Proposal:H.015275.6
Parish:Tangipahoa
Routes:LA 16
Description:LA 16: LA 445 - WASHINGTON P/L
Type Construction:MILLING ASPHALT CONCRETE, STRIPING AND RELATED WORK.
Estimated Construction Cost:$9,131,596.11
| Rank | License | Bidder | Construction Bid |
| 1 | 06276 | Barriere Construction Co., LLC | $5,809,654.57 |
| 2 | 73475 | Madden Gulf Coast, LLC | $6,091,365.38 |
| 3 | 00046 | Barber Bros. Contracting Co., L.L.C | $7,943,549.85 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Barriere Construction Co., LLC | - 2 - Madden Gulf Coast, LLC | - 3 - Barber Bros. Contracting Co., L.L.C | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 202-02-14500 | Removal of Guard Rail | 1,500 | LNFT | 6.25 | 9,375.00 | 6.25 | 9,375.00 | 7.00 | 10,500.00 | | 0002 | 202-02-38300 | Removal of Sign and U-Channel Post | 12 | EACH | 25.00 | 300.00 | 25.00 | 300.00 | 30.00 | 360.00 | | 0003 | 203-07-00100 | Borrow (Vehicular Measurement) | 1,849 | CUYD | 13.00 | 24,037.00 | 43.00 | 79,507.00 | 80.00 | 147,920.00 | | 0004 | 204-06-00100 | Temporary Silt Fencing | 64,416 | LNFT | 1.80 | 115,948.80 | 1.30 | 83,740.80 | 2.00 | 128,832.00 | | 0005 | 303-02-00100 | Removal of Existing Patches | 1,800 | SQYD | 0.01 | 18.00 | 5.00 | 9,000.00 | 18.00 | 32,400.00 | | 0006 | 303-03-00400 | In-Place Cement Treated Base Course (12" Thick) | 143,044 | SQYD | 10.00 | 1,430,440.00 | 12.50 | 1,788,050.00 | 12.00 | 1,716,528.00 | | 0007 | 402-01-00101 | Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) | 100 | CUYD | 0.01 | 1.00 | 50.00 | 5,000.00 | 65.00 | 6,500.00 | | 0008 | 502-01-00100 | Asphalt Concrete | 29,446.7 | TON | 99.00 | 2,915,223.30 | 87.00 | 2,561,862.90 | 135.00 | 3,975,304.50 | | 0009 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 1,047.1 | TON | 40.00 | 41,884.00 | 96.00 | 100,521.60 | 240.00 | 251,304.00 | | 0010 | 509-01-00100 | Milling Asphalt Pavement | 140,576 | SQYD | 2.55 | 358,468.80 | 1.69 | 237,573.44 | 5.00 | 702,880.00 | | 0011 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -6,796 | CUYD | 0.01 | -67.96 | 0.01 | -67.96 | 0.00 | 0.00 | | 0012 | 704-03-00200 | Blocked Out Guard Rail - 31", (6'-3" Post Spacing) | 450 | LNFT | 29.30 | 13,185.00 | 29.25 | 13,162.50 | 34.00 | 15,300.00 | | 0013 | 704-07-00200 | Guard Rail Transitions (Double Thrie Beam) | 300 | LNFT | 114.00 | 34,200.00 | 113.75 | 34,125.00 | 133.00 | 39,900.00 | | 0014 | 704-10-00310 | Guard Rail End Treatment, NCHRP 350 - 31" (TL-3 Flared) | 12 | EACH | 3,050.00 | 36,600.00 | 3,025.00 | 36,300.00 | 3,500.00 | 42,000.00 | | 0015 | 707-04-00100 | Asphalt Curb | 54 | LNFT | 193.00 | 10,422.00 | 290.00 | 15,660.00 | 8.00 | 432.00 | | 0016 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 230,000.00 | 230,000.00 | 250,000.00 | 250,000.00 | 250,000.00 | 250,000.00 | | 0017 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 45 | LNFT | 0.01 | 0.45 | 1.00 | 45.00 | 1.00 | 45.00 | | 0018 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 18.3 | MILE | 320.00 | 5,856.00 | 350.00 | 6,405.00 | 300.00 | 5,490.00 | | 0019 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 15.051 | MILE | 0.01 | 0.15 | 750.00 | 11,288.25 | 750.00 | 11,288.25 | | 0020 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 53.169 | MILE | 0.01 | 0.53 | 900.00 | 47,852.10 | 900.00 | 47,852.10 | | 0021 | 713-11-00100 | Portable Changeable Message Signs | 2 | EACH | 10,150.00 | 20,300.00 | 6,000.00 | 12,000.00 | 10,000.00 | 20,000.00 | | 0022 | 722-01-00100 | Project Site Laboratory | 1 | EACH | 20,050.00 | 20,050.00 | 12,000.00 | 12,000.00 | 7,500.00 | 7,500.00 | | 0023 | 724-01-00100 | Rumble Strips (Centerline) | 5.947 | MILE | 281.00 | 1,671.11 | 950.00 | 5,649.65 | 400.00 | 2,378.80 | | 0024 | 724-01-00100 | Rumble Strips (Centerline) | 0.031 | MILE | 281.00 | 8.71 | 950.00 | 29.45 | 400.00 | 12.40 | | 0025 | 724-02-00100 | Rumble Strips (Shoulder/Edge) | 11.957 | MILE | 281.00 | 3,359.92 | 950.00 | 11,359.15 | 400.00 | 4,782.80 | | 0026 | 727-01-00100 | Mobilization | 1 | LUMP | 400,000.00 | 400,000.00 | 600,000.00 | 600,000.00 | 350,000.00 | 350,000.00 | | 0027 | 729-16-00300 | Object Marker Assembly (Type 3) | 12 | EACH | 91.00 | 1,092.00 | 90.00 | 1,080.00 | 105.00 | 1,260.00 | | 0028 | 731-02-00100 | Reflectorized Raised Pavement Markers | 1,391 | EACH | 6.60 | 9,180.60 | 6.50 | 9,041.50 | 8.00 | 11,128.00 | | 0029 | 732-01-01080 | Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) | 15 | LNFT | 20.50 | 307.50 | 20.00 | 300.00 | 23.00 | 345.00 | | 0030 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 17.723 | MILE | 4,025.00 | 71,335.08 | 4,000.00 | 70,892.00 | 4,700.00 | 83,298.10 | | 0031 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 5.017 | MILE | 1,275.00 | 6,396.68 | 1,250.00 | 6,271.25 | 1,500.00 | 7,525.50 | | 0032 | 732-03-02010 | Plastic Pavement Striping (Dotted Line)(4" W)(2' L)(Thermo 90 mil) | 0.058 | MILE | 5,050.00 | 292.90 | 5,000.00 | 290.00 | 5,000.00 | 290.00 | | 0033 | 735-01-00100 | Mailboxes | 65 | EACH | 20.25 | 1,316.25 | 250.00 | 16,250.00 | 23.00 | 1,495.00 | | 0034 | 735-02-00100 | Mailbox Supports (Single) | 65 | EACH | 250.00 | 16,250.00 | 20.00 | 1,300.00 | 300.00 | 19,500.00 | | 0035 | 739-01-00100 | Hydro-Seeding | 4.437 | ACRE | 2,750.00 | 12,201.75 | 2,750.00 | 12,201.75 | 3,200.00 | 14,198.40 | | 0036 | 740-01-00100 | Construction Layout | 1 | LUMP | 20,000.00 | 20,000.00 | 43,000.00 | 43,000.00 | 35,000.00 | 35,000.00 | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 5,809,654.57 | | 6,091,365.38 | | 7,943,549.85 |
|