In-Place Cement Treated Subgrade (10" Thick) | 55,531 | SQYD | 9.55 | 530,321.05 | 11.00 | 610,841.00 | 13.00 | 721,903.00 | | 0014 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 1,867 | CUYD | 22.00 | 41,074.00 | 65.00 | 121,355.00 | 67.00 | 125,089.00 | | 0015 | 402-01-00101 | Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) | 525 | CUYD | 65.00 | 34,125.00 | 90.00 | 47,250.00 | 50.00 | 26,250.00 | | 0016 | 402-02-00101 | Traffic Maintenance Surfacing (Hard) | 48 | SQYD | 350.00 | 16,800.00 | 180.00 | 8,640.00 | 110.00 | 5,280.00 | | 0017 | 502-01-00100 | Asphalt Concrete | 16,473.3 | TON | 125.00 | 2,059,162.50 | 140.00 | 2,306,262.00 | 160.00 | 2,635,728.00 | | 0018 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 1,584.1 | TON | 92.00 | 145,737.20 | 200.00 | 316,820.00 | 160.00 | 253,456.00 | | 0019 | 509-01-00100 | Milling Asphalt Pavement | 67,573 | SQYD | 3.80 | 256,777.40 | 3.00 | 202,719.00 | 3.00 | 202,719.00 | | 0020 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -3,957 | CUYD | 0.01 | -39.57 | 0.01 | -39.57 | 1.00 | -3,957.00 | | 0021 | 510-01-00260 | Pavement Patching (16 inch Minimum Thickness) | 1,990 | SQYD | 188.00 | 374,120.00 | 195.00 | 388,050.00 | 200.00 | 398,000.00 | | 0022 | 701-02-01020 | Cross Drain Pipe Arch (30" Equiv. RCPA) | 140 | LNFT | 475.00 | 66,500.00 | 350.00 | 49,000.00 | 450.00 | 63,000.00 | | 0023 | 701-04-01060 | Storm Drain Pipe Arch (30" Equiv. RCPA) | 32 | LNFT | 425.00 | 13,600.00 | 210.00 | 6,720.00 | 850.00 | 27,200.00 | | 0024 | 701-10-01060 | Reinforced Concrete Pipe (Extension) (24") | 8 | LNFT | 400.00 | 3,200.00 | 500.00 | 4,000.00 | 1,600.00 | 12,800.00 | | 0025 | 701-10-01120 | Reinforced Concrete Pipe (Extension) (42") | 6 | LNFT | 650.00 | 3,900.00 | 700.00 | 4,200.00 | 2,000.00 | 12,000.00 | | 0026 | 701-15-00100 | Concrete Collar | 4 | EACH | 2,200.00 | 8,800.00 | 2,250.00 | 9,000.00 | 4,000.00 | 16,000.00 | | 0027 | 702-03-00100 | Catch Basins (CB-01) | 2 | EACH | 8,500.00 | 17,000.00 | 6,550.00 | 13,100.00 | 18,000.00 | 36,000.00 | | 0028 | 702-04-00150 | Adjusting Manholes w/Manhole Adjustment Rings | 5 | EACH | 2,000.00 | 10,000.00 | 500.00 | 2,500.00 | 1,000.00 | 5,000.00 | | 0029 | 706-02-00200 | Concrete Drive (6" Thick) | 627 | SQYD | 255.00 | 159,885.00 | 130.00 | 81,510.00 | 200.00 | 125,400.00 | | 0030 | 712-02-00100 | Sacked Concrete Revetment | 34 | SQYD | 700.00 | 23,800.00 | 250.00 | 8,500.00 | 2,800.00 | 95,200.00 | | 0031 | 712-04-00100 | Flexible Revetment | 21 | SQYD | 165.00 | 3,465.00 | 250.00 | 5,250.00 | 600.00 | 12,600.00 | | 0032 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 246,000.00 | 246,000.00 | 150,000.00 | 150,000.00 | 140,000.00 | 140,000.00 | | 0033 | 713-02-00100 | Temporary Pavement Markings (4" Width) | 5,940 | LNFT | 0.01 | 59.40 | 0.75 | 4,455.00 | 0.60 | 3,564.00 | | 0034 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 500 | LNFT | 0.01 | 5.00 | 1.00 | 500.00 | 0.30 | 150.00 | | 0035 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 382 | LNFT | 0.01 | 3.82 | 1.00 | 382.00 | 0.40 | 152.80 | | 0036 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 10.273 | MILE | 600.00 | 6,163.80 | 895.00 | 9,194.34 | 400.00 | 4,109.20 | | 0037 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 6.516 | MILE | 600.00 | 3,909.60 | 660.00 | 4,300.56 | 650.00 | 4,235.40 | | 0038 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 32.36 | MILE | 875.00 | 28,315.00 | 965.00 | 31,227.40 | 925.00 | 29,933.00 | | 0039 | 713-05-00220 | Temporary Pavement Legends & Symbols (Arrow - Left Turn) | 6 | EACH | 0.01 | 0.06 | 55.00 | 330.00 | 60.00 | 360.00 | | 0040 | 713-05-00230 | Temporary Pavement Legends & Symbols (Arrow - Right Turn) | 4 | EACH | 0.01 | 0.04 | 55.00 | 220.00 | 60.00 | 240.00 | | 0041 | 713-05-00300 | Temporary Pavement Legends & Symbols (ONLY) | 8 | EACH | 0.01 | 0.08 | 55.00 | 440.00 | 60.00 | 480.00 | | 0042 | 722-02-00100 | Project Site Laboratory (Equipped) | 1 | EACH | 30,000.00 | 30,000.00 | 15,000.00 | 15,000.00 | 20,000.00 | 20,000.00 | | 0043 | 724-02-00100 | Rumble Strips (Shoulder/Edge) | 7.646 | MILE | 1,200.00 | 9,175.20 | 1,100.00 | 8,410.60 | 1,100.00 | 8,410.60 | | 0044 | 726-01-00100 | Bedding Material | 40.7 | CUYD | 165.00 | 6,715.50 | 185.00 | 7,529.50 | 90.00 | 3,663.00 | | 0045 | 727-01-00100 | Mobilization | 1 | LUMP | 550,000.00 | 550,000.00 | 500,000.00 | 500,000.00 | 680,000.00 | 680,000.00 | | 0046 | 729-16-00200 | Object Marker Assembly (Type 2) | 32 | EACH | 100.00 | 3,200.00 | 85.00 | 2,720.00 | 105.00 | 3,360.00 | | 0047 | 729-16-00300 | Object Marker Assembly (Type 3) | 12 | EACH | 150.00 | 1,800.00 | 95.00 | 1,140.00 | 105.00 | 1,260.00 | | 0048 | 731-02-00100 | Reflectorized Raised Pavement Markers | 1,616 | EACH | 7.00 | 11,312.00 | 7.00 | 11,312.00 | 7.00 | 11,312.00 | | 0049 | 732-01-01000 | Plastic Pavement Striping (4" Width) (Thermoplastic 90 mil) | 2,970 | LNFT | 1.50 | 4,455.00 | 1.25 | 3,712.50 | 1.25 | 3,712.50 | | 0050 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 250 | LNFT | 3.50 | 875.00 | 3.50 | 875.00 | 3.25 | 812.50 | | 0051 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 191 | LNFT | 15.00 | 2,865.00 | 14.50 | 2,769.50 | 14.00 | 2,674.00 | | 0052 | 732-01-05000 | Plastic Pavement Striping (Dotted Line)(4" W)(2' L)(Thermo 125 mil) | 309 | LNFT | 1.50 | 463.50 | 1.50 | 463.50 | 1.50 | 463.50 | | 0053 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 16.18 | MILE | 5,000.00 | 80,900.00 | 4,750.00 | 76,855.00 | 4,500.00 | 72,810.00 | | 0054 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 3.258 | MILE | 1,750.00 | 5,701.50 | 1,650.00 | 5,375.70 | 1,600.00 | 5,212.80 | | 0055 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 3 | EACH | 375.00 | 1,125.00 | 330.00 | 990.00 | 325.00 | 975.00 | | 0056 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 2 | EACH | 375.00 | 750.00 | 330.00 | 660.00 | 325.00 | 650.00 | | 0057 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 4 | EACH | 425.00 | 1,700.00 | 385.00 | 1,540.00 | 375.00 | 1,500.00 | | 0058 | 735-01-00100 | Mailboxes | 86 | EACH | 10.00 | 860.00 | 22.00 | 1,892.00 | 30.00 | 2,580.00 | | 0059 | 735-02-00100 | Mailbox Supports (Single) | 86 | EACH | 325.00 | 27,950.00 | 275.00 | 23,650.00 | 275.00 | 23,650.00 | | 0060 | 739-01-00100 | Hydro-Seeding | 0.07 | ACRE | 75,000.00 | 5,250.00 | 15,000.00 | 1,050.00 | 17,000.00 | 1,190.00 | | 0061 | 740-01-00100 | Construction Layout | 1 | LUMP | 2,000.00 | 2,000.00 | 25,000.00 | 25,000.00 | 30,000.00 | 30,000.00 | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 5,630,554.33 | | 6,020,997.03 | | 6,891,176.30 |
|