Proposal:H.014792.6
Parish:Beauregard
Routes:LA 112
Description:LA 112: LA 113 - ALLEN P/L
Type Construction:MILLING ASPHALT CONCRETE, PAVEMENT PATCHING, ASPHALT CONCRETE OVERLAY, AND RELATED WORK.
Estimated Construction Cost:$1,207,236.10
| Rank | License | Bidder | Construction Bid |
| 1 | 34356 | Prairie Contractors LLC | $1,127,716.01 |
| 2 | 00183 | R. E. Heidt Construction Co., LLC | $1,180,647.87 |
| 3 | 12487 | Diamond B Construction Co., L.L.C. | $1,227,005.05 |
| 4 | 12312 | GILCHRIST CONSTRUCTION COMPANY, LLC | $1,308,536.11 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Prairie Contractors LLC | - 2 - R. E. Heidt Construction Co., LLC | - 3 - Diamond B Construction Co., L.L.C. | - 4 - GILCHRIST CONSTRUCTION COMPANY, LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 202-02-14500 | Removal of Guard Rail | 830.7 | LNFT | 17.00 | 14,121.90 | 7.07 | 5,873.05 | 15.00 | 12,460.50 | 8.00 | 6,645.60 | | 0002 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 23 | CUYD | 500.00 | 11,500.00 | 410.00 | 9,430.00 | 195.00 | 4,485.00 | 70.00 | 1,610.00 | | 0003 | 502-01-00100 | Asphalt Concrete | 3,680.8 | TON | 140.00 | 515,312.00 | 138.00 | 507,950.40 | 134.00 | 493,227.20 | 148.00 | 544,758.40 | | 0004 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 233 | TON | 180.00 | 41,940.00 | 185.00 | 43,105.00 | 260.00 | 60,580.00 | 350.00 | 81,550.00 | | 0005 | 509-01-00100 | Milling Asphalt Pavement | 2,418 | SQYD | 15.00 | 36,270.00 | 12.00 | 29,016.00 | 8.00 | 19,344.00 | 15.00 | 36,270.00 | | 0006 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -61 | CUYD | 0.01 | -0.61 | 0.01 | -0.61 | 1.00 | -61.00 | 0.01 | -0.61 | | 0007 | 510-01-00300 | Pavement Patching (18" Minimum Thickness) | 250 | SQYD | 130.00 | 32,500.00 | 195.00 | 48,750.00 | 235.00 | 58,750.00 | 260.00 | 65,000.00 | | 0008 | 704-01-01020 | Guard Rail (Single Thrie Beam) (6'-3" post spacing) | 240 | LNFT | 85.00 | 20,400.00 | 45.71 | 10,970.40 | 85.00 | 20,400.00 | 47.00 | 11,280.00 | | 0009 | 704-03-00200 | Blocked Out Guard Rail - 31", (6'-3" Post Spacing) | 206.3 | LNFT | 32.00 | 6,601.60 | 30.30 | 6,250.89 | 36.00 | 7,426.80 | 32.00 | 6,601.60 | | 0010 | 704-07-00200 | Guard Rail Transitions (Double Thrie Beam) | 100 | LNFT | 125.00 | 12,500.00 | 118.17 | 11,817.00 | 125.00 | 12,500.00 | 120.00 | 12,000.00 | | 0011 | 704-10-00205 | Guard Rail End Treatment, MASH, (TL-3 Tangent) | 4 | EACH | 4,200.00 | 16,800.00 | 3,636.00 | 14,544.00 | 4,200.00 | 16,800.00 | 3,800.00 | 15,200.00 | | 0012 | 707-04-00100 | Asphalt Curb | 54 | LNFT | 200.00 | 10,800.00 | 150.00 | 8,100.00 | 28.00 | 1,512.00 | 80.00 | 4,320.00 | | 0013 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 30,000.00 | 30,000.00 | 25,000.00 | 25,000.00 | 30,000.00 | 30,000.00 | 50,000.00 | 50,000.00 | | 0014 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 2.488 | MILE | 1,000.00 | 2,488.00 | 1,600.00 | 3,980.80 | 154.00 | 383.15 | 375.00 | 933.00 | | 0015 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 1.87 | MILE | 1.00 | 1.87 | 707.00 | 1,322.09 | 700.00 | 1,309.00 | 1.00 | 1.87 | | 0016 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 7.548 | MILE | 1.00 | 7.55 | 1,313.00 | 9,910.52 | 1,300.00 | 9,812.40 | 1.00 | 7.55 | | 0017 | 724-01-00100 | Rumble Strips (Centerline) | 2.407 | MILE | 1,200.00 | 2,888.40 | 1,010.00 | 2,431.07 | 1,000.00 | 2,407.00 | 1,200.00 | 2,888.40 | | 0018 | 724-02-00100 | Rumble Strips (Shoulder/Edge) | 4.814 | MILE | 1,200.00 | 5,776.80 | 1,010.00 | 4,862.14 | 1,000.00 | 4,814.00 | 1,200.00 | 5,776.80 | | 0019 | 727-01-00100 | Mobilization | 1 | LUMP | 70,000.00 | 70,000.00 | 143,000.00 | 143,000.00 | 120,000.00 | 120,000.00 | 130,000.00 | 130,000.00 | | 0020 | 729-16-00300 | Object Marker Assembly (Type 3) | 4 | EACH | 150.00 | 600.00 | 85.85 | 343.40 | 130.00 | 520.00 | 90.00 | 360.00 | | 0021 | 731-01-00100 | Nonreflectorized Raised Pavement Markers | 104 | EACH | 15.00 | 1,560.00 | 12.12 | 1,260.48 | 12.00 | 1,248.00 | 13.00 | 1,352.00 | | 0022 | 731-02-00100 | Reflectorized Raised Pavement Markers | 458 | EACH | 10.00 | 4,580.00 | 8.59 | 3,934.22 | 9.00 | 4,122.00 | 9.00 | 4,122.00 | | 0023 | 732-01-05000 | Plastic Pavement Striping (Dotted Line)(4" W)(2' L)(Thermo 125 mil) | 135 | LNFT | 2.50 | 337.50 | 2.02 | 272.70 | 2.00 | 270.00 | 2.50 | 337.50 | | 0024 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 7.548 | MILE | 6,500.00 | 49,062.00 | 6,363.00 | 48,027.92 | 6,500.00 | 49,062.00 | 6,500.00 | 49,062.00 | | 0025 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 1.87 | MILE | 3,200.00 | 5,984.00 | 3,181.50 | 5,949.41 | 3,200.00 | 5,984.00 | 3,200.00 | 5,984.00 | | 0026 | 732-05-00100 | Removal of Existing Markings | 0.023 | MILE | 15,000.00 | 345.00 | 13,130.00 | 301.99 | 15,000.00 | 345.00 | 12,000.00 | 276.00 | | 0027 | 735-01-00100 | Mailboxes | 4 | EACH | 10.00 | 40.00 | 1.25 | 5.00 | 1.00 | 4.00 | 35.00 | 140.00 | | 0028 | 735-02-00100 | Mailbox Supports (Single) | 4 | EACH | 550.00 | 2,200.00 | 515.00 | 2,060.00 | 550.00 | 2,200.00 | 275.00 | 1,100.00 | | 0029 | 740-01-00100 | Construction Layout | 1 | LUMP | 100.00 | 100.00 | 8,500.00 | 8,500.00 | 7,500.00 | 7,500.00 | 10,000.00 | 10,000.00 | | 0030 | NS-401-00100 | Hot-Mix Asphalt Aggregate Surface Course | 1,864 | TON | 125.00 | 233,000.00 | 120.00 | 223,680.00 | 150.00 | 279,600.00 | 140.00 | 260,960.00 | | | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 1,127,716.01 | | 1,180,647.87 | | 1,227,005.05 | | 1,308,536.11 |
|