Proposal:H.015303.6
Parish:Ouachita
Routes:LA 143
Description:LA 143: US 80 - LA 616
Type Construction:PAVEMENT PATCHING AND RELATED WORK.
Estimated Construction Cost:$1,640,039.00
| Rank | License | Bidder | Construction Bid |
| 1 | 30774 | Progressive Construction Co., LLC | $1,879,983.74 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Progressive Construction Co., LLC | | Unit Price | Total Amount | | 0001 | 202-02-06140 | Removal of Curbs (Concrete) | 324 | LNFT | 15.00 | 4,860.00 | | 0002 | 602-02-00200 | Cleaning and Resealing Existing Longitudinal Pavement Joints | 10,580 | LNFT | 4.25 | 44,965.00 | | 0003 | 602-02-00300 | Cleaning and Resealing Existing Transverse Pavements Joints | 16,656 | LNFT | 4.25 | 70,788.00 | | 0004 | 602-16-00101 | High Early Strength (HES) Concrete Pavement Full Depth Patching | 3,257.7 | SQYD | 410.00 | 1,335,657.00 | | 0005 | 702-03-00001 | Catch Basin (Remove and Replace Frame and Cover) | 10 | EACH | 6,200.00 | 62,000.00 | | 0006 | 702-04-00100 | Adjusting Manholes | 10 | EACH | 3,800.00 | 38,000.00 | | 0007 | 707-01-00100 | Concrete Curb | 324 | LNFT | 40.00 | 12,960.00 | | 0008 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 43,000.00 | 43,000.00 | | 0009 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 1,096 | LNFT | 0.28 | 306.88 | | 0010 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 156 | LNFT | 0.60 | 93.60 | | 0011 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 2.592 | MILE | 2,000.00 | 5,184.00 | | 0012 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 1.618 | MILE | 770.00 | 1,245.86 | | 0013 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 2.38 | MILE | 1,320.00 | 3,141.60 | | 0014 | 713-05-00220 | Temporary Pavement Legends & Symbols (Arrow - Left Turn) | 23 | EACH | 25.00 | 575.00 | | 0015 | 713-05-00300 | Temporary Pavement Legends & Symbols (ONLY) | 11 | EACH | 25.00 | 275.00 | | 0016 | 727-01-00100 | Mobilization | 1 | LUMP | 160,000.00 | 160,000.00 | | 0017 | 731-02-00100 | Reflectorized Raised Pavement Markers | 570 | EACH | 7.00 | 3,990.00 | | 0018 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 1,096 | LNFT | 3.85 | 4,219.60 | | 0019 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 156 | LNFT | 22.00 | 3,432.00 | | 0020 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 2.38 | MILE | 600.00 | 1,428.00 | | 0021 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.534 | MILE | 1,300.00 | 694.20 | | 0022 | 732-03-04001 | Plastic Pav't Striping (Broken) (7" Width) (Preformed Tape) (Retroreflectivity Level I) (Black and White Contrast) | 1.084 | MILE | 11,000.00 | 11,924.00 | | 0023 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 23 | EACH | 440.00 | 10,120.00 | | 0024 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 11 | EACH | 700.00 | 7,700.00 | | 0025 | 732-05-00100 | Removal of Existing Markings | 0.648 | MILE | 13,000.00 | 8,424.00 | | 0026 | 740-01-00100 | Construction Layout | 1 | LUMP | 10,000.00 | 10,000.00 | | 0027 | 741-35-00100 | Adjust Valve or Meter Box | 14 | EACH | 2,500.00 | 35,000.00 | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 1,879,983.74 |
|