Bid Tabulations for the Letting of 8/28/2024 LA DOTD Headquarters

Proposal:H.014756.6
Parish:Caddo
Routes:1-20
Description:I-20: DECEL LANE EXT EX 8
Type Construction:GRADING, MILLING ASPHALT CONCRETE, CLASS II BASE COURSE, LIME TREATMENT, ASPHALT CONCRETE PAVEMENT, LIGHTING AND RELATED WORK.
Estimated Construction Cost:$799,928.21
Rank License BidderConstruction Bid
167822Earnest Contracting LLC$947,007.52


Line
Number
Item NumberItem DescriptionQuantityUnit of
Measure
- 1 -
Earnest Contracting LLC
Unit PriceTotal
Amount
0001202-02-32000Removal of Paved Ditches 86     SQYD25.002,150.00
0002203-05-00100Excavation and Embankment 1     LUMP75,000.0075,000.00
0003204-02-00100Temporary Hay Bales 12     EACH10.00120.00
0004204-06-00100Temporary Silt Fencing 2,128     LNFT2.755,852.00
0005302-02-05010Class II Base Course (5" Thick) (Asphalt Concrete Base) 992.9   SQYD47.3547,013.82
0006304-01-00100Lime 14.07  TON300.004,221.00
0007304-05-00100Lime Treatment (Type E) 995     SQYD55.0054,725.00
0008502-01-00100Asphalt Concrete 543.4   TON175.0095,095.00
0009502-04-00100Asphalt Concrete (SMA) Wearing Course 260.9   TON400.00104,360.00
0010509-01-00100Milling Asphalt Pavement 1,488     SQYD10.0014,880.00
0011509-02-00100Contractor Retained Reclaimed Asphalt Pavement -143     CUYD0.10-14.30
0012706-03-00100Incidental Concrete Paving (4" Thick) 237.5   SQYD100.0023,750.00
0013713-01-00100Temporary Signs and Barricades 1     LUMP50,000.0050,000.00
0014713-03-01000Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) 0.496 MILE1,000.00496.00
0015713-03-02000Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) 0.496 MILE2,000.00992.00
0016713-04-01000Temporary Pavement Markings (Solid Line) (4" Width) 0.496 MILE2,000.00992.00
0017713-08-00100Temporary Precast Concrete Barrier (Department Furnished) 71     EACH750.0053,250.00
0018713-11-00100Portable Changeable Message Signs 2     EACH10,000.0020,000.00
0019716-01-00100Mulch (Vegetative) 1.2   TON5,000.006,000.00
0020717-01-00100Seeding 36     LB50.001,800.00
0021718-01-00100Fertilizer 608     LB5.003,040.00
0022720-01-02020Erosion Control System, Flexible (Channel Liner) (Type D) 85     SQYD20.001,700.00
0023724-02-00100Rumble Strips (Shoulder/Edge) 0.202 MILE35,000.007,070.00
0024727-01-00100Mobilization 1     LUMP50,000.0050,000.00
0025731-02-00100Reflectorized Raised Pavement Markers 170     EACH20.003,400.00
0026732-01-01080Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) 338     LNFT25.008,450.00
0027732-02-02000Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) 0.248 MILE50,000.0012,400.00
0028732-02-02040Plastic Pavement Striping (Solid Line) (8" Width) (Thermoplastic 90 mil) 0.203 MILE50,000.0010,150.00
0029732-03-02040Plastic Pavement Striping (Dotted Line)(8" W)(3' L)(Thermo 90 mil) 0.137 MILE30,000.004,110.00
0030732-05-00100Removal of Existing Markings 0.111 MILE100,000.0011,100.00
0031740-01-00100Construction Layout 1     LUMP25,000.0025,000.00
0032822-11-00100Removal and Disposal of Electrical Equipment 1     LUMP2,500.002,500.00
0033822-12-00100Removal and Storage of Light Pole (Ground Mount) (Lowmast)1     EACH4,500.004,500.00
0034822-13-00100Removal and Disposal of Light Pole Foundation (Ground)3     EACH1,000.003,000.00
0035822-14-00100Removal and Disposal of Luminaire 65     EACH150.009,750.00
0036NS-500-00340Saw Cutting Asphalt Concrete Pavement 10,640     INLF1.0010,640.00
0037NS-700-00810Impact Attenuator (Construction Zone)(Test Level 3) 1     EACH15,000.0015,000.00
0038NS-822-00175Light Pole Foundation (15' Length) 3     EACH11,500.0034,500.00
0039TS-822-09105Trenching and Backfilling 800     LNFT5.004,000.00
0040TS-822-09110Conduit w Conductors (PVC/HDPE) (2") (2#4, 1#8 Ground)800     LNFT15.5012,400.00
0041TS-822-09130Light Pole (Steel) (Single Arm) (10')3     EACH9,500.0028,500.00
0042TS-822-09156Luminaire (Roadway) (LED) (4K)77     EACH1,375.00105,875.00
0043TS-822-09164Underground Junction Box (Polymer Concrete) (11"x18")2     EACH1,535.003,070.00
0044TS-822-09164Underground Junction Box (Polymer Concrete) (12"x12")3     EACH1,480.004,440.00
0045TS-822-09172Modular Breakaway Cable System 3     EACH3,510.0010,530.00
0046TS-822-09178Underground Marker Tape (6") (Detectable)800     LNFT1.501,200.00
       
  CONTRACTOR TOTAL   947,007.52