Proposal:H.014904.6
Parish:Morehouse
Routes:LA 138, US 165, US 425
Description:US 425: UP RR XING (MER ROUGE)
Type Construction:DRAINAGE STRUCTURES, MILLING ASPHALT CONCRETE, ASPHALT CONCRETE OVERLAY, AND RELATED WORK.
Estimated Construction Cost:$260,924.10
| Rank | License | Bidder | Construction Bid |
| 1 | 05789 | D & J CONSTRUCTION CO., LLC | $420,191.70 |
| 2 | 15099 | Amethyst Construction, Inc. | $428,583.90 |
| 3 | 12487 | Diamond B Construction Co., L.L.C. | $699,919.72 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - D & J CONSTRUCTION CO., LLC | - 2 - Amethyst Construction, Inc. | - 3 - Diamond B Construction Co., L.L.C. | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 202-02-03030 | Removal of Pavement Structure | 43.7 | SQYD | 30.00 | 1,311.00 | 150.00 | 6,555.00 | 650.00 | 28,405.00 | | 0002 | 202-02-06060 | Removal of Concrete Catch Basin | 1 | EACH | 2,000.00 | 2,000.00 | 6,500.00 | 6,500.00 | 12,000.00 | 12,000.00 | | 0003 | 202-02-06100 | Removal of Concrete Walks and Drives | 31 | SQYD | 42.00 | 1,302.00 | 95.00 | 2,945.00 | 45.00 | 1,395.00 | | 0004 | 202-02-06140 | Removal of Curbs (Concrete) | 12 | LNFT | 65.00 | 780.00 | 110.00 | 1,320.00 | 45.00 | 540.00 | | 0005 | 202-02-32100 | Removal of Pipe (Cross Drain) Cross Drain Pipe 18" RCP | 40 | LNFT | 85.00 | 3,400.00 | 95.00 | 3,800.00 | 45.00 | 1,800.00 | | 0006 | 203-07-00100 | Borrow (Vehicular Measurement) | 10 | CUYD | 75.00 | 750.00 | 250.00 | 2,500.00 | 35.00 | 350.00 | | 0007 | 204-06-00100 | Temporary Silt Fencing | 120 | LNFT | 7.00 | 840.00 | 10.00 | 1,200.00 | 10.00 | 1,200.00 | | 0008 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 16 | CUYD | 100.00 | 1,600.00 | 225.00 | 3,600.00 | 95.00 | 1,520.00 | | 0009 | 402-02-00101 | Traffic Maintenance Surfacing (Hard) | 23 | SQYD | 100.00 | 2,300.00 | 225.00 | 5,175.00 | 800.00 | 18,400.00 | | 0010 | 502-01-00100 | Asphalt Concrete | 408.5 | TON | 420.00 | 171,570.00 | 340.00 | 138,890.00 | 600.00 | 245,100.00 | | 0011 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 29.5 | TON | 420.00 | 12,390.00 | 350.00 | 10,325.00 | 1,100.00 | 32,450.00 | | 0012 | 509-01-00100 | Milling Asphalt Pavement | 1,833 | SQYD | 20.00 | 36,660.00 | 15.00 | 27,495.00 | 16.00 | 29,328.00 | | 0013 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -102 | CUYD | 1.00 | -102.00 | 1.00 | -102.00 | 1.00 | -102.00 | | 0014 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 25 | SQYD | 325.00 | 8,125.00 | 305.00 | 7,625.00 | 850.00 | 21,250.00 | | 0015 | 701-01-00900 | Cross Drain Pipe (18" RCP) | 48 | LNFT | 400.00 | 19,200.00 | 500.00 | 24,000.00 | 400.00 | 19,200.00 | | 0016 | 702-03-00100 | Catch Basins (CB-01) | 1 | EACH | 5,500.00 | 5,500.00 | 14,500.00 | 14,500.00 | 15,000.00 | 15,000.00 | | 0017 | 702-04-00300 | Adjusting Junction Boxes | 1 | EACH | 4,000.00 | 4,000.00 | 4,500.00 | 4,500.00 | 12,000.00 | 12,000.00 | | 0018 | 706-04-00110 | Curb Ramps TYPE 8 | 31 | SQYD | 200.00 | 6,200.00 | 200.00 | 6,200.00 | 1,100.00 | 34,100.00 | | 0019 | 707-01-00100 | Concrete Curb | 12 | LNFT | 175.00 | 2,100.00 | 225.00 | 2,700.00 | 105.00 | 1,260.00 | | 0020 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 65,000.00 | 65,000.00 | 65,000.00 | 65,000.00 | 69,000.00 | 69,000.00 | | 0021 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 62 | LNFT | 1.00 | 62.00 | 0.95 | 58.90 | 0.75 | 46.50 | | 0022 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 0.019 | MILE | 300.00 | 5.70 | 6,500.00 | 123.50 | 85.00 | 1.62 | | 0023 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 0.148 | MILE | 2,500.00 | 370.00 | 1,500.00 | 222.00 | 1,500.00 | 222.00 | | 0024 | 724-02-00100 | Rumble Strips (Shoulder/Edge) | 0.068 | MILE | 3,500.00 | 238.00 | 3,000.00 | 204.00 | 3,000.00 | 204.00 | | 0025 | 726-01-00100 | Bedding Material | 18.7 | CUYD | 250.00 | 4,675.00 | 225.00 | 4,207.50 | 185.00 | 3,459.50 | | 0026 | 727-01-00100 | Mobilization | 1 | LUMP | 42,000.00 | 42,000.00 | 40,000.00 | 40,000.00 | 69,000.00 | 69,000.00 | | 0027 | 729-16-00200 | Object Marker Assembly (Type 2) | 1 | EACH | 350.00 | 350.00 | 450.00 | 450.00 | 185.00 | 185.00 | | 0028 | 731-02-00100 | Reflectorized Raised Pavement Markers | 6 | EACH | 60.00 | 360.00 | 70.00 | 420.00 | 60.00 | 360.00 | | 0029 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 62 | LNFT | 50.00 | 3,100.00 | 75.00 | 4,650.00 | 45.00 | 2,790.00 | | 0030 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 0.148 | MILE | 20,000.00 | 2,960.00 | 19,000.00 | 2,812.00 | 10,000.00 | 1,480.00 | | 0031 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.019 | MILE | 5,000.00 | 95.00 | 12,000.00 | 228.00 | 2,900.00 | 55.10 | | 0032 | 740-01-00100 | Construction Layout | 1 | LUMP | 12,000.00 | 12,000.00 | 35,000.00 | 35,000.00 | 69,000.00 | 69,000.00 | | 0033 | 741-35-00100 | Adjust Valve or Meter Box | 1 | EACH | 3,000.00 | 3,000.00 | 1,850.00 | 1,850.00 | 6,500.00 | 6,500.00 | | 0034 | NS-500-00360 | Saw Cutting Asphalt Concrete Pavement Over Portland Cement Concrete Composite Pavement | 1,210 | INLF | 5.00 | 6,050.00 | 3.00 | 3,630.00 | 2.00 | 2,420.00 | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 420,191.70 | | 428,583.90 | | 699,919.72 |
|