Proposal:H.015559.6
Parish:West Feliciana
Routes: LA 10
Description:LA 10: US 61 - 1.3 MI E US 61
Type Construction:MILLING ASPHALT CONCRETE, PAVEMENT PATCHING, ASPHALT CONCRETE OVERLAY, AND RELATED WORK.
Estimated Construction Cost:$1,291,800.76
| Rank | License | Bidder | Construction Bid |
| 1 | 06276 | Barriere Construction Co., LLC | $1,167,692.73 |
| 2 | 12031 | R.J. Daigle & Sons Contractors, Inc | $1,246,613.33 |
| 3 | 00046 | Barber Bros. Contracting Co., L.L.C | $1,277,379.15 |
| 4 | 73475 | Madden Gulf Coast, LLC | $1,294,596.33 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Barriere Construction Co., LLC | - 2 - R.J. Daigle & Sons Contractors, Inc | - 3 - Barber Bros. Contracting Co., L.L.C | - 4 - Madden Gulf Coast, LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 202-02-06100 | Removal of Concrete Walks and Drives | 400 | SQYD | 24.25 | 9,700.00 | 35.00 | 14,000.00 | 14.00 | 5,600.00 | 23.00 | 9,200.00 | | 0002 | 202-02-06120 | Removal of Curbs (Asphalt) | 436 | LNFT | 0.50 | 218.00 | 5.00 | 2,180.00 | 1.00 | 436.00 | 10.00 | 4,360.00 | | 0003 | 202-02-14500 | Removal of Guard Rail | 1,520 | LNFT | 6.00 | 9,120.00 | 10.00 | 15,200.00 | 10.00 | 15,200.00 | 6.00 | 9,120.00 | | 0004 | 203-07-00100 | Borrow (Vehicular Measurement) | 1,200 | CUYD | 45.00 | 54,000.00 | 65.00 | 78,000.00 | 48.00 | 57,600.00 | 45.00 | 54,000.00 | | 0005 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 330 | CUYD | 70.00 | 23,100.00 | 130.00 | 42,900.00 | 100.00 | 33,000.00 | 137.00 | 45,210.00 | | 0006 | 502-01-00100 | Asphalt Concrete | 3,521.9 | TON | 121.00 | 426,149.90 | 121.50 | 427,910.85 | 130.00 | 457,847.00 | 110.00 | 387,409.00 | | 0007 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 500 | TON | 200.00 | 100,000.00 | 175.00 | 87,500.00 | 130.00 | 65,000.00 | 150.00 | 75,000.00 | | 0008 | 509-01-00100 | Milling Asphalt Pavement | 15,399 | SQYD | 3.00 | 46,197.00 | 3.50 | 53,896.50 | 3.50 | 53,896.50 | 2.50 | 38,497.50 | | 0009 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -687 | CUYD | 0.01 | -6.87 | 0.01 | -6.87 | 0.00 | 0.00 | 0.01 | -6.87 | | 0010 | 510-01-00300 | Pavement Patching (18" Minimum Thickness) | 1,000 | SQYD | 166.00 | 166,000.00 | 186.00 | 186,000.00 | 140.00 | 140,000.00 | 158.00 | 158,000.00 | | 0011 | 704-03-00200 | Blocked Out Guard Rail - 31", (6'-3" Post Spacing) | 600 | LNFT | 28.50 | 17,100.00 | 32.00 | 19,200.00 | 35.00 | 21,000.00 | 28.50 | 17,100.00 | | 0012 | 704-06-00200 | Guard Rail Bridge Attachments (Single Thrie Beam) | 100 | LNFT | 40.00 | 4,000.00 | 44.00 | 4,400.00 | 50.00 | 5,000.00 | 40.00 | 4,000.00 | | 0013 | 704-07-00200 | Guard Rail Transitions (Double Thrie Beam) | 200 | LNFT | 108.00 | 21,600.00 | 120.00 | 24,000.00 | 130.00 | 26,000.00 | 108.00 | 21,600.00 | | 0014 | 704-10-00205 | Guard Rail End Treatment, MASH, (TL-3 Tangent) | 8 | EACH | 3,200.00 | 25,600.00 | 3,500.00 | 28,000.00 | 4,000.00 | 32,000.00 | 3,200.00 | 25,600.00 | | 0015 | 706-02-00200 | Concrete Drive (6" Thick) | 400 | SQYD | 97.25 | 38,900.00 | 90.00 | 36,000.00 | 115.00 | 46,000.00 | 112.00 | 44,800.00 | | 0016 | 711-03-00500 | Riprap (130 lb) | 40 | TON | 325.00 | 13,000.00 | 222.00 | 8,880.00 | 225.00 | 9,000.00 | 350.00 | 14,000.00 | | 0017 | 711-04-00100 | Geotextile Fabric | 100 | SQYD | 1.50 | 150.00 | 6.50 | 650.00 | 3.00 | 300.00 | 15.00 | 1,500.00 | | 0018 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 78,000.00 | 78,000.00 | 65,000.00 | 65,000.00 | 112,000.00 | 112,000.00 | 150,000.00 | 150,000.00 | | 0019 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 3.9 | MILE | 650.00 | 2,535.00 | 300.00 | 1,170.00 | 250.00 | 975.00 | 350.00 | 1,365.00 | | 0020 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 1.947 | MILE | 700.00 | 1,362.90 | 1,100.00 | 2,141.70 | 700.00 | 1,362.90 | 700.00 | 1,362.90 | | 0021 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 12.681 | MILE | 1,000.00 | 12,681.00 | 1,400.00 | 17,753.40 | 1,000.00 | 12,681.00 | 1,000.00 | 12,681.00 | | 0022 | 720-01-02000 | Erosion Control System, Flexible (Channel Liner) (Type C) | 800 | SQYD | 3.25 | 2,600.00 | 3.50 | 2,800.00 | 3.50 | 2,800.00 | 3.10 | 2,480.00 | | 0023 | 727-01-00100 | Mobilization | 1 | LUMP | 72,000.00 | 72,000.00 | 80,000.00 | 80,000.00 | 120,000.00 | 120,000.00 | 128,000.00 | 128,000.00 | | 0024 | 729-16-00300 | Object Marker Assembly (Type 3) | 8 | EACH | 85.00 | 680.00 | 95.00 | 760.00 | 125.00 | 1,000.00 | 85.00 | 680.00 | | 0025 | 731-02-00100 | Reflectorized Raised Pavement Markers | 259 | EACH | 6.00 | 1,554.00 | 11.00 | 2,849.00 | 7.00 | 1,813.00 | 6.00 | 1,554.00 | | 0026 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 10 | LNFT | 22.00 | 220.00 | 22.00 | 220.00 | 25.00 | 250.00 | 22.00 | 220.00 | | 0027 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 4.227 | MILE | 5,000.00 | 21,135.00 | 5,500.00 | 23,248.50 | 5,800.00 | 24,516.60 | 5,000.00 | 21,135.00 | | 0028 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.649 | MILE | 1,200.00 | 778.80 | 2,250.00 | 1,460.25 | 1,350.00 | 876.15 | 1,200.00 | 778.80 | | 0029 | 735-01-00100 | Mailboxes | 5 | EACH | 20.00 | 100.00 | 40.00 | 200.00 | 25.00 | 125.00 | 250.00 | 1,250.00 | | 0030 | 735-02-00100 | Mailbox Supports (Single) | 5 | EACH | 250.00 | 1,250.00 | 300.00 | 1,500.00 | 300.00 | 1,500.00 | 20.00 | 100.00 | | 0031 | 739-01-00100 | Hydro-Seeding | 4 | ACRE | 2,867.00 | 11,468.00 | 3,200.00 | 12,800.00 | 2,900.00 | 11,600.00 | 2,900.00 | 11,600.00 | | 0032 | 740-01-00100 | Construction Layout | 1 | LUMP | 6,500.00 | 6,500.00 | 6,000.00 | 6,000.00 | 18,000.00 | 18,000.00 | 52,000.00 | 52,000.00 | | | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 1,167,692.73 | | 1,246,613.33 | | 1,277,379.15 | | 1,294,596.33 |
|