Proposal:H.014334.6
Parish:Jefferson
Description:BONNABEL BLVD: METAIRIE RD - I-10
Type Construction:MILLING ASPHALT PAVEMENT, PAVEMENT PATCHING, CLASS II BASE COURSE, ASPHALT CONCRETE PAVEMENT, ROADWAY REINFORCING MESH, ROADWAY JOINT REINFORCING COMPOSITE MEMBRANE, LOOP DETECTOR, AND RELATED WORK.
Estimated Construction Cost:$2,663,777.73
| Rank | License | Bidder | Construction Bid |
| 1 | 06276 | Barriere Construction Co., LLC | $3,081,793.29 |
| 2 | 02179 | Boh Bros. Construction Co., LLC. | $3,143,063.65 |
| 3 | 73475 | Madden Gulf Coast, LLC | $3,234,848.65 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Barriere Construction Co., LLC | - 2 - Boh Bros. Construction Co., LLC. | - 3 - Madden Gulf Coast, LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 202-02-06100 | Removal of Concrete Walks and Drives | 829 | SQYD | 30.00 | 24,870.00 | 30.00 | 24,870.00 | 28.00 | 23,212.00 | | 0002 | 202-02-06140 | Removal of Curbs (Concrete) | 482 | LNFT | 27.00 | 13,014.00 | 6.00 | 2,892.00 | 9.00 | 4,338.00 | | 0003 | 203-01-00100 | General Excavation | 50 | CUYD | 73.00 | 3,650.00 | 150.00 | 7,500.00 | 165.00 | 8,250.00 | | 0004 | 203-07-00100 | Borrow (Vehicular Measurement) | 8 | CUYD | 30.00 | 240.00 | 200.00 | 1,600.00 | 1,000.00 | 8,000.00 | | 0005 | 302-02-08070 | Class II Base Course (8" Thick) (Crushed Stone or Recycled Portland Cement Concrete) | 232.6 | SQYD | 122.00 | 28,377.20 | 115.00 | 26,749.00 | 109.00 | 25,353.40 | | 0006 | 502-01-00100 | Asphalt Concrete | 5,249.9 | TON | 173.00 | 908,232.70 | 165.00 | 866,233.50 | 200.00 | 1,049,980.00 | | 0007 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 55.1 | TON | 575.00 | 31,682.50 | 400.00 | 22,040.00 | 400.00 | 22,040.00 | | 0008 | 509-01-00100 | Milling Asphalt Pavement | 25,391 | SQYD | 8.30 | 210,745.30 | 5.00 | 126,955.00 | 11.00 | 279,301.00 | | 0009 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -2,610 | CUYD | 10.00 | -26,100.00 | 0.01 | -26.10 | 0.01 | -26.10 | | 0010 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 1,653 | SQYD | 122.00 | 201,666.00 | 200.00 | 330,600.00 | 171.00 | 282,663.00 | | 0011 | 602-02-00200 | Cleaning and Resealing Existing Longitudinal Pavement Joints | 14,300 | LNFT | 5.00 | 71,500.00 | 5.50 | 78,650.00 | 4.00 | 57,200.00 | | 0012 | 602-02-00300 | Cleaning and Resealing Existing Transverse Pavements Joints | 11,400 | LNFT | 5.00 | 57,000.00 | 5.50 | 62,700.00 | 4.00 | 45,600.00 | | 0013 | 602-03-00100 | Cleaning and Sealing Random Cracks | 2,000 | LNFT | 5.00 | 10,000.00 | 5.50 | 11,000.00 | 5.25 | 10,500.00 | | 0014 | 602-16-00101 | High Early Strength (HES) Concrete Pavement Full Depth Patching | 662.3 | SQYD | 500.00 | 331,150.00 | 225.00 | 149,017.50 | 168.00 | 111,266.40 | | 0015 | 702-02-00001 | Manhole (Remove and Replace Frame and Cover) | 2 | EACH | 1,830.00 | 3,660.00 | 1,500.00 | 3,000.00 | 1,420.00 | 2,840.00 | | 0016 | 702-03-00001 | Catch Basin (Remove and Replace Frame and Cover) | 3 | EACH | 3,550.00 | 10,650.00 | 2,500.00 | 7,500.00 | 1,975.00 | 5,925.00 | | 0017 | 702-04-00100 | Adjusting Manholes | 23 | EACH | 1,275.00 | 29,325.00 | 1,500.00 | 34,500.00 | 750.00 | 17,250.00 | | 0018 | 702-04-00200 | Adjusting Catch Basins | 16 | EACH | 2,900.00 | 46,400.00 | 2,000.00 | 32,000.00 | 870.00 | 13,920.00 | | 0019 | 706-01-00100 | Concrete Walk (4" Thick) | 380 | SQYD | 102.00 | 38,760.00 | 125.00 | 47,500.00 | 100.00 | 38,000.00 | | 0020 | 706-04-00110 | Curb Ramps Type 1 | 156.9 | SQYD | 360.00 | 56,484.00 | 200.00 | 31,380.00 | 225.00 | 35,302.50 | | 0021 | 706-04-00110 | Curb Ramps Type 2 | 44.4 | SQYD | 375.00 | 16,650.00 | 200.00 | 8,880.00 | 225.00 | 9,990.00 | | 0022 | 706-04-00110 | Curb Ramps Type 3 | 183.9 | SQYD | 375.00 | 68,962.50 | 225.00 | 41,377.50 | 225.00 | 41,377.50 | | 0023 | 706-04-00110 | Curb Ramps Type 7 | 141 | SQYD | 430.00 | 60,630.00 | 225.00 | 31,725.00 | 225.00 | 31,725.00 | | 0024 | 707-01-00100 | Concrete Curb | 1,080.4 | LNFT | 53.00 | 57,261.20 | 35.00 | 37,814.00 | 30.00 | 32,412.00 | | 0025 | 707-03-00100 | Combination Concrete Curb and Gutter | 854 | LNFT | 68.00 | 58,072.00 | 60.00 | 51,240.00 | 50.00 | 42,700.00 | | 0026 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 190,000.00 | 190,000.00 | 285,000.00 | 285,000.00 | 250,000.00 | 250,000.00 | | 0027 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 3,477 | LNFT | 0.55 | 1,912.35 | 0.75 | 2,607.75 | 1.00 | 3,477.00 | | 0028 | 713-02-00400 | Temporary Pavement Markings (12" Width) | 630 | LNFT | 0.75 | 472.50 | 1.00 | 630.00 | 1.50 | 945.00 | | 0029 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 1,251 | LNFT | 0.90 | 1,125.90 | 1.00 | 1,251.00 | 2.00 | 2,502.00 | | 0030 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 4.215 | MILE | 1,450.00 | 6,111.75 | 550.00 | 2,318.25 | 350.00 | 1,475.25 | | 0031 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 4.215 | MILE | 530.00 | 2,233.95 | 550.00 | 2,318.25 | 750.00 | 3,161.25 | | 0032 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 8.049 | MILE | 700.00 | 5,634.30 | 700.00 | 5,634.30 | 1,000.00 | 8,049.00 | | 0033 | 713-05-00220 | Temporary Pavement Legends & Symbols (Arrow - Left Turn) | 2 | EACH | 22.00 | 44.00 | 35.00 | 70.00 | 50.00 | 100.00 | | 0034 | 713-05-00230 | Temporary Pavement Legends & Symbols (Arrow - Right Turn) | 2 | EACH | 22.00 | 44.00 | 35.00 | 70.00 | 75.00 | 150.00 | | 0035 | 713-05-00600 | Temporary Pavement Legends & Symbols (U-Turn) | 4 | EACH | 44.00 | 176.00 | 35.00 | 140.00 | 100.00 | 400.00 | | 0036 | 714-01-00100 | Slab Sodding (Bermuda Grass) | 177 | SQYD | 22.00 | 3,894.00 | 25.00 | 4,425.00 | 40.00 | 7,080.00 | | 0037 | 727-01-00100 | Mobilization | 1 | LUMP | 156,000.00 | 156,000.00 | 300,000.00 | 300,000.00 | 300,000.00 | 300,000.00 | | 0038 | 729-01-00103 | Sign (Type A)(Relocate) | 19.6 | SQFT | 194.00 | 3,802.40 | 100.00 | 1,960.00 | 140.00 | 2,744.00 | | 0039 | 731-02-00100 | Reflectorized Raised Pavement Markers | 266 | EACH | 5.50 | 1,463.00 | 6.50 | 1,729.00 | 10.00 | 2,660.00 | | 0040 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 1,159 | LNFT | 3.80 | 4,404.20 | 4.50 | 5,215.50 | 3.00 | 3,477.00 | | 0041 | 732-01-02060 | Plastic Pavement Striping (12" Width) (Thermoplastic 125 mil) | 210 | LNFT | 10.00 | 2,100.00 | 11.50 | 2,415.00 | 7.00 | 1,470.00 | | 0042 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 417 | LNFT | 13.00 | 5,421.00 | 13.00 | 5,421.00 | 14.00 | 5,838.00 | | 0043 | 732-01-05200 | Plastic Pavement Striping (Dotted Line)(8" W)(2' L)(Thermo 125 mil) | 161 | LNFT | 3.30 | 531.30 | 4.00 | 644.00 | 5.00 | 805.00 | | 0044 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 2.683 | MILE | 4,400.00 | 11,805.20 | 5,000.00 | 13,415.00 | 5,500.00 | 14,756.50 | | 0045 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 1.405 | MILE | 1,000.00 | 1,405.00 | 1,200.00 | 1,686.00 | 2,000.00 | 2,810.00 | | 0046 | 732-04-00001 | Plastic Pavement Legends and Symbols (Message) School | 2 | EACH | 440.00 | 880.00 | 550.00 | 1,100.00 | 1,600.00 | 3,200.00 | | 0047 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 1 | EACH | 327.00 | 327.00 | 350.00 | 350.00 | 1,400.00 | 1,400.00 | | 0048 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 1 | EACH | 327.00 | 327.00 | 350.00 | 350.00 | 1,350.00 | 1,350.00 | | 0049 | 732-04-01121 | Plastic Pavement Legends and Symbols (U-Turn) | 2 | EACH | 722.00 | 1,444.00 | 700.00 | 1,400.00 | 1,200.00 | 2,400.00 | | 0050 | 732-05-00100 | Removal of Existing Markings | 0.494 | MILE | 277.00 | 136.84 | 300.00 | 148.20 | 14,000.00 | 6,916.00 | | 0051 | 736-01-00100 | Trenching and Backfilling | 5 | LNFT | 18.00 | 90.00 | 20.00 | 100.00 | 17.00 | 85.00 | | 0052 | 736-09-00100 | Loop Detector | 281 | LNFT | 35.00 | 9,835.00 | 35.00 | 9,835.00 | 32.30 | 9,076.30 | | 0053 | 736-11-00050 | Conduit (1/2" HDPE, Schedule 80) | 5 | LNFT | 7.00 | 35.00 | 10.00 | 50.00 | 7.00 | 35.00 | | 0054 | 740-01-00100 | Construction Layout | 1 | LUMP | 25,000.00 | 25,000.00 | 40,000.00 | 40,000.00 | 40,000.00 | 40,000.00 | | 0055 | 741-28-02010 | Service Connection (3/4" PE) | 1,960 | LNFT | 10.00 | 19,600.00 | 25.00 | 49,000.00 | 20.00 | 39,200.00 | | 0056 | NS-201-00005 | Arborist Services | 1 | LUMP | 8,900.00 | 8,900.00 | 15,000.00 | 15,000.00 | 10,000.00 | 10,000.00 | | 0057 | NS-500-00180 | Roadway Reinforcing Mesh (Complete Road System) | 18,213 | SQYD | 7.50 | 136,597.50 | 9.00 | 163,917.00 | 7.05 | 128,401.65 | | 0058 | NS-500-00360 | Saw Cutting Asphalt Concrete Pavement Over Portland Cement Concrete Composite Pavement | 3,666 | INLF | 0.95 | 3,482.70 | 1.00 | 3,666.00 | 2.50 | 9,165.00 | | 0059 | NS-719-00002 | Tree Trimming | 1 | LUMP | 14,000.00 | 14,000.00 | 15,000.00 | 15,000.00 | 14,000.00 | 14,000.00 | | 0060 | NS-719-00003 | Root Pruning | 1 | LUMP | 18,500.00 | 18,500.00 | 20,000.00 | 20,000.00 | 20,000.00 | 20,000.00 | | 0061 | TS-500-00100 | Roadway Joint Reinforcing Composite Membrane | 24,750 | LNFT | 5.30 | 131,175.00 | 6.00 | 148,500.00 | 5.60 | 138,600.00 | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 3,081,793.29 | | 3,143,063.65 | | 3,234,848.65 |
|