Bid Tabulations for the Letting of 10/9/2024 LA DOTD Headquarters

Proposal:H.015884.6
Parish:St. Charles
Routes:US 90
Description:US 90: LA 3060 - 1560' W JEFFERSON P/L
Type Construction:MILLING ASPHALT CONCRETE, PAVEMENT PATCHING, ASPAHLT CONCRETE OVERLAY, LOOP DETECTORS, AND RELATED WORK.
Estimated Construction Cost:$4,987,674.45
Rank License BidderConstruction Bid
106276Barriere Construction Co., LLC$3,222,762.95
273475Madden Gulf Coast, LLC$3,544,807.43
362139Huey P. Stockstill, LLC$4,068,791.36
402179Boh Bros. Construction Co., LLC.$5,128,728.88


Line
Number
Item NumberItem DescriptionQuantityUnit of
Measure
- 1 -
Barriere Construction Co., LLC
- 2 -
Madden Gulf Coast, LLC
- 3 -
Huey P. Stockstill, LLC
- 4 -
Boh Bros. Construction Co., LLC.
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001202-02-02020Removal of Asphalt Pavement 325.4   SQYD98.0031,889.2026.008,460.4022.007,158.8015.004,881.00
0002202-02-06120Removal of Curbs (Asphalt) 185     LNFT65.0012,025.0040.007,400.0025.004,625.0030.005,550.00
0003202-02-06140Removal of Curbs (Concrete) 30     LNFT45.001,350.0026.00780.0060.001,800.0075.002,250.00
0004202-02-14500Removal of Guard Rail 1,086     LNFT12.0013,032.0018.0019,548.0014.5015,747.008.008,688.00
0005203-07-00100Borrow (Vehicular Measurement) 1,820     CUYD37.0067,340.00103.00187,460.0020.0036,400.0015.0027,300.00
0006502-01-00100Asphalt Concrete 14,054.5   TON118.001,658,431.00118.001,658,431.00160.002,248,720.00160.002,248,720.00
0007502-01-00200Asphalt Concrete, Drives, Turnouts and Miscellaneous 467.3   TON278.00129,909.40354.00165,424.20240.00112,152.00195.0091,123.50
0008509-01-00100Milling Asphalt Pavement 127,727     SQYD2.60332,090.202.00255,454.003.00383,181.006.00766,362.00
0009509-02-00100Contractor Retained Reclaimed Asphalt Pavement -5,319     CUYD0.10-531.900.01-53.190.01-53.190.03-159.57
0010510-01-00400Pavement Patching (24" Minimum Thickness) 698     SQYD243.00169,614.00294.00205,212.00240.00167,520.00275.00191,950.00
0011704-01-01020Guard Rail (Single Thrie Beam) (6'-3" post spacing) 118     LNFT75.008,850.0046.505,487.0092.0010,856.0050.005,900.00
0012704-03-00100Blocked Out Guard rail 31.25  LNFT35.001,093.7527.00843.7538.001,187.5030.00937.50
0013704-03-00200Blocked Out Guard Rail - 31", (6'-3" Post Spacing) 862.5   LNFT40.0034,500.0027.0023,287.5045.0038,812.5030.0025,875.00
0014704-05-00100Guard Rail Anchor Sections (Trailing End) 6.25  LNFT25.00156.25165.001,031.2530.00187.50200.001,250.00
0015704-05-00300Guard Rail Anchor Sections - 31", (Trailing End) 49.5   LNFT125.006,187.50195.009,652.50135.006,682.50225.0011,137.50
0016704-07-00200Guard Rail Transitions (Double Thrie Beam) 50     LNFT150.007,500.00110.005,500.00135.006,750.00125.006,250.00
0017704-10-00205Guard Rail End Treatment, MASH, (TL-3 Tangent) 3     EACH3,500.0010,500.003,550.0010,650.004,000.0012,000.004,000.0012,000.00
0018704-10-00310Guard Rail End Treatment, NCHRP 350 - 31" (TL-3 Flared) 2     EACH3,000.006,000.003,150.006,300.003,250.006,500.003,500.007,000.00
0019706-03-00700Incidental Concrete Paving (10" Thick) 6.7   SQYD111.00743.70300.002,010.00600.004,020.00400.002,680.00
0020707-01-00100Concrete Curb 30     LNFT128.003,840.00200.006,000.0070.002,100.00150.004,500.00
0021707-04-00100Asphalt Curb 210     LNFT80.0016,800.00157.0032,970.00150.0031,500.00100.0021,000.00
0022713-01-00100Temporary Signs and Barricades 1     LUMP285,000.00285,000.00277,000.00277,000.00215,000.00215,000.00750,000.00750,000.00
0023713-02-00300Temporary Pavement Markings (8" Width) 3,521     LNFT0.25880.250.25880.250.451,584.450.501,760.50
0024713-02-00500Temporary Pavement Markings (24" Width) 2,302     LNFT0.501,151.000.451,035.901.002,302.001.252,877.50
0025713-03-01000Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) 15.784 MILE115.001,815.16400.006,313.60150.002,367.60400.006,313.60
0026713-03-02000Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) 15.784 MILE601.009,486.18600.009,470.40750.0011,838.00800.0012,627.20
0027713-04-01000Temporary Pavement Markings (Solid Line) (4" Width) 34.948 MILE901.0031,488.15900.0031,453.20950.0033,200.601,000.0034,948.00
0028713-05-00220Temporary Pavement Legends & Symbols (Arrow - Left Turn) 8     EACH25.00200.0025.00200.0025.00200.0060.00480.00
0029713-05-00230Temporary Pavement Legends & Symbols (Arrow - Right Turn) 4     EACH25.00100.0025.00100.0025.00100.0060.00240.00
0030716-01-00100Mulch (Vegetative) 10.3   TON596.006,138.80596.956,148.59600.006,180.00650.006,695.00
0031717-01-00100Seeding 309     LB1.45448.051.42438.781.40432.601.75540.75
0032718-01-00100Fertilizer 5,156     LB0.854,382.600.854,382.600.854,382.601.005,156.00
0033724-02-00100Rumble Strips (Shoulder/Edge) 7.666 MILE281.002,154.15280.002,146.48725.005,557.85400.003,066.40
0034727-01-00100Mobilization 1     LUMP140,000.00140,000.00350,000.00350,000.00400,000.00400,000.00500,000.00500,000.00
0035729-16-00300Object Marker Assembly (Type 3) 13     EACH95.001,235.0085.001,105.0014.00182.00100.001,300.00
0036731-02-00100Reflectorized Raised Pavement Markers 1,967     EACH5.009,835.004.508,851.508.2516,227.758.0015,736.00
0037732-01-01040Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) 1,761     LNFT3.005,283.003.005,283.003.506,163.503.506,163.50
0038732-01-01080Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) 1,067     LNFT18.0019,206.0018.0019,206.0012.2513,070.7512.0012,804.00
0039732-01-02080Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) 84     LNFT23.101,940.4023.001,932.0018.501,554.0017.001,428.00
0040732-02-02000Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) 18.608 MILE4,500.0083,736.004,500.0083,736.004,100.0076,292.804,500.0083,736.00
0041732-03-02000Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) 7.325 MILE1,205.008,826.631,200.008,790.001,350.009,888.751,500.0010,987.50
0042732-03-02030Plastic Pavement Striping (Dotted Line)(8" W)(2' L)(Thermo 90 mil) 0.08  MILE12,500.001,000.0012,500.001,000.0010,500.00840.0012,000.00960.00
0043732-03-02102Plastic Pav't Striping (Broken) (4" W) (Preformed Tape Retroreflectivity I or Thermo 90 mil)(Black and White Contrast) 1.134 MILE3,500.003,969.003,500.003,969.005,500.006,237.006,000.006,804.00
0044732-04-01080Plastic Pavement Legends and Symbols (Arrow - Left Turn) 4     EACH400.001,600.00400.001,600.00425.001,700.00475.001,900.00
0045732-04-01100Plastic Pavement Legends and Symbols (Arrow - Right Turn) 2     EACH400.00800.00400.00800.00425.00850.00475.00950.00
0046732-05-00100Removal of Existing Markings 1.423 MILE5,000.007,115.005,000.007,115.007,500.0010,672.5010,000.0014,230.00
0047736-01-00100Trenching and Backfilling 24     LNFT14.00336.0013.97335.2816.50396.0025.00600.00
0048736-09-00100Loop Detector 546     LNFT30.0016,380.0029.7816,259.8835.0019,110.0035.0019,110.00
0049736-10-00200Underground Junction Box (Type E) 4     EACH1,460.005,840.001,452.525,810.081,750.007,000.001,750.007,000.00
0050736-11-00050Conduit (1/2" HDPE, Schedule 80) 24     LNFT4.0296.484.0296.484.75114.005.00120.00
0051740-01-00100Construction Layout 1     LUMP9,000.009,000.0025,000.0025,000.0025,000.0025,000.0080,000.0080,000.00
0052NS-700-00830Impact Attenuator (Reusable, Test Level 2) 1     EACH22,000.0022,000.0023,500.0023,500.0027,500.0027,500.0025,000.0025,000.00
0053NS-713-00009Portable Changeable Message Sign (with communications) 2     EACH10,000.0020,000.006,000.0012,000.0020,000.0040,000.0025,000.0050,000.00
0054NS-719-00002Tree Trimming 1     LUMP10,000.0010,000.0017,000.0017,000.0025,000.0025,000.0020,000.0020,000.00
             
  CONTRACTOR TOTAL   3,222,762.95 3,544,807.43 4,068,791.36 5,128,728.88