Proposal:H.015556.6
Parish:Assumption
Routes:LA 308
Description:LA 308: LA 1011 - FRANKLIN AVE
Type Construction:DRAINAGE STRUCTURES, PAVEMENT PATCHING, THIN ASPHALT CONCRETE OVERLAY, AND RELATED WORK.
Estimated Construction Cost:$1,352,940.71
| Rank | License | Bidder | Construction Bid |
| 1 | 00046 | Barber Bros. Contracting Co., L.L.C | $1,914,596.98 |
| 2 | 06276 | Barriere Construction Co., LLC | $2,058,583.44 |
| 3 | 62139 | Huey P. Stockstill, LLC | $2,162,078.47 |
| 4 | 73475 | Madden Gulf Coast, LLC | $2,279,610.28 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Barber Bros. Contracting Co., L.L.C | - 2 - Barriere Construction Co., LLC | - 3 - Huey P. Stockstill, LLC | - 4 - Madden Gulf Coast, LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 202-02-06060 | Removal of Concrete Catch Basin | 2 | EACH | 2,100.00 | 4,200.00 | 255.00 | 510.00 | 1,800.00 | 3,600.00 | 1,000.00 | 2,000.00 | | 0002 | 202-02-14500 | Removal of Guard Rail | 489 | LNFT | 9.00 | 4,401.00 | 9.00 | 4,401.00 | 9.50 | 4,645.50 | 10.00 | 4,890.00 | | 0003 | 202-02-32100 | Removal of Pipe (Cross Drain) 24" RCP, 24" CMP, 30" CMP | 206 | LNFT | 35.00 | 7,210.00 | 35.00 | 7,210.00 | 65.00 | 13,390.00 | 40.00 | 8,240.00 | | 0004 | 202-02-32120 | Removal of Pipe (Side Drain) 18" RPVCCP | 20 | LNFT | 35.00 | 700.00 | 35.00 | 700.00 | 60.00 | 1,200.00 | 40.00 | 800.00 | | 0005 | 202-02-32140 | Removal of Pipe (Storm Drain) 24" RPECP | 72 | LNFT | 35.00 | 2,520.00 | 25.00 | 1,800.00 | 65.00 | 4,680.00 | 40.00 | 2,880.00 | | 0006 | 202-02-32180 | Removal of Pipe Headwalls | 4 | EACH | 3,000.00 | 12,000.00 | 250.00 | 1,000.00 | 1,205.00 | 4,820.00 | 500.00 | 2,000.00 | | 0007 | 203-07-00100 | Borrow (Vehicular Measurement) | 1,159 | CUYD | 55.00 | 63,745.00 | 120.00 | 139,080.00 | 25.00 | 28,975.00 | 40.00 | 46,360.00 | | 0008 | 203-10-00100 | Cleaning Existing Ditches | 6,200 | LNFT | 16.00 | 99,200.00 | 15.00 | 93,000.00 | 22.00 | 136,400.00 | 9.00 | 55,800.00 | | 0009 | 204-06-00100 | Temporary Silt Fencing | 400 | LNFT | 3.00 | 1,200.00 | 5.00 | 2,000.00 | 5.00 | 2,000.00 | 6.00 | 2,400.00 | | 0010 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 649 | CUYD | 125.00 | 81,125.00 | 1.00 | 649.00 | 185.00 | 120,065.00 | 50.00 | 32,450.00 | | 0011 | 402-01-00101 | Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) | 239.7 | CUYD | 90.00 | 21,573.00 | 5.00 | 1,198.50 | 295.00 | 70,711.50 | 1.00 | 239.70 | | 0012 | 501-02-00100 | Thin Asphalt Concrete (Coarse Mix) | 3,257.3 | TON | 198.00 | 644,945.40 | 181.00 | 589,571.30 | 200.00 | 651,460.00 | 190.00 | 618,887.00 | | 0013 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 281.2 | TON | 220.00 | 61,864.00 | 500.00 | 140,600.00 | 300.00 | 84,360.00 | 475.00 | 133,570.00 | | 0014 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -8 | CUYD | 0.00 | 0.00 | 0.01 | -0.08 | 0.01 | -0.08 | 0.01 | -0.08 | | 0015 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 84 | SQYD | 230.00 | 19,320.00 | 220.00 | 18,480.00 | 205.00 | 17,220.00 | 300.00 | 25,200.00 | | 0016 | 510-01-00300 | Pavement Patching (18" Minimum Thickness) | 151 | SQYD | 280.00 | 42,280.00 | 205.00 | 30,955.00 | 290.00 | 43,790.00 | 350.00 | 52,850.00 | | 0017 | 701-01-01001 | Cross Drain Pipe (24" RCP) | 168 | LNFT | 310.00 | 52,080.00 | 325.00 | 54,600.00 | 205.00 | 34,440.00 | 260.00 | 43,680.00 | | 0018 | 701-01-01021 | Cross Drain Pipe (30" RCP) | 56 | LNFT | 370.00 | 20,720.00 | 360.00 | 20,160.00 | 275.00 | 15,400.00 | 360.00 | 20,160.00 | | 0019 | 701-03-01110 | Storm Drain Pipe (24" RCP) | 72 | LNFT | 300.00 | 21,600.00 | 325.00 | 23,400.00 | 250.00 | 18,000.00 | 280.00 | 20,160.00 | | 0020 | 701-06-00040 | Side Drain Pipe Arch (24" Equiv. RCPA) | 24 | LNFT | 390.00 | 9,360.00 | 300.00 | 7,200.00 | 285.00 | 6,840.00 | 250.00 | 6,000.00 | | 0021 | 701-14-00100 | Cleaning Existing Pipes | 524 | LNFT | 46.00 | 24,104.00 | 80.00 | 41,920.00 | 65.00 | 34,060.00 | 20.00 | 10,480.00 | | 0022 | 701-17-00100 | Trench Excavation Safety Protection (Depth >5 feet) | 128 | LNFT | 0.00 | 0.00 | 10.00 | 1,280.00 | 225.00 | 28,800.00 | 20.00 | 2,560.00 | | 0023 | 702-03-00100 | Catch Basins (CB-01) | 2 | EACH | 8,000.00 | 16,000.00 | 8,000.00 | 16,000.00 | 7,500.00 | 15,000.00 | 7,500.00 | 15,000.00 | | 0024 | 704-01-01020 | Guard Rail (Single Thrie Beam) (6'-3" post spacing) | 125 | LNFT | 218.00 | 27,250.00 | 200.00 | 25,000.00 | 240.00 | 30,000.00 | 200.00 | 25,000.00 | | 0025 | 704-03-00200 | Blocked Out Guard Rail - 31", (6'-3" Post Spacing) | 737.5 | LNFT | 36.00 | 26,550.00 | 34.00 | 25,075.00 | 40.00 | 29,500.00 | 35.00 | 25,812.50 | | 0026 | 704-07-00200 | Guard Rail Transitions (Double Thrie Beam) | 100 | LNFT | 138.00 | 13,800.00 | 130.00 | 13,000.00 | 150.00 | 15,000.00 | 125.00 | 12,500.00 | | 0027 | 704-10-00205 | Guard Rail End Treatment, MASH, (TL-3 Tangent) | 7 | EACH | 4,100.00 | 28,700.00 | 3,900.00 | 27,300.00 | 4,500.00 | 31,500.00 | 4,000.00 | 28,000.00 | | 0028 | 704-10-00310 | Guard Rail End Treatment, NCHRP 350 - 31" (TL-3 Flared) | 1 | EACH | 3,600.00 | 3,600.00 | 3,500.00 | 3,500.00 | 4,010.00 | 4,010.00 | 3,500.00 | 3,500.00 | | 0029 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 130,000.00 | 130,000.00 | 200,000.00 | 200,000.00 | 160,000.00 | 160,000.00 | 450,000.00 | 450,000.00 | | 0030 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 8.808 | MILE | 320.00 | 2,818.56 | 320.00 | 2,818.56 | 350.00 | 3,082.80 | 400.00 | 3,523.20 | | 0031 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 3.844 | MILE | 500.00 | 1,922.00 | 500.00 | 1,922.00 | 1,000.00 | 3,844.00 | 1,000.00 | 3,844.00 | | 0032 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 9.368 | MILE | 900.00 | 8,431.20 | 900.00 | 8,431.20 | 1,750.00 | 16,394.00 | 1,800.00 | 16,862.40 | | 0033 | 724-02-00100 | Rumble Strips (Shoulder/Edge) | 8.778 | MILE | 300.00 | 2,633.40 | 270.00 | 2,370.06 | 675.00 | 5,925.15 | 270.00 | 2,370.06 | | 0034 | 726-01-00100 | Bedding Material | 127.5 | CUYD | 160.00 | 20,400.00 | 80.00 | 10,200.00 | 240.00 | 30,600.00 | 100.00 | 12,750.00 | | 0035 | 727-01-00100 | Mobilization | 1 | LUMP | 185,000.00 | 185,000.00 | 200,000.00 | 200,000.00 | 216,000.00 | 216,000.00 | 220,000.00 | 220,000.00 | | 0036 | 729-16-00200 | Object Marker Assembly (Type 2) | 62 | EACH | 60.00 | 3,720.00 | 60.00 | 3,720.00 | 65.00 | 4,030.00 | 60.00 | 3,720.00 | | 0037 | 729-16-00300 | Object Marker Assembly (Type 3) | 8 | EACH | 100.00 | 800.00 | 10.00 | 80.00 | 105.00 | 840.00 | 100.00 | 800.00 | | 0038 | 731-02-00100 | Reflectorized Raised Pavement Markers | 968 | EACH | 6.00 | 5,808.00 | 5.00 | 4,840.00 | 12.00 | 11,616.00 | 10.00 | 9,680.00 | | 0039 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 16.225 | MILE | 5,100.00 | 82,747.50 | 4,800.00 | 77,880.00 | 6,635.00 | 107,652.88 | 5,500.00 | 89,237.50 | | 0040 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 6.203 | MILE | 990.00 | 6,140.97 | 1,000.00 | 6,203.00 | 1,805.00 | 11,196.42 | 1,500.00 | 9,304.50 | | 0041 | 732-05-00100 | Removal of Existing Markings | 2.359 | MILE | 3,850.00 | 9,082.15 | 3,500.00 | 8,256.50 | 12,000.00 | 28,308.00 | 10,000.00 | 23,590.00 | | 0042 | 739-01-00100 | Hydro-Seeding | 2.133 | ACRE | 2,200.00 | 4,692.60 | 2,900.00 | 6,185.70 | 2,000.00 | 4,266.00 | 3,000.00 | 6,399.00 | | 0043 | 740-01-00100 | Construction Layout | 1 | LUMP | 10,000.00 | 10,000.00 | 80,000.00 | 80,000.00 | 30,000.00 | 30,000.00 | 125,000.00 | 125,000.00 | | 0044 | NS-500-00300 | Traffic Maintenance Asphalt Concrete | 49.3 | TON | 250.00 | 12,325.00 | 1.00 | 49.30 | 280.00 | 13,804.00 | 335.00 | 16,515.50 | | 0045 | NS-500-00340 | Saw Cutting Asphalt Concrete Pavement | 88 | INLF | 1.00 | 88.00 | 50.00 | 4,400.00 | 0.75 | 66.00 | 4.00 | 352.00 | | 0046 | NS-509-00001 | Micro-Milling Asphaltic Pavement | 56,162 | SQYD | 2.10 | 117,940.20 | 2.70 | 151,637.40 | 1.15 | 64,586.30 | 1.50 | 84,243.00 | | | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 1,914,596.98 | | 2,058,583.44 | | 2,162,078.47 | | 2,279,610.28 |
|