Proposal:H.015232.6
Parish:Lincoln
Routes:LA 146
Description:LA 146: DRAINAGE IMPROVEMENTS
Type Construction:MILLING ASPHALT CONCRETE, ASPHALT CONCRETE PAVEMENT, AND RELATED WORK.
Estimated Construction Cost:$399,663.50
| Rank | License | Bidder | Construction Bid |
| 1 | 15099 | Amethyst Construction, Inc. | $390,680.50 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Amethyst Construction, Inc. |
| Unit Price | Total Amount |
| 0001 | 203-07-00100 | Borrow (Vehicular Measurement) | 170 | CUYD | 95.00 | 16,150.00 |
| 0002 | 204-06-00100 | Temporary Silt Fencing | 1,200 | LNFT | 7.00 | 8,400.00 |
| 0003 | 502-01-00100 | Asphalt Concrete | 809.5 | TON | 275.00 | 222,612.50 |
| 0004 | 509-01-00100 | Milling Asphalt Pavement | 363 | SQYD | 30.00 | 10,890.00 |
| 0005 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -10 | CUYD | 1.00 | -10.00 |
| 0006 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 65,000.00 | 65,000.00 |
| 0007 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 0.624 | MILE | 1,500.00 | 936.00 |
| 0008 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 2.496 | MILE | 2,400.00 | 5,990.40 |
| 0009 | 716-01-00100 | Mulch (Vegetative) | 0.4 | TON | 8,500.00 | 3,400.00 |
| 0010 | 717-01-00100 | Seeding | 11 | LB | 10.00 | 110.00 |
| 0011 | 718-01-00100 | Fertilizer | 208 | LB | 1.00 | 208.00 |
| 0012 | 727-01-00100 | Mobilization | 1 | LUMP | 35,000.00 | 35,000.00 |
| 0013 | 731-02-00100 | Reflectorized Raised Pavement Markers | 27 | EACH | 30.00 | 810.00 |
| 0014 | 731-03-00100 | Removal of Raised Pavement Markers | 0.104 | MILE | 650.00 | 67.60 |
| 0015 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 0.416 | MILE | 13,500.00 | 5,616.00 |
| 0016 | 740-01-00100 | Construction Layout | 1 | LUMP | 15,500.00 | 15,500.00 |
| | | | | | | |
| | | CONTRACTOR TOTAL | | | | 390,680.50 |