Proposal:H.013239.6-R1
Parish:St. John the Baptist
Routes:US 61
Description:HIGHWAY 61 STREETSCAPE IMPROVEMENTS
Type Construction:CLEARING AND GRUBBING, GRADING, DRAINAGE STRUCTURES, SIDEWALKS, CONCRETE AND ASPHALT DRIVES, LANDSCAPING, CABLED ARTICULATED CONCRETE BLOCK MATTRESS, SEWER AND WATER LINE RELOCATION, AND RELATED WORK.
Estimated Construction Cost:$3,325,312.26
| Rank | License | Bidder | Construction Bid |
| 1 | 48896 | Command Construction Industries LLC | $4,290,130.00 |
| 2 | 34263 | La Contracting Enterprise LLC | $4,482,344.25 |
| 3 | 12198 | Byron E. Talbot Contractor, Inc. | $4,638,734.50 |
| 4 | 35678 | BEVERLY CONSTRUCTION CO. LLC | $5,241,537.50 |
| 5 | 69770 | Omega Foundation Services | $5,458,902.00 |
| 6 | 14914 | Kass Bros. Inc. | $5,557,736.00 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Command Construction Industries LLC | - 2 - La Contracting Enterprise LLC | - 3 - Byron E. Talbot Contractor, Inc. | - 4 - BEVERLY CONSTRUCTION CO. LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 201-01-00100 | Clearing and Grubbing | 1.18 | LUMP | 50,000.00 | 50,000.00 | 20,000.00 | 20,000.00 | 25,000.00 | 25,000.00 | 60,000.00 | 60,000.00 | | 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 50,000.00 | 50,000.00 | 70,000.00 | 70,000.00 | 25,000.00 | 25,000.00 | 65,000.00 | 65,000.00 | | 0003 | 202-02-02000 | Removal of Asphalt Drives | 499 | SQYD | 25.00 | 12,475.00 | 34.00 | 16,966.00 | 25.00 | 12,475.00 | 24.00 | 11,976.00 | | 0004 | 202-02-06100 | Removal of Concrete Walks and Drives | 1,706 | SQYD | 25.00 | 42,650.00 | 34.00 | 58,004.00 | 25.00 | 42,650.00 | 24.00 | 40,944.00 | | 0005 | 202-02-06102 | Removal of Incidental Concrete Paving | 55 | SQYD | 5.00 | 275.00 | 40.00 | 2,200.00 | 25.00 | 1,375.00 | 24.00 | 1,320.00 | | 0006 | 203-02-00100 | Drainage Excavation | 883 | CUYD | 50.00 | 44,150.00 | 8.00 | 7,064.00 | 25.00 | 22,075.00 | 37.00 | 32,671.00 | | 0007 | 203-04-00200 | Nonplastic Embankment (Sand) | 542 | CUYD | 65.00 | 35,230.00 | 75.00 | 40,650.00 | 50.00 | 27,100.00 | 56.00 | 30,352.00 | | 0008 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 20,000.00 | 20,000.00 | 100,000.00 | 100,000.00 | 50,000.00 | 50,000.00 | 325,000.00 | 325,000.00 | | 0009 | 203-08-00100 | Geotextile Fabric | 30 | SQYD | 5.00 | 150.00 | 15.00 | 450.00 | 7.00 | 210.00 | 9.00 | 270.00 | | 0010 | 204-02-00100 | Temporary Hay Bales | 198 | EACH | 5.00 | 990.00 | 25.00 | 4,950.00 | 30.00 | 5,940.00 | 21.00 | 4,158.00 | | 0011 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 297.7 | CUYD | 150.00 | 44,655.00 | 160.00 | 47,632.00 | 100.00 | 29,770.00 | 100.00 | 29,770.00 | | 0012 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 165 | TON | 500.00 | 82,500.00 | 350.00 | 57,750.00 | 400.00 | 66,000.00 | 315.00 | 51,975.00 | | 0013 | 602-05-02200 | Full Depth Patching of Jointed Concrete Pavement (16.1 square yards to 48.0 square yards) (10" Thick) | 48.2 | SQYD | 450.00 | 21,690.00 | 300.00 | 14,460.00 | 250.00 | 12,050.00 | 500.00 | 24,100.00 | | 0014 | 701-03-01022 | Storm Drain Pipe (18" RCP/RPVCP) | 183 | LNFT | 200.00 | 36,600.00 | 90.00 | 16,470.00 | 150.00 | 27,450.00 | 125.00 | 22,875.00 | | 0015 | 701-03-01042 | Storm Drain Pipe (24" RCP/RPVCP) | 688 | LNFT | 250.00 | 172,000.00 | 108.00 | 74,304.00 | 170.00 | 116,960.00 | 155.00 | 106,640.00 | | 0016 | 701-03-01062 | Storm Drain Pipe (30" RCP/RPVCP) | 401 | LNFT | 300.00 | 120,300.00 | 142.00 | 56,942.00 | 225.00 | 90,225.00 | 185.00 | 74,185.00 | | 0017 | 701-03-01082 | Storm Drain Pipe (36" RCP/RPVCP) | 2,664 | LNFT | 330.00 | 879,120.00 | 185.00 | 492,840.00 | 275.00 | 732,600.00 | 215.00 | 572,760.00 | | 0018 | 701-12-01060 | Corrugated Metal Pipe (Extension) (24") | 5 | LNFT | 250.00 | 1,250.00 | 400.00 | 2,000.00 | 500.00 | 2,500.00 | 700.00 | 3,500.00 | | 0019 | 701-15-00100 | Concrete Collar | 1 | EACH | 1,500.00 | 1,500.00 | 3,000.00 | 3,000.00 | 2,500.00 | 2,500.00 | 7,000.00 | 7,000.00 | | 0020 | 702-02-00100 | Manholes (MH-06) | 5 | EACH | 10,000.00 | 50,000.00 | 7,300.00 | 36,500.00 | 6,000.00 | 30,000.00 | 7,000.00 | 35,000.00 | | 0021 | 702-03-00100 | Catch Basins (CB-01) | 15 | EACH | 7,500.00 | 112,500.00 | 5,800.00 | 87,000.00 | 5,200.00 | 78,000.00 | 5,000.00 | 75,000.00 | | 0022 | 702-03-01100 | Catch Basins (CB-SD02) | 18 | EACH | 7,500.00 | 135,000.00 | 11,100.00 | 199,800.00 | 8,200.00 | 147,600.00 | 7,500.00 | 135,000.00 | | 0023 | 706-01-00100 | Concrete Walk (4" Thick) | 943.5 | SQYD | 125.00 | 117,937.50 | 95.00 | 89,632.50 | 92.00 | 86,802.00 | 61.00 | 57,553.50 | | 0024 | 706-02-00200 | Concrete Drive (6" Thick) | 1,744 | SQYD | 150.00 | 261,600.00 | 100.00 | 174,400.00 | 125.00 | 218,000.00 | 71.00 | 123,824.00 | | 0025 | 706-03-00300 | Incidental Concrete Paving (6" Thick) | 1,625.7 | SQYD | 100.00 | 162,570.00 | 98.00 | 159,318.60 | 100.00 | 162,570.00 | 75.00 | 121,927.50 | | 0026 | 706-04-00110 | Curb Ramps Type 3 | 56.7 | SQYD | 250.00 | 14,175.00 | 220.00 | 12,474.00 | 385.00 | 21,829.50 | 225.00 | 12,757.50 | | 0027 | 707-01-00100 | Concrete Curb | 658.5 | LNFT | 25.00 | 16,462.50 | 25.00 | 16,462.50 | 39.00 | 25,681.50 | 25.00 | 16,462.50 | | 0028 | 712-05-00100 | Cabled Articulated Concrete Block Mattress | 595 | SQYD | 100.00 | 59,500.00 | 50.00 | 29,750.00 | 95.00 | 56,525.00 | 90.00 | 53,550.00 | | 0029 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 50,000.00 | 50,000.00 | 60,000.00 | 60,000.00 | 65,000.00 | 65,000.00 | 75,000.00 | 75,000.00 | | 0030 | 715-01-00100 | Topsoil | 10 | CUYD | 50.00 | 500.00 | 175.00 | 1,750.00 | 100.00 | 1,000.00 | 225.00 | 2,250.00 | | 0031 | 719-01-01100 | Plants (Tree) (Balled and Burlapped) (3-1/2 inch cal) Autumn Gold Cypress) | 77 | EACH | 800.00 | 61,600.00 | 770.00 | 59,290.00 | 1,150.00 | 88,550.00 | 1,300.00 | 100,100.00 | | 0032 | 719-01-02060 | Plants (Tree) (Container) (2-1/2 inch cal) Teddy Bear Magnolia) | 53 | EACH | 500.00 | 26,500.00 | 715.00 | 37,895.00 | 515.00 | 27,295.00 | 700.00 | 37,100.00 | | 0033 | 719-01-06020 | Plants (Plant) (Container) (1 gallon) Liatris | 12 | EACH | 15.00 | 180.00 | 19.25 | 231.00 | 18.50 | 222.00 | 19.00 | 228.00 | | 0034 | 719-01-06020 | Plants (Plant) (Container) (1 gallon) Louisiana Iris | 2,578 | EACH | 15.00 | 38,670.00 | 13.50 | 34,803.00 | 11.00 | 28,358.00 | 19.00 | 48,982.00 | | 0035 | 719-01-06060 | Plants (Plant) (Container) (3 gallon) Blond Ambition Gamma Grass) | 71 | EACH | 30.00 | 2,130.00 | 34.65 | 2,460.15 | 22.50 | 1,597.50 | 37.00 | 2,627.00 | | 0036 | 719-01-06060 | Plants (Plant) (Container) (3 gallon) Blue Arrow Juncus) | 291 | EACH | 30.00 | 8,730.00 | 35.00 | 10,185.00 | 34.00 | 9,894.00 | 37.00 | 10,767.00 | | 0037 | 719-01-06060 | Plants (Plant) (Container) (3 gallon) Dwarf Burford Holly | 74 | EACH | 15.00 | 1,110.00 | 33.00 | 2,442.00 | 25.00 | 1,850.00 | 37.00 | 2,738.00 | | 0038 | 719-01-06060 | Plants (Plant) (Container) (3 gallon) Dwarf Pittosporum) | 414 | EACH | 20.00 | 8,280.00 | 34.50 | 14,283.00 | 25.00 | 10,350.00 | 37.00 | 15,318.00 | | 0039 | 719-01-06060 | Plants (Plant) (Container) (3 gallon) Indian Hawthorn | 154 | EACH | 20.00 | 3,080.00 | 35.00 | 5,390.00 | 24.00 | 3,696.00 | 35.00 | 5,390.00 | | 0040 | 719-01-06060 | Plants (Plant) (Container) (3 gallon) Lomandra Breeze | 203 | EACH | 25.00 | 5,075.00 | 32.00 | 6,496.00 | 24.00 | 4,872.00 | 35.00 | 7,105.00 | | 0041 | 719-01-06060 | Plants (Plant) (Container) (3 gallon) Parsons Juniper) | 334 | EACH | 20.00 | 6,680.00 | 32.00 | 10,688.00 | 25.00 | 8,350.00 | 35.00 | 11,690.00 | | 0042 | 719-01-06060 | Plants (Plant) (Container) (3 gallon) Pink Muhly Grass | 245 | EACH | 20.00 | 4,900.00 | 33.00 | 8,085.00 | 25.00 | 6,125.00 | 32.00 | 7,840.00 | | 0043 | 719-01-06060 | Plants (Plant) (Container) (3 gallon) White Cloud Muhly | 248 | EACH | 20.00 | 4,960.00 | 36.00 | 8,928.00 | 33.00 | 8,184.00 | 35.00 | 8,680.00 | | 0044 | 719-02-00100 | Top Dressing Mulch (3" Depth) | 2,207 | SQYD | 15.00 | 33,105.00 | 15.00 | 33,105.00 | 5.50 | 12,138.50 | 135.00 | 297,945.00 | | 0045 | 719-03-00400 | Bed Preparation ( ____" Depth) 12 | 1,610 | SQYD | 50.00 | 80,500.00 | 11.00 | 17,710.00 | 26.75 | 43,067.50 | 46.00 | 74,060.00 | | 0046 | 719-03-00400 | Bed Preparation ( ____" Depth) 8 | 308 | SQYD | 40.00 | 12,320.00 | 11.00 | 3,388.00 | 20.00 | 6,160.00 | 46.00 | 14,168.00 | | 0047 | 726-01-00100 | Bedding Material | 463.7 | CUYD | 100.00 | 46,370.00 | 150.00 | 69,555.00 | 135.00 | 62,599.50 | 115.00 | 53,325.50 | | 0048 | 727-01-00100 | Mobilization | 1 | LUMP | 300,000.00 | 300,000.00 | 400,000.00 | 400,000.00 | 250,000.00 | 250,000.00 | 465,000.00 | 465,000.00 | | 0049 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 22 | LNFT | 100.00 | 2,200.00 | 110.00 | 2,420.00 | 55.00 | 1,210.00 | 105.00 | 2,310.00 | | 0050 | 732-05-00100 | Removal of Existing Markings | 0.013 | MILE | 50,000.00 | 650.00 | 55,000.00 | 715.00 | 110,000.00 | 1,430.00 | 40,000.00 | 520.00 | | 0051 | 740-01-00100 | Construction Layout | 1 | LUMP | 50,000.00 | 50,000.00 | 30,000.00 | 30,000.00 | 31,000.00 | 31,000.00 | 50,000.00 | 50,000.00 | | 0052 | 740-02-00100 | Utility Oversight and Coordination | 1 | LUMP | 1,000.00 | 1,000.00 | 800.00 | 800.00 | 12,500.00 | 12,500.00 | 20,000.00 | 20,000.00 | | 0053 | 741-20-01120 | Water Main (10" PVC) | 1,010 | LNFT | 175.00 | 176,750.00 | 200.00 | 202,000.00 | 175.00 | 176,750.00 | 155.00 | 156,550.00 | | 0054 | 741-22-00500 | Tapping Sleeve and Valve (10") | 8 | EACH | 10,000.00 | 80,000.00 | 14,000.00 | 112,000.00 | 10,500.00 | 84,000.00 | 11,500.00 | 92,000.00 | | 0055 | 741-23-01120 | Insertion Valve (10") | 8 | EACH | 7,500.00 | 60,000.00 | 24,000.00 | 192,000.00 | 25,000.00 | 200,000.00 | 21,000.00 | 168,000.00 | | 0056 | 741-33-00100 | Adjust Service Connection (20’ or less) | 15 | EACH | 500.00 | 7,500.00 | 1,700.00 | 25,500.00 | 1,500.00 | 22,500.00 | 2,000.00 | 30,000.00 | | 0057 | 742-02-00200 | Sanitary Sewer Force Main Pipe 20" PVC | 375 | LNFT | 500.00 | 187,500.00 | 650.00 | 243,750.00 | 600.00 | 225,000.00 | 650.00 | 243,750.00 | | 0058 | NS-201-00001 | Tree and Stump Removal (<= 36" Diameter) | 4 | EACH | 5,000.00 | 20,000.00 | 1,200.00 | 4,800.00 | 1,850.00 | 7,400.00 | 4,000.00 | 16,000.00 | | 0059 | NS-719-00001 | Tree Protection Fencing | 1 | LUMP | 5,000.00 | 5,000.00 | 3,000.00 | 3,000.00 | 9,000.00 | 9,000.00 | 12,500.00 | 12,500.00 | | 0060 | NS-719-00002 | Tree Trimming | 1 | LUMP | 5,000.00 | 5,000.00 | 3,000.00 | 3,000.00 | 4,500.00 | 4,500.00 | 11,000.00 | 11,000.00 | | 0061 | NS-719-00005 | Gravel Bed and Filter Cloth over Tree Roots | 13 | SQYD | 50.00 | 650.00 | 50.00 | 650.00 | 1.50 | 19.50 | 180.00 | 2,340.00 | | 0062 | TS-714-00100 | Slab Sodding (Empire Zoysia) | 8,991 | SQYD | 10.00 | 89,910.00 | 10.50 | 94,405.50 | 8.00 | 71,928.00 | 13.00 | 116,883.00 | | 0063 | TS-726-37003 | Round River Rock (3" to 8") | 4 | CUYD | 1,000.00 | 4,000.00 | 400.00 | 1,600.00 | 325.00 | 1,300.00 | 1,150.00 | 4,600.00 | | 0064 | TS-741-10042 | Plug and Abandon Water Main | 16 | EACH | 2,000.00 | 32,000.00 | 2,000.00 | 32,000.00 | 1,750.00 | 28,000.00 | 1,100.00 | 17,600.00 | | 0065 | TS-741-23020 | Insertion Valve (20”) | 8 | EACH | 15,000.00 | 120,000.00 | 50,000.00 | 400,000.00 | 72,500.00 | 580,000.00 | 55,000.00 | 440,000.00 | | 0066 | TS-741-60029 | Tapping Sleeve, Valve and Box 20" | 8 | EACH | 25,000.00 | 200,000.00 | 50,000.00 | 400,000.00 | 46,000.00 | 368,000.00 | 57,000.00 | 456,000.00 | | 0067 | TS-742-00005 | Plug and Abandon Sewer Force Main | 16 | EACH | 500.00 | 8,000.00 | 3,500.00 | 56,000.00 | 3,500.00 | 56,000.00 | 4,100.00 | 65,600.00 | | | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 4,290,130.00 | | 4,482,344.25 | | 4,638,734.50 | | 5,241,537.50 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 5 - Omega Foundation Services | - 6 - Kass Bros. Inc. | | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 201-01-00100 | Clearing and Grubbing | 1.18 | LUMP | 10,000.00 | 10,000.00 | 15,000.00 | 15,000.00 | | 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 25,000.00 | 25,000.00 | 60,000.00 | 60,000.00 | | 0003 | 202-02-02000 | Removal of Asphalt Drives | 499 | SQYD | 23.00 | 11,477.00 | 35.00 | 17,465.00 | | 0004 | 202-02-06100 | Removal of Concrete Walks and Drives | 1,706 | SQYD | 32.00 | 54,592.00 | 35.00 | 59,710.00 | | 0005 | 202-02-06102 | Removal of Incidental Concrete Paving | 55 | SQYD | 25.00 | 1,375.00 | 35.00 | 1,925.00 | | 0006 | 203-02-00100 | Drainage Excavation | 883 | CUYD | 25.00 | 22,075.00 | 35.00 | 30,905.00 | | 0007 | 203-04-00200 | Nonplastic Embankment (Sand) | 542 | CUYD | 50.00 | 27,100.00 | 65.00 | 35,230.00 | | 0008 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 55,000.00 | 55,000.00 | 150,000.00 | 150,000.00 | | 0009 | 203-08-00100 | Geotextile Fabric | 30 | SQYD | 7.00 | 210.00 | 2.00 | 60.00 | | 0010 | 204-02-00100 | Temporary Hay Bales | 198 | EACH | 30.00 | 5,940.00 | 30.00 | 5,940.00 | | 0011 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 297.7 | CUYD | 100.00 | 29,770.00 | 125.00 | 37,212.50 | | 0012 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 165 | TON | 560.00 | 92,400.00 | 500.00 | 82,500.00 | | 0013 | 602-05-02200 | Full Depth Patching of Jointed Concrete Pavement (16.1 square yards to 48.0 square yards) (10" Thick) | 48.2 | SQYD | 435.00 | 20,967.00 | 600.00 | 28,920.00 | | 0014 | 701-03-01022 | Storm Drain Pipe (18" RCP/RPVCP) | 183 | LNFT | 160.00 | 29,280.00 | 130.00 | 23,790.00 | | 0015 | 701-03-01042 | Storm Drain Pipe (24" RCP/RPVCP) | 688 | LNFT | 180.00 | 123,840.00 | 190.00 | 130,720.00 | | 0016 | 701-03-01062 | Storm Drain Pipe (30" RCP/RPVCP) | 401 | LNFT | 225.00 | 90,225.00 | 220.00 | 88,220.00 | | 0017 | 701-03-01082 | Storm Drain Pipe (36" RCP/RPVCP) | 2,664 | LNFT | 270.00 | 719,280.00 | 225.00 | 599,400.00 | | 0018 | 701-12-01060 | Corrugated Metal Pipe (Extension) (24") | 5 | LNFT | 370.00 | 1,850.00 | 800.00 | 4,000.00 | | 0019 | 701-15-00100 | Concrete Collar | 1 | EACH | 3,000.00 | 3,000.00 | 2,800.00 | 2,800.00 | | 0020 | 702-02-00100 | Manholes (MH-06) | 5 | EACH | 14,000.00 | 70,000.00 | 10,000.00 | 50,000.00 | | 0021 | 702-03-00100 | Catch Basins (CB-01) | 15 | EACH | 8,500.00 | 127,500.00 | 9,000.00 | 135,000.00 | | 0022 | 702-03-01100 | Catch Basins (CB-SD02) | 18 | EACH | 11,500.00 | 207,000.00 | 12,000.00 | 216,000.00 | | 0023 | 706-01-00100 | Concrete Walk (4" Thick) | 943.5 | SQYD | 92.00 | 86,802.00 | 115.00 | 108,502.50 | | 0024 | 706-02-00200 | Concrete Drive (6" Thick) | 1,744 | SQYD | 110.00 | 191,840.00 | 140.00 | 244,160.00 | | 0025 | 706-03-00300 | Incidental Concrete Paving (6" Thick) | 1,625.7 | SQYD | 110.00 | 178,827.00 | 100.00 | 162,570.00 | | 0026 | 706-04-00110 | Curb Ramps Type 3 | 56.7 | SQYD | 300.00 | 17,010.00 | 325.00 | 18,427.50 | | 0027 | 707-01-00100 | Concrete Curb | 658.5 | LNFT | 50.00 | 32,925.00 | 80.00 | 52,680.00 | | 0028 | 712-05-00100 | Cabled Articulated Concrete Block Mattress | 595 | SQYD | 70.00 | 41,650.00 | 170.00 | 101,150.00 | | 0029 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 80,000.00 | 80,000.00 | 200,000.00 | 200,000.00 | | 0030 | 715-01-00100 | Topsoil | 10 | CUYD | 215.00 | 2,150.00 | 150.00 | 1,500.00 | | 0031 | 719-01-01100 | Plants (Tree) (Balled and Burlapped) (3-1/2 inch cal) Autumn Gold Cypress) | 77 | EACH | 1,500.00 | 115,500.00 | 1,200.00 | 92,400.00 | | 0032 | 719-01-02060 | Plants (Tree) (Container) (2-1/2 inch cal) Teddy Bear Magnolia) | 53 | EACH | 1,200.00 | 63,600.00 | 650.00 | 34,450.00 | | 0033 | 719-01-06020 | Plants (Plant) (Container) (1 gallon) Liatris | 12 | EACH | 20.00 | 240.00 | 15.00 | 180.00 | | 0034 | 719-01-06020 | Plants (Plant) (Container) (1 gallon) Louisiana Iris | 2,578 | EACH | 20.00 | 51,560.00 | 15.00 | 38,670.00 | | 0035 | 719-01-06060 | Plants (Plant) (Container) (3 gallon) Blond Ambition Gamma Grass) | 71 | EACH | 50.00 | 3,550.00 | 30.00 | 2,130.00 | | 0036 | 719-01-06060 | Plants (Plant) (Container) (3 gallon) Blue Arrow Juncus) | 291 | EACH | 50.00 | 14,550.00 | 30.00 | 8,730.00 | | 0037 | 719-01-06060 | Plants (Plant) (Container) (3 gallon) Dwarf Burford Holly | 74 | EACH | 50.00 | 3,700.00 | 30.00 | 2,220.00 | | 0038 | 719-01-06060 | Plants (Plant) (Container) (3 gallon) Dwarf Pittosporum) | 414 | EACH | 50.00 | 20,700.00 | 30.00 | 12,420.00 | | 0039 | 719-01-06060 | Plants (Plant) (Container) (3 gallon) Indian Hawthorn | 154 | EACH | 50.00 | 7,700.00 | 30.00 | 4,620.00 | | 0040 | 719-01-06060 | Plants (Plant) (Container) (3 gallon) Lomandra Breeze | 203 | EACH | 50.00 | 10,150.00 | 30.00 | 6,090.00 | | 0041 | 719-01-06060 | Plants (Plant) (Container) (3 gallon) Parsons Juniper) | 334 | EACH | 50.00 | 16,700.00 | 30.00 | 10,020.00 | | 0042 | 719-01-06060 | Plants (Plant) (Container) (3 gallon) Pink Muhly Grass | 245 | EACH | 50.00 | 12,250.00 | 30.00 | 7,350.00 | | 0043 | 719-01-06060 | Plants (Plant) (Container) (3 gallon) White Cloud Muhly | 248 | EACH | 50.00 | 12,400.00 | 30.00 | 7,440.00 | | 0044 | 719-02-00100 | Top Dressing Mulch (3" Depth) | 2,207 | SQYD | 20.00 | 44,140.00 | 130.00 | 286,910.00 | | 0045 | 719-03-00400 | Bed Preparation ( ____" Depth) 12 | 1,610 | SQYD | 25.00 | 40,250.00 | 50.00 | 80,500.00 | | 0046 | 719-03-00400 | Bed Preparation ( ____" Depth) 8 | 308 | SQYD | 25.00 | 7,700.00 | 45.00 | 13,860.00 | | 0047 | 726-01-00100 | Bedding Material | 463.7 | CUYD | 140.00 | 64,918.00 | 120.00 | 55,644.00 | | 0048 | 727-01-00100 | Mobilization | 1 | LUMP | 450,000.00 | 450,000.00 | 500,000.00 | 500,000.00 | | 0049 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 22 | LNFT | 145.00 | 3,190.00 | 120.00 | 2,640.00 | | 0050 | 732-05-00100 | Removal of Existing Markings | 0.013 | MILE | 145,000.00 | 1,885.00 | 60,000.00 | 780.00 | | 0051 | 740-01-00100 | Construction Layout | 1 | LUMP | 40,000.00 | 40,000.00 | 50,000.00 | 50,000.00 | | 0052 | 740-02-00100 | Utility Oversight and Coordination | 1 | LUMP | 30,000.00 | 30,000.00 | 3,000.00 | 3,000.00 | | 0053 | 741-20-01120 | Water Main (10" PVC) | 1,010 | LNFT | 300.00 | 303,000.00 | 205.00 | 207,050.00 | | 0054 | 741-22-00500 | Tapping Sleeve and Valve (10") | 8 | EACH | 30,000.00 | 240,000.00 | 15,000.00 | 120,000.00 | | 0055 | 741-23-01120 | Insertion Valve (10") | 8 | EACH | 30,000.00 | 240,000.00 | 15,000.00 | 120,000.00 | | 0056 | 741-33-00100 | Adjust Service Connection (20’ or less) | 15 | EACH | 4,000.00 | 60,000.00 | 2,200.00 | 33,000.00 | | 0057 | 742-02-00200 | Sanitary Sewer Force Main Pipe 20" PVC | 375 | LNFT | 400.00 | 150,000.00 | 600.00 | 225,000.00 | | 0058 | NS-201-00001 | Tree and Stump Removal (<= 36" Diameter) | 4 | EACH | 2,500.00 | 10,000.00 | 3,000.00 | 12,000.00 | | 0059 | NS-719-00001 | Tree Protection Fencing | 1 | LUMP | 16,000.00 | 16,000.00 | 10,000.00 | 10,000.00 | | 0060 | NS-719-00002 | Tree Trimming | 1 | LUMP | 11,000.00 | 11,000.00 | 3,500.00 | 3,500.00 | | 0061 | NS-719-00005 | Gravel Bed and Filter Cloth over Tree Roots | 13 | SQYD | 17.00 | 221.00 | 316.00 | 4,108.00 | | 0062 | TS-714-00100 | Slab Sodding (Empire Zoysia) | 8,991 | SQYD | 23.00 | 206,793.00 | 11.50 | 103,396.50 | | 0063 | TS-726-37003 | Round River Rock (3" to 8") | 4 | CUYD | 430.00 | 1,720.00 | 960.00 | 3,840.00 | | 0064 | TS-741-10042 | Plug and Abandon Water Main | 16 | EACH | 1,200.00 | 19,200.00 | 3,000.00 | 48,000.00 | | 0065 | TS-741-23020 | Insertion Valve (20”) | 8 | EACH | 86,000.00 | 688,000.00 | 50,000.00 | 400,000.00 | | 0066 | TS-741-60029 | Tapping Sleeve, Valve and Box 20" | 8 | EACH | 15,000.00 | 120,000.00 | 42,000.00 | 336,000.00 | | 0067 | TS-742-00005 | Plug and Abandon Sewer Force Main | 16 | EACH | 1,200.00 | 19,200.00 | 3,000.00 | 48,000.00 | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 5,458,902.00 | | 5,557,736.00 |
|