Proposal:H.010343.6
Parish:DeSoto, Natchitoches
Routes:LA 174
Description:LA 174: SABINE P/L - I-49 INTERCHANGE
Type Construction:DRAINAGE STRUCTURES, MILLING ASPHALT CONCRETE, PAVEMENT PATCHING, ASPHALT SURFACE TREATMENT, ASPHALT CONCRETE PAVEMENT, AND RELATED WORK.
Estimated Construction Cost:$5,575,633.85
| Rank | License | Bidder | Construction Bid |
| 1 | 08584 | Madden Contracting Co., LLC | $7,047,072.07 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Madden Contracting Co., LLC | | Unit Price | Total Amount | | 0001 | 202-02-32100 | Removal of Pipe (Cross Drain) (24" RCP) | 51 | LNFT | 25.00 | 1,275.00 | | 0002 | 202-02-32100 | Removal of Pipe (Cross Drain) (30" RCP) | 34 | LNFT | 25.00 | 850.00 | | 0003 | 203-07-00100 | Borrow (Vehicular Measurement) | 557 | CUYD | 94.24 | 52,491.68 | | 0004 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 10 | EACH | 225.00 | 2,250.00 | | 0005 | 204-06-00100 | Temporary Silt Fencing | 150 | LNFT | 8.00 | 1,200.00 | | 0006 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 1,847 | CUYD | 59.56 | 110,007.32 | | 0007 | 502-01-00100 | Asphalt Concrete | 19,502.6 | TON | 149.10 | 2,907,837.66 | | 0008 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 516.1 | TON | 106.40 | 54,913.04 | | 0009 | 507-01-00100 | Asphalt Material (CRS-2P Emulsion) | 51,880 | GAL | 3.74 | 194,031.20 | | 0010 | 507-02-00200 | Aggregate (S2) | 76,296 | SQYD | 2.59 | 197,606.64 | | 0011 | 507-02-00300 | Aggregate (S3) | 76,296 | SQYD | 2.18 | 166,325.28 | | 0012 | 509-01-00100 | Milling Asphalt Pavement | 83,891 | SQYD | 3.91 | 328,013.81 | | 0013 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -3,501 | CUYD | 0.10 | -350.10 | | 0014 | 510-01-00100 | Pavement Patching (6" Minimum Thickness) | 266 | SQYD | 84.46 | 22,466.36 | | 0015 | 510-01-00260 | Pavement Patching (16 inch Minimum Thickness) | 5,010 | SQYD | 226.83 | 1,136,418.30 | | 0016 | 510-02-00100 | Pavement Widening (16" THICK) | 3,530.7 | SQYD | 163.03 | 575,610.02 | | 0017 | 701-01-01003 | Cross Drain Pipe (24" RCP/RPVCP/CPEPDW) | 48 | LNFT | 335.00 | 16,080.00 | | 0018 | 701-01-01023 | Cross Drain Pipe (30" RCP/RPVCP/CPEPDW) | 40 | LNFT | 374.00 | 14,960.00 | | 0019 | 701-10-01060 | Reinforced Concrete Pipe (Extension) (24") | 8 | LNFT | 250.00 | 2,000.00 | | 0020 | 701-15-00100 | Concrete Collar | 1 | EACH | 2,450.00 | 2,450.00 | | 0021 | 701-17-00100 | Trench Excavation Safety Protection (Depth >5 feet) | 79 | LNFT | 5.00 | 395.00 | | 0022 | 711-01-04000 | Riprap (55 lb, 18" Thick) | 25 | SQYD | 169.00 | 4,225.00 | | 0023 | 711-04-00100 | Geotextile Fabric | 25 | SQYD | 5.00 | 125.00 | | 0024 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 436,000.00 | 436,000.00 | | 0025 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 19.053 | MILE | 300.00 | 5,715.90 | | 0026 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 6.989 | MILE | 800.00 | 5,591.20 | | 0027 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 81.925 | MILE | 1,315.00 | 107,731.38 | | 0028 | 713-06-00200 | Temporary Reflectorized Raised Pavement Markers (Tabs) | 3,353 | EACH | 2.50 | 8,382.50 | | 0029 | 726-01-00100 | Bedding Material | 22.3 | CUYD | 121.00 | 2,698.30 | | 0030 | 727-01-00100 | Mobilization | 1 | LUMP | 436,000.00 | 436,000.00 | | 0031 | 729-16-00200 | Object Marker Assembly (Type 2) | 5 | EACH | 95.00 | 475.00 | | 0032 | 731-02-00100 | Reflectorized Raised Pavement Markers | 1,446 | EACH | 8.50 | 12,291.00 | | 0033 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 565 | LNFT | 5.00 | 2,825.00 | | 0034 | 732-01-01080 | Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) | 112 | LNFT | 19.50 | 2,184.00 | | 0035 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 23.656 | MILE | 6,300.00 | 149,032.80 | | 0036 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 1.747 | MILE | 3,325.00 | 5,808.78 | | 0037 | 735-01-00100 | Mailboxes | 7 | EACH | 20.00 | 140.00 | | 0038 | 735-02-00100 | Mailbox Supports (Single) | 7 | EACH | 355.00 | 2,485.00 | | 0039 | 739-01-00100 | Hydro-Seeding | 3.08 | ACRE | 3,500.00 | 10,780.00 | | 0040 | 740-01-00100 | Construction Layout | 1 | LUMP | 67,750.00 | 67,750.00 | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 7,047,072.07 |
|