Proposal:H.014780.6
Parish:Lafourche
Routes:LA 3266
Description:LA 3266: LA 308 - FORTY ARPENT RD
Type Construction:GRADING, MILLING ASPHALT CONCRETE, IN-PLACE SLAG STABILIZED BCS BASE COURSE, CLASS II BASE COURSE, ASPHALT CONCRETE OVERLAY, AND RELATED WORK.
Estimated Construction Cost:$3,694,395.80
| Rank | License | Bidder | Construction Bid |
| 1 | 73475 | Madden Gulf Coast, LLC | $1,955,810.13 |
| 2 | 00046 | Barber Bros. Contracting Co., L.L.C | $2,244,008.10 |
| 3 | 06276 | Barriere Construction Co., LLC | $2,435,156.96 |
| 4 | 62139 | Huey P. Stockstill, LLC | $2,835,425.83 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Madden Gulf Coast, LLC | - 2 - Barber Bros. Contracting Co., L.L.C | - 3 - Barriere Construction Co., LLC | - 4 - Huey P. Stockstill, LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 202-02-38300 | Removal of Sign and U-Channel Post | 12 | EACH | 25.00 | 300.00 | 25.00 | 300.00 | 128.00 | 1,536.00 | 130.00 | 1,560.00 | | 0002 | 203-01-00100 | General Excavation | 291 | CUYD | 50.00 | 14,550.00 | 20.00 | 5,820.00 | 85.00 | 24,735.00 | 175.00 | 50,925.00 | | 0003 | 203-03-00100 | Embankment | 481 | CUYD | 57.00 | 27,417.00 | 20.00 | 9,620.00 | 82.00 | 39,442.00 | 45.00 | 21,645.00 | | 0004 | 203-07-00100 | Borrow (Vehicular Measurement) | 230 | CUYD | 102.00 | 23,460.00 | 75.00 | 17,250.00 | 300.00 | 69,000.00 | 105.00 | 24,150.00 | | 0005 | 302-02-08070 | Class II Base Course (8" Thick) (Crushed Stone or Recycled Portland Cement Concrete) | 530.3 | SQYD | 40.00 | 21,212.00 | 65.00 | 34,469.50 | 82.00 | 43,484.60 | 130.00 | 68,939.00 | | 0006 | 502-01-00100 | Asphalt Concrete | 10,561.1 | TON | 102.00 | 1,077,232.20 | 137.00 | 1,446,870.70 | 117.00 | 1,235,648.70 | 155.00 | 1,636,970.50 | | 0007 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 209.5 | TON | 166.00 | 34,777.00 | 225.00 | 47,137.50 | 351.00 | 73,534.50 | 280.00 | 58,660.00 | | 0008 | 509-01-00100 | Milling Asphalt Pavement | 30,042 | SQYD | 1.80 | 54,075.60 | 4.00 | 120,168.00 | 3.75 | 112,657.50 | 3.25 | 97,636.50 | | 0009 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -1,462 | CUYD | 0.01 | -14.62 | 0.00 | 0.00 | 0.10 | -146.20 | 0.01 | -14.62 | | 0010 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 138,000.00 | 138,000.00 | 75,000.00 | 75,000.00 | 190,000.00 | 190,000.00 | 100,000.00 | 100,000.00 | | 0011 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 570 | LNFT | 0.50 | 285.00 | 0.20 | 114.00 | 0.50 | 285.00 | 0.50 | 285.00 | | 0012 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 1,898 | LNFT | 0.50 | 949.00 | 0.75 | 1,423.50 | 0.50 | 949.00 | 0.50 | 949.00 | | 0013 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 2.592 | MILE | 350.00 | 907.20 | 350.00 | 907.20 | 1,100.00 | 2,851.20 | 225.00 | 583.20 | | 0014 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 2.05 | MILE | 750.00 | 1,537.50 | 600.00 | 1,230.00 | 751.00 | 1,539.55 | 750.00 | 1,537.50 | | 0015 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 6.26 | MILE | 1,250.00 | 7,825.00 | 900.00 | 5,634.00 | 1,251.00 | 7,831.26 | 1,250.00 | 7,825.00 | | 0016 | 713-05-00200 | Temporary Pavement Legends & Symbols (Arrow - Double) | 4 | EACH | 50.00 | 200.00 | 20.00 | 80.00 | 51.00 | 204.00 | 35.00 | 140.00 | | 0017 | 713-05-00220 | Temporary Pavement Legends & Symbols (Arrow - Left Turn) | 34 | EACH | 50.00 | 1,700.00 | 20.00 | 680.00 | 51.00 | 1,734.00 | 35.00 | 1,190.00 | | 0018 | 713-05-00230 | Temporary Pavement Legends & Symbols (Arrow - Right Turn) | 4 | EACH | 50.00 | 200.00 | 20.00 | 80.00 | 51.00 | 204.00 | 35.00 | 140.00 | | 0019 | 713-05-00300 | Temporary Pavement Legends & Symbols (ONLY) | 4 | EACH | 50.00 | 200.00 | 40.00 | 160.00 | 51.00 | 204.00 | 35.00 | 140.00 | | 0020 | 716-01-00100 | Mulch (Vegetative) | 1.5 | TON | 1,500.00 | 2,250.00 | 2,000.00 | 3,000.00 | 1,310.00 | 1,965.00 | 1,500.00 | 2,250.00 | | 0021 | 717-01-00100 | Seeding | 27 | LB | 25.00 | 675.00 | 29.00 | 783.00 | 21.00 | 567.00 | 25.00 | 675.00 | | 0022 | 718-01-00100 | Fertilizer | 900 | LB | 1.00 | 900.00 | 1.60 | 1,440.00 | 0.80 | 720.00 | 1.15 | 1,035.00 | | 0023 | 727-01-00100 | Mobilization | 1 | LUMP | 180,500.00 | 180,500.00 | 105,000.00 | 105,000.00 | 95,000.00 | 95,000.00 | 283,500.00 | 283,500.00 | | 0024 | 729-16-00300 | Object Marker Assembly (Type 3) | 12 | EACH | 85.00 | 1,020.00 | 90.00 | 1,080.00 | 100.00 | 1,200.00 | 110.00 | 1,320.00 | | 0025 | 729-19-00300 | Dead End Road Installations (Type C) | 2 | EACH | 950.00 | 1,900.00 | 1,000.00 | 2,000.00 | 1,400.00 | 2,800.00 | 1,500.00 | 3,000.00 | | 0026 | 731-02-00100 | Reflectorized Raised Pavement Markers | 1,810 | EACH | 7.00 | 12,670.00 | 4.20 | 7,602.00 | 7.50 | 13,575.00 | 8.00 | 14,480.00 | | 0027 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 285 | LNFT | 3.00 | 855.00 | 3.20 | 912.00 | 3.05 | 869.25 | 3.50 | 997.50 | | 0028 | 732-01-01080 | Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) | 910 | LNFT | 10.00 | 9,100.00 | 10.50 | 9,555.00 | 10.25 | 9,327.50 | 11.50 | 10,465.00 | | 0029 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 62 | LNFT | 12.00 | 744.00 | 12.60 | 781.20 | 12.10 | 750.20 | 14.25 | 883.50 | | 0030 | 732-01-05200 | Plastic Pavement Striping (Dotted Line)(8" W)(2' L)(Thermo 125 mil) | 495 | LNFT | 3.00 | 1,485.00 | 3.00 | 1,485.00 | 3.10 | 1,534.50 | 3.25 | 1,608.75 | | 0031 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 3.13 | MILE | 5,000.00 | 15,650.00 | 3,700.00 | 11,581.00 | 5,100.00 | 15,963.00 | 6,000.00 | 18,780.00 | | 0032 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 1.025 | MILE | 1,250.00 | 1,281.25 | 1,300.00 | 1,332.50 | 1,250.00 | 1,281.25 | 1,450.00 | 1,486.25 | | 0033 | 732-04-01040 | Plastic Pavement Legends and Symbols (Arrow - Double) | 2 | EACH | 300.00 | 600.00 | 315.00 | 630.00 | 301.00 | 602.00 | 350.00 | 700.00 | | 0034 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 17 | EACH | 300.00 | 5,100.00 | 315.00 | 5,355.00 | 301.00 | 5,117.00 | 350.00 | 5,950.00 | | 0035 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 2 | EACH | 300.00 | 600.00 | 315.00 | 630.00 | 301.00 | 602.00 | 350.00 | 700.00 | | 0036 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 2 | EACH | 300.00 | 600.00 | 315.00 | 630.00 | 301.00 | 602.00 | 350.00 | 700.00 | | 0037 | 740-01-00100 | Construction Layout | 1 | LUMP | 6,800.00 | 6,800.00 | 15,000.00 | 15,000.00 | 30,000.00 | 30,000.00 | 28,300.00 | 28,300.00 | | 0038 | NS-303-00008 | In-Place Slag Stabilized BCS Base Course 8.0" Thick | 30,826.7 | SQYD | 10.00 | 308,267.00 | 10.00 | 308,267.00 | 14.50 | 446,987.15 | 12.50 | 385,333.75 | | | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 1,955,810.13 | | 2,244,008.10 | | 2,435,156.96 | | 2,835,425.83 |
|