Proposal:H.015069.6
Parish:Jefferson, Orleans
Routes:LA 428
Description:LA 428: GEN DEGAULLE DR - INDUSTRY CANAL
Type Construction:GRADING, DRAINAGE STRUCTURES, MILLING ASPHALT CONCRETE, PAVEMENT PATCHING, ASPHALT CONCRETE OVERLAY, AND RELATED WORK.
Estimated Construction Cost:$5,145,729.30
| Rank | License | Bidder | Construction Bid |
| 1 | 02179 | Boh Bros. Construction Co., LLC. | $3,186,332.25 |
| 2 | 06276 | Barriere Construction Co., LLC | $3,483,180.96 |
| 3 | 73475 | Madden Gulf Coast, LLC | $3,574,280.80 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Boh Bros. Construction Co., LLC. | - 2 - Barriere Construction Co., LLC | - 3 - Madden Gulf Coast, LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 202-02-00010 | Removal of Brick Catch Basins | 4 | EACH | 3,000.00 | 12,000.00 | 2,750.00 | 11,000.00 | 4,500.00 | 18,000.00 | | 0002 | 202-02-03030 | Removal of Pavement Structure | 92.7 | SQYD | 35.00 | 3,244.50 | 76.00 | 7,045.20 | 74.00 | 6,859.80 | | 0003 | 202-02-06100 | Removal of Concrete Walks and Drives | 563 | SQYD | 35.00 | 19,705.00 | 32.00 | 18,016.00 | 25.00 | 14,075.00 | | 0004 | 202-02-06140 | Removal of Curbs (Concrete) | 1,449 | LNFT | 25.00 | 36,225.00 | 32.00 | 46,368.00 | 22.50 | 32,602.50 | | 0005 | 202-02-38300 | Removal of Sign and U-Channel Post | 4 | EACH | 50.00 | 200.00 | 15.00 | 60.00 | 20.00 | 80.00 | | 0006 | 203-01-00100 | General Excavation | 114 | CUYD | 70.00 | 7,980.00 | 130.00 | 14,820.00 | 72.00 | 8,208.00 | | 0007 | 203-07-00100 | Borrow (Vehicular Measurement) | 347 | CUYD | 30.00 | 10,410.00 | 190.00 | 65,930.00 | 125.00 | 43,375.00 | | 0008 | 204-06-00100 | Temporary Silt Fencing | 500 | LNFT | 5.00 | 2,500.00 | 4.98 | 2,490.00 | 4.98 | 2,490.00 | | 0009 | 302-02-06030 | Class II Base Course (6" Thick) (Asphalt Concrete Base) | 49.4 | SQYD | 100.00 | 4,940.00 | 135.00 | 6,669.00 | 157.00 | 7,755.80 | | 0010 | 502-01-00100 | Asphalt Concrete | 11,672.7 | TON | 115.00 | 1,342,360.50 | 120.00 | 1,400,724.00 | 125.00 | 1,459,087.50 | | 0011 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 260.9 | TON | 175.00 | 45,657.50 | 391.25 | 102,077.13 | 260.00 | 67,834.00 | | 0012 | 509-01-00100 | Milling Asphalt Pavement | 99,041 | SQYD | 3.00 | 297,123.00 | 3.80 | 376,355.80 | 2.90 | 287,218.90 | | 0013 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -4,130 | CUYD | 0.02 | -82.60 | 0.10 | -413.00 | 0.01 | -41.30 | | 0014 | 510-01-00260 | Pavement Patching (16 inch Minimum Thickness) | 1,368 | SQYD | 170.00 | 232,560.00 | 171.00 | 233,928.00 | 165.00 | 225,720.00 | | 0015 | 702-03-00500 | Catch Basins (CB-06) | 4 | EACH | 6,000.00 | 24,000.00 | 5,410.00 | 21,640.00 | 8,500.00 | 34,000.00 | | 0016 | 702-04-00100 | Adjusting Manholes | 19 | EACH | 1,200.00 | 22,800.00 | 1,050.00 | 19,950.00 | 3,950.00 | 75,050.00 | | 0017 | 702-04-00150 | Adjusting Manholes w/Manhole Adjustment Rings | 4 | EACH | 300.00 | 1,200.00 | 142.00 | 568.00 | 1,500.00 | 6,000.00 | | 0018 | 702-04-00200 | Adjusting Catch Basins | 31 | EACH | 3,500.00 | 108,500.00 | 3,200.00 | 99,200.00 | 5,500.00 | 170,500.00 | | 0019 | 706-01-00100 | Concrete Walk (4" Thick) | 94.7 | SQYD | 90.00 | 8,523.00 | 87.00 | 8,238.90 | 145.00 | 13,731.50 | | 0020 | 706-04-00110 | Curb Ramps TYPE 3 | 137.7 | SQYD | 275.00 | 37,867.50 | 265.00 | 36,490.50 | 225.00 | 30,982.50 | | 0021 | 706-04-00110 | Curb Ramps TYPE 4 | 53.7 | SQYD | 265.00 | 14,230.50 | 255.00 | 13,693.50 | 255.00 | 13,693.50 | | 0022 | 706-04-00110 | Curb Ramps TYPE 6 | 27.4 | SQYD | 295.00 | 8,083.00 | 285.00 | 7,809.00 | 255.00 | 6,987.00 | | 0023 | 706-04-00110 | Curb Ramps TYPE 7 | 425.6 | SQYD | 275.00 | 117,040.00 | 275.00 | 117,040.00 | 230.00 | 97,888.00 | | 0024 | 707-01-00100 | Concrete Curb | 1,180 | LNFT | 45.00 | 53,100.00 | 41.00 | 48,380.00 | 39.00 | 46,020.00 | | 0025 | 707-03-00100 | Combination Concrete Curb and Gutter | 96 | LNFT | 80.00 | 7,680.00 | 75.00 | 7,200.00 | 250.00 | 24,000.00 | | 0026 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 160,000.00 | 160,000.00 | 315,000.00 | 315,000.00 | 200,000.00 | 200,000.00 | | 0027 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 2,770 | LNFT | 0.40 | 1,108.00 | 0.35 | 969.50 | 0.25 | 692.50 | | 0028 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 6,660 | LNFT | 1.00 | 6,660.00 | 1.00 | 6,660.00 | 0.45 | 2,997.00 | | 0029 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 10.688 | MILE | 275.00 | 2,939.20 | 1,055.00 | 11,275.84 | 350.00 | 3,740.80 | | 0030 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 14.36 | MILE | 1,000.00 | 14,360.00 | 1,000.00 | 14,360.00 | 700.00 | 10,052.00 | | 0031 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 21.116 | MILE | 1,500.00 | 31,674.00 | 1,500.00 | 31,674.00 | 1,000.00 | 21,116.00 | | 0032 | 713-05-00220 | Temporary Pavement Legends & Symbols (Arrow - Left Turn) | 84 | EACH | 40.00 | 3,360.00 | 50.00 | 4,200.00 | 25.00 | 2,100.00 | | 0033 | 713-05-00230 | Temporary Pavement Legends & Symbols (Arrow - Right Turn) | 4 | EACH | 40.00 | 160.00 | 50.00 | 200.00 | 25.00 | 100.00 | | 0034 | 713-05-00240 | Temporary Pavement Legends & Symbols (Arrow - Merge) | 2 | EACH | 40.00 | 80.00 | 50.00 | 100.00 | 35.00 | 70.00 | | 0035 | 713-05-00300 | Temporary Pavement Legends & Symbols (ONLY) | 34 | EACH | 30.00 | 1,020.00 | 25.00 | 850.00 | 35.00 | 1,190.00 | | 0036 | 713-06-00100 | Temporary Reflectorized Raised Pavement Markers | 231 | EACH | 8.00 | 1,848.00 | 7.50 | 1,732.50 | 6.00 | 1,386.00 | | 0037 | 716-01-00100 | Mulch (Vegetative) | 3 | TON | 1,500.00 | 4,500.00 | 1,277.00 | 3,831.00 | 1,276.99 | 3,830.97 | | 0038 | 717-01-00100 | Seeding | 60 | LB | 20.00 | 1,200.00 | 13.21 | 792.60 | 13.21 | 792.60 | | 0039 | 718-01-00100 | Fertilizer | 2,010 | LB | 1.00 | 2,010.00 | 1.00 | 2,010.00 | 0.99 | 1,989.90 | | 0040 | 726-01-00100 | Bedding Material | 2.8 | CUYD | 125.00 | 350.00 | 98.00 | 274.40 | 500.00 | 1,400.00 | | 0041 | 727-01-00100 | Mobilization | 1 | LUMP | 300,000.00 | 300,000.00 | 173,000.00 | 173,000.00 | 352,000.00 | 352,000.00 | | 0042 | 729-01-00100 | Sign (Type A) | 9 | SQFT | 50.00 | 450.00 | 25.00 | 225.00 | 75.00 | 675.00 | | 0043 | 729-01-00103 | Sign (Type A)(Relocate) | 9 | SQFT | 100.00 | 900.00 | 25.00 | 225.00 | 30.00 | 270.00 | | 0044 | 729-16-00300 | Object Marker Assembly (Type 3) | 3 | EACH | 100.00 | 300.00 | 200.00 | 600.00 | 85.00 | 255.00 | | 0045 | 729-21-00100 | U-Channel Post | 2 | EACH | 200.00 | 400.00 | 325.00 | 650.00 | 150.00 | 300.00 | | 0046 | 731-02-00100 | Reflectorized Raised Pavement Markers | 2,630 | EACH | 8.00 | 21,040.00 | 7.50 | 19,725.00 | 5.00 | 13,150.00 | | 0047 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 1,385 | LNFT | 4.25 | 5,886.25 | 4.00 | 5,540.00 | 3.00 | 4,155.00 | | 0048 | 732-01-01080 | Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) | 963 | LNFT | 13.00 | 12,519.00 | 12.50 | 12,037.50 | 16.00 | 15,408.00 | | 0049 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 2,367 | LNFT | 15.50 | 36,688.50 | 15.00 | 35,505.00 | 17.00 | 40,239.00 | | 0050 | 732-01-05200 | Plastic Pavement Striping (Dotted Line)(8" W)(2' L)(Thermo 125 mil) | 392 | LNFT | 5.00 | 1,960.00 | 4.00 | 1,568.00 | 3.00 | 1,176.00 | | 0051 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 10.384 | MILE | 4,100.00 | 42,574.40 | 4,000.00 | 41,536.00 | 4,500.00 | 46,728.00 | | 0052 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 7.18 | MILE | 1,550.00 | 11,129.00 | 1,500.00 | 10,770.00 | 1,200.00 | 8,616.00 | | 0053 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 42 | EACH | 375.00 | 15,750.00 | 350.00 | 14,700.00 | 350.00 | 14,700.00 | | 0054 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 2 | EACH | 375.00 | 750.00 | 350.00 | 700.00 | 350.00 | 700.00 | | 0055 | 732-04-01120 | Plastic Pavement Legends and Symbols (Arrow - Merge) | 1 | EACH | 775.00 | 775.00 | 750.00 | 750.00 | 650.00 | 650.00 | | 0056 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 17 | EACH | 375.00 | 6,375.00 | 350.00 | 5,950.00 | 500.00 | 8,500.00 | | 0057 | 732-04-19020 | Plastic Pavement Legends and Symbols (SCHOOL) | 2 | EACH | 775.00 | 1,550.00 | 750.00 | 1,500.00 | 850.00 | 1,700.00 | | 0058 | 732-05-00100 | Removal of Existing Markings | 0.029 | MILE | 20,000.00 | 580.00 | 25,000.00 | 725.00 | 20,000.00 | 580.00 | | 0059 | 736-01-00100 | Trenching and Backfilling | 20 | LNFT | 15.00 | 300.00 | 13.97 | 279.40 | 13.97 | 279.40 | | 0060 | 736-09-00100 | Loop Detector | 329 | LNFT | 32.00 | 10,528.00 | 30.62 | 10,073.98 | 30.62 | 10,073.98 | | 0061 | 736-10-00200 | Underground Junction Box (Type E) | 1 | EACH | 1,500.00 | 1,500.00 | 1,390.00 | 1,390.00 | 1,389.05 | 1,389.05 | | 0062 | 736-11-00050 | Conduit (1/2" HDPE, Schedule 80) | 20 | LNFT | 5.00 | 100.00 | 4.05 | 81.00 | 4.02 | 80.40 | | 0063 | 740-01-00100 | Construction Layout | 1 | LUMP | 20,000.00 | 20,000.00 | 44,988.81 | 44,988.81 | 54,000.00 | 54,000.00 | | 0064 | NS-500-00340 | Saw Cutting Asphalt Concrete Pavement | 6,774 | INLF | 1.50 | 10,161.00 | 1.10 | 7,451.40 | 0.75 | 5,080.50 | | 0065 | NS-719-00002 | Tree Trimming | 1 | LUMP | 35,000.00 | 35,000.00 | 34,000.00 | 34,000.00 | 50,000.00 | 50,000.00 | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 3,186,332.25 | | 3,483,180.96 | | 3,574,280.80 |
|