Proposal:H.014485.6
Parish:Calcasieu
Routes:LA 14, US 171
Description:LA 14: POWER CENTER PKWY - US 90
Type Construction:GRADING, MILLING ASPHALT CONCRETE, ASPHALT CONCRETE OVERLAY AND RELATED WORK.
Estimated Construction Cost:$7,236,687.66
| Rank | License | Bidder | Construction Bid |
| 1 | 30774 | Progressive Construction Co., LLC | $11,222,719.06 |
| 2 | 52306 | SIEMA CONSTRUCTION, LLC | $11,517,785.70 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Progressive Construction Co., LLC | - 2 - SIEMA CONSTRUCTION, LLC | | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 202-02-06060 | Removal of Concrete Catch Basin | 3 | EACH | 2,000.00 | 6,000.00 | 850.00 | 2,550.00 | | 0002 | 202-02-06080 | Removal of Concrete Combination Curb and Gutter | 6,941 | LNFT | 27.00 | 187,407.00 | 33.50 | 232,523.50 | | 0003 | 202-02-06100 | Removal of Concrete Walks and Drives | 4,265 | SQYD | 24.00 | 102,360.00 | 41.15 | 175,504.75 | | 0004 | 202-02-06140 | Removal of Curbs (Concrete) | 120 | LNFT | 22.00 | 2,640.00 | 4.75 | 570.00 | | 0005 | 202-02-32140 | Removal of Pipe (Storm Drain) 15" RCP | 24 | LNFT | 70.00 | 1,680.00 | 30.00 | 720.00 | | 0006 | 202-02-32140 | Removal of Pipe (Storm Drain) 18" RCP | 16 | LNFT | 70.00 | 1,120.00 | 45.00 | 720.00 | | 0007 | 202-02-32140 | Removal of Pipe (Storm Drain) 24" RCP | 16 | LNFT | 70.00 | 1,120.00 | 45.00 | 720.00 | | 0008 | 203-01-00100 | General Excavation | 50 | CUYD | 50.00 | 2,500.00 | 23.00 | 1,150.00 | | 0009 | 203-07-00100 | Borrow (Vehicular Measurement) | 41 | CUYD | 50.00 | 2,050.00 | 50.00 | 2,050.00 | | 0010 | 204-02-00100 | Temporary Hay Bales | 24 | EACH | 50.00 | 1,200.00 | 83.00 | 1,992.00 | | 0011 | 402-01-00101 | Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) | 695 | CUYD | 165.00 | 114,675.00 | 142.25 | 98,863.75 | | 0012 | 501-03-00100 | Thin Asphalt Concrete (OGFC) | 4,901.8 | TON | 265.00 | 1,298,977.00 | 230.00 | 1,127,414.00 | | 0013 | 502-01-00100 | Asphalt Concrete | 2,507.9 | TON | 165.00 | 413,803.50 | 149.00 | 373,677.10 | | 0014 | 509-01-00100 | Milling Asphalt Pavement | 20,020 | SQYD | 7.00 | 140,140.00 | 6.15 | 123,123.00 | | 0015 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -1,076 | CUYD | 0.01 | -10.76 | 0.01 | -10.76 | | 0016 | 602-02-00200 | Cleaning and Resealing Existing Longitudinal Pavement Joints | 79,599 | LNFT | 3.75 | 298,496.25 | 3.85 | 306,456.15 | | 0017 | 602-02-00300 | Cleaning and Resealing Existing Transverse Pavements Joints | 62,809 | LNFT | 3.75 | 235,533.75 | 4.15 | 260,657.35 | | 0018 | 602-03-00100 | Cleaning and Sealing Random Cracks | 4,918 | LNFT | 8.50 | 41,803.00 | 8.75 | 43,032.50 | | 0019 | 602-05-01200 | Full Depth Patching of Jointed Concrete Pavement (16.0 square yards and under) (10" Thick) | 1,768.1 | SQYD | 303.00 | 535,734.30 | 315.00 | 556,951.50 | | 0020 | 602-05-02200 | Full Depth Patching of Jointed Concrete Pavement (16.1 square yards to 48.0 square yards) (10" Thick) | 2,789.4 | SQYD | 254.00 | 708,507.60 | 235.00 | 655,509.00 | | 0021 | 602-05-03200 | Full Depth Patching of Jointed Concrete Pavement (48.1 square yards and over) (10" Thick) | 3,206.6 | SQYD | 209.00 | 670,179.40 | 200.00 | 641,320.00 | | 0022 | 602-06-00100 | Partial Depth Patching of Jointed Concrete Pavement | 160.8 | SQYD | 3,000.00 | 482,400.00 | 1,245.00 | 200,196.00 | | 0023 | 701-03-01002 | Storm Drain Pipe (15" RCP/RPVCP) | 46 | LNFT | 175.00 | 8,050.00 | 135.00 | 6,210.00 | | 0024 | 701-03-01022 | Storm Drain Pipe (18" RCP/RPVCP) | 16 | LNFT | 230.00 | 3,680.00 | 186.00 | 2,976.00 | | 0025 | 701-03-01042 | Storm Drain Pipe (24" RCP/RPVCP) | 30 | LNFT | 250.00 | 7,500.00 | 195.00 | 5,850.00 | | 0026 | 701-15-00100 | Concrete Collar | 4 | EACH | 2,300.00 | 9,200.00 | 1,285.00 | 5,140.00 | | 0027 | 702-02-00100 | Manholes (MH-06) | 1 | EACH | 6,400.00 | 6,400.00 | 16,700.00 | 16,700.00 | | 0028 | 702-03-00001 | Catch Basin (Remove and Replace Frame and Cover) | 10 | EACH | 6,400.00 | 64,000.00 | 6,500.00 | 65,000.00 | | 0029 | 702-03-00100 | Catch Basins (CB-01) | 3 | EACH | 7,200.00 | 21,600.00 | 16,700.00 | 50,100.00 | | 0030 | 702-03-00500 | Catch Basins (CB-06) | 3 | EACH | 7,200.00 | 21,600.00 | 16,900.00 | 50,700.00 | | 0031 | 702-04-00001 | Adjusting Miscellaneous Structures (Replace Drainage Grates) | 2 | EACH | 6,400.00 | 12,800.00 | 4,100.00 | 8,200.00 | | 0032 | 702-04-00150 | Adjusting Manholes w/Manhole Adjustment Rings | 9 | EACH | 750.00 | 6,750.00 | 670.00 | 6,030.00 | | 0033 | 702-04-00200 | Adjusting Catch Basins | 6 | EACH | 6,800.00 | 40,800.00 | 9,000.00 | 54,000.00 | | 0034 | 706-02-00200 | Concrete Drive (6" Thick) | 4,248 | SQYD | 108.00 | 458,784.00 | 135.00 | 573,480.00 | | 0035 | 706-03-00300 | Incidental Concrete Paving (6" Thick) | 24 | SQYD | 165.00 | 3,960.00 | 165.00 | 3,960.00 | | 0036 | 707-01-00100 | Concrete Curb | 120 | LNFT | 40.00 | 4,800.00 | 42.00 | 5,040.00 | | 0037 | 707-03-00100 | Combination Concrete Curb and Gutter | 6,941 | LNFT | 71.00 | 492,811.00 | 89.00 | 617,749.00 | | 0038 | 710-01-00100 | Flowable Fill | 40 | CUYD | 300.00 | 12,000.00 | 214.00 | 8,560.00 | | 0039 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 378,000.00 | 378,000.00 | 500,000.00 | 500,000.00 | | 0040 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 3,194 | LNFT | 0.80 | 2,555.20 | 0.51 | 1,628.94 | | 0041 | 713-02-00400 | Temporary Pavement Markings (12" Width) | 480 | LNFT | 1.10 | 528.00 | 0.51 | 244.80 | | 0042 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 3,512 | LNFT | 1.65 | 5,794.80 | 1.50 | 5,268.00 | | 0043 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 6.718 | MILE | 1,700.00 | 11,420.60 | 1,283.00 | 8,619.19 | | 0044 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 13.436 | MILE | 1,600.00 | 21,497.60 | 821.00 | 11,030.96 | | 0045 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 14.406 | MILE | 3,000.00 | 43,218.00 | 1,283.00 | 18,482.90 | | 0046 | 713-05-00200 | Temporary Pavement Legends & Symbols (Arrow - Double) | 1 | EACH | 110.00 | 110.00 | 25.50 | 25.50 | | 0047 | 713-05-00220 | Temporary Pavement Legends & Symbols (Arrow - Left Turn) | 72 | EACH | 110.00 | 7,920.00 | 25.50 | 1,836.00 | | 0048 | 713-05-00300 | Temporary Pavement Legends & Symbols (ONLY) | 3 | EACH | 110.00 | 330.00 | 20.50 | 61.50 | | 0049 | 713-05-00400 | Temporary Pavement Legends & Symbols (RR Crossing) | 4 | EACH | 110.00 | 440.00 | 103.00 | 412.00 | | 0050 | 713-11-00100 | Portable Changeable Message Signs | 6 | EACH | 21,000.00 | 126,000.00 | 40,000.00 | 240,000.00 | | 0051 | 714-01-00600 | Slab Sodding (St. Augustine) | 61 | SQYD | 55.00 | 3,355.00 | 56.50 | 3,446.50 | | 0052 | 726-01-00100 | Bedding Material | 12 | CUYD | 140.00 | 1,680.00 | 200.00 | 2,400.00 | | 0053 | 727-01-00100 | Mobilization | 1 | LUMP | 1,100,000.00 | 1,100,000.00 | 1,145,000.00 | 1,145,000.00 | | 0054 | 731-02-00100 | Reflectorized Raised Pavement Markers | 2,751 | EACH | 14.00 | 38,514.00 | 8.75 | 24,071.25 | | 0055 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 2,228 | LNFT | 8.00 | 17,824.00 | 4.25 | 9,469.00 | | 0056 | 732-01-01060 | Plastic Pavement Striping (12" Width) (Thermoplastic 90 mil) | 480 | LNFT | 18.00 | 8,640.00 | 9.75 | 4,680.00 | | 0057 | 732-01-02040 | Plastic Pavement Striping (8" Width) (Thermoplastic 125 mil) | 503 | LNFT | 9.00 | 4,527.00 | 5.25 | 2,640.75 | | 0058 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 2,501 | LNFT | 38.00 | 95,038.00 | 21.55 | 53,896.55 | | 0059 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 12.566 | MILE | 10,000.00 | 125,660.00 | 6,980.00 | 87,710.68 | | 0060 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 11.139 | MILE | 3,100.00 | 34,530.90 | 3,182.00 | 35,444.30 | | 0061 | 732-03-02010 | Plastic Pavement Striping (Dotted Line)(4" W)(2' L)(Thermo 90 mil) | 0.303 | MILE | 11,000.00 | 3,333.00 | 5,130.00 | 1,554.39 | | 0062 | 732-03-02030 | Plastic Pavement Striping (Dotted Line)(8" W)(2' L)(Thermo 90 mil) | 0.177 | MILE | 14,000.00 | 2,478.00 | 13,865.00 | 2,454.11 | | 0063 | 732-04-00001 | Plastic Pavement Legends and Symbols (Message) WEST | 2 | EACH | 1,650.00 | 3,300.00 | 821.00 | 1,642.00 | | 0064 | 732-04-01040 | Plastic Pavement Legends and Symbols (Arrow - Double) | 1 | EACH | 1,300.00 | 1,300.00 | 821.00 | 821.00 | | 0065 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 72 | EACH | 1,300.00 | 93,600.00 | 410.50 | 29,556.00 | | 0066 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 3 | EACH | 1,300.00 | 3,900.00 | 410.50 | 1,231.50 | | 0067 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 3 | EACH | 1,300.00 | 3,900.00 | 410.50 | 1,231.50 | | 0068 | 732-04-18000 | Plastic Pavement Legends and Symbols (RR Crossing) | 4 | EACH | 1,300.00 | 5,200.00 | 1,232.00 | 4,928.00 | | 0069 | 732-04-19040 | Plastic Pavement Legends and Symbols (Shield - Interstate) (Preformed Heat Applied Retroreflective Thermoplastic) | 2 | EACH | 2,700.00 | 5,400.00 | 1,695.00 | 3,390.00 | | 0070 | 732-05-00100 | Removal of Existing Markings | 2.894 | MILE | 55,000.00 | 159,170.00 | 13,850.00 | 40,081.90 | | 0071 | 740-01-00100 | Construction Layout | 1 | LUMP | 82,000.00 | 82,000.00 | 100,000.00 | 100,000.00 | | 0072 | 741-35-00100 | Adjust Valve or Meter Box | 45 | EACH | 900.00 | 40,500.00 | 500.00 | 22,500.00 | | 0073 | 815-02-00500 | Sealed Expansion Joint EJ-4INCH | 2,607 | LNFT | 125.00 | 325,875.00 | 7.50 | 19,552.50 | | 0074 | 830-07-00100 | Structural Concrete Patching | 6 | SQFT | 2,900.00 | 17,400.00 | 805.00 | 4,830.00 | | 0075 | NS-500-00220 | Sawing and Sealing Longitudinal Joints in Asphalt Concrete Overlay | 12,908 | LNFT | 3.00 | 38,724.00 | 3.60 | 46,468.80 | | 0076 | NS-500-00240 | Sawing and Sealing Transverse Joints in Asphalt Concrete Overlay | 10,143 | LNFT | 3.00 | 30,429.00 | 3.60 | 36,514.80 | | 0077 | NS-500-00260 | Sawcuts in Asphalt Concrete Lifts | 5,360 | LNFT | 2.00 | 10,720.00 | 2.05 | 10,988.00 | | 0078 | NS-509-00100 | Asphalt Diamond Grinding | 194.44 | SQYD | 53.00 | 10,305.32 | 11.00 | 2,138.84 | | 0079 | NS-509-00110 | Asphalt Diamond Grinding of Pavement Edges | 666.7 | SQYD | 53.00 | 35,335.10 | 11.00 | 7,333.70 | | 0080 | NS-602-00001 | Milling Concrete Pavement | 5,336.5 | SQYD | 27.00 | 144,085.50 | 26.00 | 138,749.00 | | 0081 | NS-602-00011 | Expansion Joint Rehabilitation | 2,607 | LNFT | 400.00 | 1,042,800.00 | 750.00 | 1,955,250.00 | | 0082 | NS-602-00014 | Pavement Repair System | 933 | CUFT | 710.00 | 662,430.00 | 652.00 | 608,316.00 | | 0083 | NS-702-00001 | Cleaning Existing Catch Basin | 3 | EACH | 1,700.00 | 5,100.00 | 500.00 | 1,500.00 | | 0084 | NS-DEV-00005 | Adjusting Catch Basins w\ Inlet Risers | 7 | EACH | 6,400.00 | 44,800.00 | 5,000.00 | 35,000.00 | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 11,222,719.06 | | 11,517,785.70 |
|