Proposal:H.014136.6
Parish:Tensas
Routes: LA 573
Description:LA 573: COOTER POINT RD. - LA 892
Type Construction:CLEARING AND GRUBBING, MILLING ASPHALT PAVEMENT, PAVEMENT PATCHING, ASPHALT CONCRETE OVERLAY, AND RELATED WORK.
Estimated Construction Cost:$2,352,670.45
| Rank | License | Bidder | Construction Bid |
| 1 | 05789 | D & J CONSTRUCTION CO., LLC | $2,427,259.80 |
| 2 | 12487 | Diamond B Construction Co., L.L.C. | $2,974,781.99 |
| 3 | 12312 | GILCHRIST CONSTRUCTION COMPANY, LLC | $3,004,708.00 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - D & J CONSTRUCTION CO., LLC | - 2 - Diamond B Construction Co., L.L.C. | - 3 - GILCHRIST CONSTRUCTION COMPANY, LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 201-01-00200 | Clearing and Grubbing (Selective) | 1 | LUMP | 7,500.00 | 7,500.00 | 3,500.00 | 3,500.00 | 85,000.00 | 85,000.00 | | 0002 | 202-02-32100 | Removal of Pipe (Cross Drain) 24", 30" & 36" RCP | 32 | LNFT | 20.00 | 640.00 | 22.00 | 704.00 | 500.00 | 16,000.00 | | 0003 | 203-07-00100 | Borrow (Vehicular Measurement) | 260 | CUYD | 25.00 | 6,500.00 | 45.00 | 11,700.00 | 50.00 | 13,000.00 | | 0004 | 204-06-00100 | Temporary Silt Fencing | 300 | LNFT | 5.00 | 1,500.00 | 5.00 | 1,500.00 | 6.00 | 1,800.00 | | 0005 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 1,796 | CUYD | 100.00 | 179,600.00 | 200.00 | 359,200.00 | 150.00 | 269,400.00 | | 0006 | 502-01-00100 | Asphalt Concrete | 10,254.2 | TON | 150.00 | 1,538,130.00 | 165.00 | 1,691,943.00 | 164.00 | 1,681,688.80 | | 0007 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 379.6 | TON | 150.00 | 56,940.00 | 350.00 | 132,860.00 | 330.00 | 125,268.00 | | 0008 | 509-01-00100 | Milling Asphalt Pavement | 508 | SQYD | 25.00 | 12,700.00 | 30.00 | 15,240.00 | 40.00 | 20,320.00 | | 0009 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -14 | CUYD | 1.00 | -14.00 | 1.00 | -14.00 | 1.00 | -14.00 | | 0010 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 550 | SQYD | 225.00 | 123,750.00 | 225.00 | 123,750.00 | 225.00 | 123,750.00 | | 0011 | 701-08-00100 | Relaying Pipe 36" RCP | 4 | LNFT | 350.00 | 1,400.00 | 300.00 | 1,200.00 | 450.00 | 1,800.00 | | 0012 | 701-10-01060 | Reinforced Concrete Pipe (Extension) (24") | 32 | LNFT | 300.00 | 9,600.00 | 285.00 | 9,120.00 | 320.00 | 10,240.00 | | 0013 | 701-10-01080 | Reinforced Concrete Pipe (Extension) (30") | 8 | LNFT | 325.00 | 2,600.00 | 315.00 | 2,520.00 | 360.00 | 2,880.00 | | 0014 | 701-10-01100 | Reinforced Concrete Pipe (Extension) (36") | 8 | LNFT | 335.00 | 2,680.00 | 325.00 | 2,600.00 | 420.00 | 3,360.00 | | 0015 | 701-15-00100 | Concrete Collar | 6 | EACH | 1,500.00 | 9,000.00 | 2,750.00 | 16,500.00 | 3,500.00 | 21,000.00 | | 0016 | 711-01-04020 | Riprap (55 lb, 24" Thick) | 22 | SQYD | 150.00 | 3,300.00 | 200.00 | 4,400.00 | 375.00 | 8,250.00 | | 0017 | 711-04-00100 | Geotextile Fabric | 22 | SQYD | 5.00 | 110.00 | 15.00 | 330.00 | 4.00 | 88.00 | | 0018 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 34,000.00 | 34,000.00 | 55,000.00 | 55,000.00 | 51,000.00 | 51,000.00 | | 0019 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 7.902 | MILE | 300.00 | 2,370.60 | 154.00 | 1,216.91 | 250.00 | 1,975.50 | | 0020 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 4.175 | MILE | 700.00 | 2,922.50 | 725.00 | 3,026.88 | 700.00 | 2,922.50 | | 0021 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 26.376 | MILE | 1,200.00 | 31,651.20 | 1,200.00 | 31,651.20 | 900.00 | 23,738.40 | | 0022 | 716-01-00100 | Mulch (Vegetative) | 0.2 | TON | 4,000.00 | 800.00 | 10,000.00 | 2,000.00 | 6,000.00 | 1,200.00 | | 0023 | 717-01-00100 | Seeding | 6 | LB | 25.00 | 150.00 | 100.00 | 600.00 | 160.00 | 960.00 | | 0024 | 718-01-00100 | Fertilizer | 100 | LB | 5.00 | 500.00 | 15.00 | 1,500.00 | 6.00 | 600.00 | | 0025 | 726-01-00100 | Bedding Material | 26.6 | CUYD | 130.00 | 3,458.00 | 200.00 | 5,320.00 | 225.00 | 5,985.00 | | 0026 | 727-01-00100 | Mobilization | 1 | LUMP | 160,000.00 | 160,000.00 | 254,000.00 | 254,000.00 | 300,000.00 | 300,000.00 | | 0027 | 729-16-00200 | Object Marker Assembly (Type 2) | 12 | EACH | 85.00 | 1,020.00 | 115.00 | 1,380.00 | 110.00 | 1,320.00 | | 0028 | 731-02-00100 | Reflectorized Raised Pavement Markers | 1,536 | EACH | 7.00 | 10,752.00 | 6.00 | 9,216.00 | 7.00 | 10,752.00 | | 0029 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 26.376 | MILE | 5,750.00 | 151,662.00 | 5,500.00 | 145,068.00 | 3,800.00 | 100,228.80 | | 0030 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 4.175 | MILE | 1,500.00 | 6,262.50 | 1,200.00 | 5,010.00 | 1,400.00 | 5,845.00 | | 0031 | 735-01-00100 | Mailboxes | 15 | EACH | 35.00 | 525.00 | 1.00 | 15.00 | 30.00 | 450.00 | | 0032 | 735-02-00100 | Mailbox Supports (Single) | 15 | EACH | 350.00 | 5,250.00 | 515.00 | 7,725.00 | 260.00 | 3,900.00 | | 0033 | 740-01-00100 | Construction Layout | 1 | LUMP | 20,000.00 | 20,000.00 | 15,000.00 | 15,000.00 | 25,000.00 | 25,000.00 | | 0034 | NS-719-00002 | Tree Trimming | 1 | LUMP | 40,000.00 | 40,000.00 | 60,000.00 | 60,000.00 | 85,000.00 | 85,000.00 | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 2,427,259.80 | | 2,974,781.99 | | 3,004,708.00 |
|