Proposal:H.015233.6
Parish:Lincoln
Routes:LA 823
Description:LA 823: DRAINAGE IMPROVEMENTS
Type Construction:MILLING ASPHALT CONCRETE, ASPHALT CONCRETE PAVEMENT, AND RELATED WORK.
Estimated Construction Cost:$451,194.46
| Rank | License | Bidder | Construction Bid |
| 1 | 12487 | Diamond B Construction Co., L.L.C. | $394,839.63 |
| 2 | 15099 | Amethyst Construction, Inc. | $397,578.65 |
| 3 | 05789 | D & J CONSTRUCTION CO., LLC | $415,570.05 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Diamond B Construction Co., L.L.C. | - 2 - Amethyst Construction, Inc. | - 3 - D & J CONSTRUCTION CO., LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 203-07-00100 | Borrow (Vehicular Measurement) | 643 | CUYD | 20.00 | 12,860.00 | 50.00 | 32,150.00 | 45.00 | 28,935.00 | | 0002 | 204-06-00100 | Temporary Silt Fencing | 2,284 | LNFT | 3.00 | 6,852.00 | 3.50 | 7,994.00 | 3.00 | 6,852.00 | | 0003 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 72 | CUYD | 375.00 | 27,000.00 | 220.00 | 15,840.00 | 200.00 | 14,400.00 | | 0004 | 502-01-00100 | Asphalt Concrete | 931.4 | TON | 236.00 | 219,810.40 | 245.00 | 228,193.00 | 255.00 | 237,507.00 | | 0005 | 509-01-00100 | Milling Asphalt Pavement | 285 | SQYD | 89.00 | 25,365.00 | 25.00 | 7,125.00 | 35.00 | 9,975.00 | | 0006 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -8 | CUYD | 0.55 | -4.40 | 1.00 | -8.00 | 1.00 | -8.00 | | 0007 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 10,000.00 | 10,000.00 | 35,000.00 | 35,000.00 | 48,000.00 | 48,000.00 | | 0008 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 1.463 | MILE | 175.00 | 256.03 | 1,500.00 | 2,194.50 | 250.00 | 365.75 | | 0009 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 5.852 | MILE | 1,100.00 | 6,437.20 | 950.00 | 5,559.40 | 900.00 | 5,266.80 | | 0010 | 716-01-00100 | Mulch (Vegetative) | 1.2 | TON | 950.00 | 1,140.00 | 1,500.00 | 1,800.00 | 800.00 | 960.00 | | 0011 | 717-01-00100 | Seeding | 37 | LB | 60.00 | 2,220.00 | 30.00 | 1,110.00 | 16.00 | 592.00 | | 0012 | 718-01-00100 | Fertilizer | 636 | LB | 1.25 | 795.00 | 2.50 | 1,590.00 | 1.00 | 636.00 | | 0013 | 727-01-00100 | Mobilization | 1 | LUMP | 64,500.00 | 64,500.00 | 35,000.00 | 35,000.00 | 41,000.00 | 41,000.00 | | 0014 | 731-02-00100 | Reflectorized Raised Pavement Markers | 55 | EACH | 7.00 | 385.00 | 8.00 | 440.00 | 10.00 | 550.00 | | 0015 | 731-03-00100 | Removal of Raised Pavement Markers | 0.209 | MILE | 600.00 | 125.40 | 750.00 | 156.75 | 2,500.00 | 522.50 | | 0016 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 0.836 | MILE | 5,500.00 | 4,598.00 | 6,500.00 | 5,434.00 | 6,000.00 | 5,016.00 | | 0017 | 740-01-00100 | Construction Layout | 1 | LUMP | 12,500.00 | 12,500.00 | 18,000.00 | 18,000.00 | 15,000.00 | 15,000.00 | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 394,839.63 | | 397,578.65 | | 415,570.05 |
|