Search


Bid Tabulations for the Letting of 5/8/2024 LA DOTD Headquarters

Proposal:H.002264.6
Parish:Jefferson
Routes:LA 302, LA 3257, LA 45
Description:LA 302: BAYOU BARATARIA MB REPL PHASE 2
Type Construction:CLEARING AND GRUBBING, GRADING, DRAINAGE STRUCTURES, MILLING ASPHALT CONCRETE, PAVEMENT PATCHING, CLASS II BASE COURSE, ASPHALT CONCRETE PAVEMENT, PAVEMENT WIDENING, AND RELATED WORK.
Estimated Construction Cost:$10,893,985.85
Rank License BidderConstruction Bid
106276Barriere Construction Co., LLC$7,869,881.09
236961Cycle Construction Co. L.L.C.$10,064,567.59
355950Brown Industrial Construction, LLC$10,257,122.07
402179Boh Bros. Construction Co., LLC.$12,967,860.99


Line
Number
Item NumberItem DescriptionQuantityUnit of
Measure
- 1 -
Barriere Construction Co., LLC
- 2 -
Cycle Construction Co. L.L.C.
- 3 -
Brown Industrial Construction, LLC
- 4 -
Boh Bros. Construction Co., LLC.
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001201-01-00100Clearing and Grubbing 3.44  LUMP150,000.00150,000.00165,000.00165,000.001,278,000.001,278,000.00285,000.00285,000.00
0002202-01-00100Removal of Structures and Obstructions 1     LUMP200.00200.0070,000.0070,000.005,000.005,000.009,250.009,250.00
0003202-02-00010Removal of Temporary 4" Concrete Slab4     EACH750.003,000.00785.003,140.001,500.006,000.00500.002,000.00
0004202-02-02000Removal of Asphalt Drives 144     SQYD20.002,880.0080.0011,520.0055.007,920.0030.004,320.00
0005202-02-02020Removal of Asphalt Pavement 5,316.2   SQYD9.0047,845.8011.0058,478.2012.0063,794.409.0047,845.80
0006202-02-03000Removal of Base – Soil Cement, Asphalt, or BCS 5,316.2   SQYD2.0010,632.4013.0069,110.6012.2064,857.647.0037,213.40
0007202-02-06020Removal of Concrete Box Culverts (8' x 3' x 30')1     EACH5,000.005,000.0012,000.0012,000.004,090.004,090.008,500.008,500.00
0008202-02-06040Removal of Concrete Box Headwall (Sta. 207+25)2     EACH5,000.0010,000.002,000.004,000.001,760.003,520.004,000.008,000.00
0009202-02-32120Removal of Pipe (Side Drain) (According to Removal of Drainage Table)181     LNFT20.003,620.00106.0019,186.0023.504,253.5050.009,050.00
0010202-02-32140Removal of Pipe (Storm Drain) (According to Removal of Drainage Table)15     LNFT30.00450.00218.003,270.0038.00570.0075.001,125.00
0011203-01-00100General Excavation (Roadway and Muck)5,981     CUYD30.00179,430.0031.50188,401.5028.75171,953.7553.00316,993.00
0012203-03-00100Embankment 5,403     CUYD75.00405,225.0061.00329,583.0075.50407,926.50160.00864,480.00
0013203-04-00200Nonplastic Embankment (Sand) 19,002     CUYD40.00760,080.0034.00646,068.0060.001,140,120.0079.501,510,659.00
0014203-04-00200Nonplastic Embankment (Sand) (Surcharge)6,264     CUYD40.00250,560.0070.00438,480.0046.00288,144.0072.50454,140.00
0015203-08-00100Geotextile Fabric 20,765     SQYD3.0062,295.005.00103,825.002.0041,530.002.7557,103.75
0016203-11-00100Settlement Plate Installation and Monitoring 19     EACH4,000.0076,000.002,475.0047,025.003,378.0064,182.002,750.0052,250.00
0017204-02-00100Temporary Hay Bales 90     EACH25.002,250.0025.002,250.0062.005,580.0025.002,250.00
0018204-06-00100Temporary Silt Fencing 7,375     LNFT2.0014,750.004.0029,500.002.2516,593.754.0029,500.00
0019302-02-12070Class II Base Course (12" Thick) (Crushed Stone or Recycled Portland Cement Concrete) 10,082.7   SQYD50.00504,135.0052.50529,341.7537.60379,109.5276.50771,326.55
0020402-01-00101Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) 50     CUYD250.0012,500.00238.0011,900.00177.008,850.00290.0014,500.00
0021502-01-00100Asphalt Concrete 3,697.2   TON171.50634,069.80190.00702,468.00193.00713,559.60300.001,109,160.00
0022502-01-00200Asphalt Concrete, Drives, Turnouts and Miscellaneous 868.8   TON298.00258,902.40325.00282,360.00335.00291,048.00400.00347,520.00
0023509-01-00100Milling Asphalt Pavement 4,547     SQYD13.0059,111.0014.0063,658.0014.5065,931.5015.0068,205.00
0024509-02-00100Contractor Retained Reclaimed Asphalt Pavement -252.6   CUYD0.10-25.260.10-25.260.11-27.790.10-25.26
0025510-01-00102Pavement Patching (8" Minimum Thickness) 34.2   SQYD250.008,550.00260.008,892.00281.009,610.20600.0020,520.00
0026510-02-00100Pavement Widening (4" Thick)939     SQYD55.0051,645.0058.0054,462.0062.0058,218.00245.00230,055.00
0027510-02-00100Pavement Widening (8" Thick)305.1   SQYD96.0029,289.6098.0029,899.80108.0032,950.80440.00134,244.00
0028701-02-01000Cross Drain Pipe Arch (24" Equiv. RCPA) 272     LNFT225.0061,200.00210.0057,120.00163.0044,336.00375.00102,000.00
0029701-02-01020Cross Drain Pipe Arch (30" Equiv. RCPA) 152     LNFT250.0038,000.00310.0047,120.00186.0028,272.00450.0068,400.00
0030701-03-01042Storm Drain Pipe (24" RCP/RPVCP) 197     LNFT200.0039,400.00185.0036,445.00148.0029,156.00275.0054,175.00
0031701-04-01020Storm Drain Pipe Arch (18" Equiv. RCPA) 274     LNFT180.0049,320.00200.0054,800.00133.0036,442.00250.0068,500.00
0032701-05-01045Side Drain Pipe (18" RCP/RPVCP/CPEPDW) 112     LNFT150.0016,800.00170.0019,040.0097.0010,864.00225.0025,200.00
0033701-06-00020Side Drain Pipe Arch (18" Equiv. RCPA) 160     LNFT150.0024,000.00200.0032,000.00141.0022,560.00225.0036,000.00
0034701-07-00600Yard Drain Pipe (15") 200     LNFT60.0012,000.00140.0028,000.0099.0019,800.00190.0038,000.00
0035702-03-00100Catch Basins (CB-01) 1     EACH6,000.006,000.009,900.009,900.003,500.003,500.0012,000.0012,000.00
0036702-03-01000Catch Basins (CB-2TOP02) 1     EACH12,000.0012,000.0014,500.0014,500.0011,550.0011,550.0020,000.0020,000.00
0037704-03-00200Blocked Out Guard Rail - 31", (6'-3" Post Spacing) 50     LNFT36.001,800.0036.001,800.0033.001,650.0045.002,250.00
0038704-07-00200Guard Rail Transitions (Double Thrie Beam) 100     LNFT150.0015,000.00130.0013,000.00140.0014,000.00125.0012,500.00
0039704-10-00310Guard Rail End Treatment, NCHRP 350 - 31" (TL-3 Flared) 4     EACH3,600.0014,400.003,500.0014,000.003,378.0013,512.004,500.0018,000.00
0040706-01-00100Concrete Walk (4" Thick) 17.4   SQYD150.002,610.00350.006,090.00135.002,349.00500.008,700.00
0041708-01-00100Right-of-Way Monument 35     EACH350.0012,250.00695.0024,325.00675.0023,625.00650.0022,750.00
0042708-02-00100Right-of-Way Monument Witness Post 35     EACH350.0012,250.00230.008,050.00225.007,875.00200.007,000.00
0043713-01-00100Temporary Signs and Barricades 1     LUMP200,000.00200,000.00350,000.00350,000.00101,500.00101,500.00250,000.00250,000.00
0044713-03-01000Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) 0.259 MILE3,600.00932.406,000.001,554.003,391.00878.271,900.00492.10
0045713-03-02000Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) 0.341 MILE1,200.00409.201,100.00375.103,368.001,148.491,900.00647.90
0046713-04-01000Temporary Pavement Markings (Solid Line) (4" Width) 0.341 MILE3,000.001,023.002,800.00954.805,928.002,021.453,750.001,278.75
0047713-06-00100Temporary Reflectorized Raised Pavement Markers 45     EACH18.00810.0017.00765.0011.00495.0029.001,305.00
0048713-08-00100Temporary Precast Concrete Barrier (Department Furnished) 88     EACH750.0066,000.001,050.0092,400.00990.0087,120.00475.0041,800.00
0049716-01-00100Mulch (Vegetative) 16.3   TON800.0013,040.00925.0015,077.50957.0015,599.10950.0015,485.00
0050717-01-00100Seeding 279     LB35.009,765.0030.008,370.0033.009,207.0030.008,370.00
0051718-01-00100Fertilizer 9,305     LB1.5013,957.501.009,305.000.857,909.251.009,305.00
0052722-01-00100Project Site Laboratory 1     EACH100,000.00100,000.0060,000.0060,000.0069,700.0069,700.00115,000.00115,000.00
0053726-01-00100Bedding Material 105.1   CUYD140.0014,714.00120.0012,612.00144.0015,134.40200.0021,020.00
0054727-01-00100Mobilization 1     LUMP765,000.00765,000.001,650,000.001,650,000.001,021,000.001,021,000.00957,500.00957,500.00
0055729-01-00100Sign (Type A) 54     SQFT30.001,620.0028.001,512.0022.001,188.0037.001,998.00
0056729-02-00100Sign (Type B) 70     SQFT42.002,940.0028.001,960.0028.001,960.0037.002,590.00
0057729-16-00200Object Marker Assembly (Type 2) 6     EACH115.00690.00115.00690.0085.00510.00150.00900.00
0058729-16-00300Object Marker Assembly (Type 3) 4     EACH210.00840.00115.00460.00106.00424.00105.00420.00
0059729-22-00200Square Tubing Post with 2-1/4" Omni-Directional Anchor 22     EACH400.008,800.00220.004,840.00225.004,950.00225.004,950.00
0060731-02-00100Reflectorized Raised Pavement Markers 157     EACH12.001,884.0011.001,727.0011.201,758.4020.003,140.00
0061732-01-02080Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) 45     LNFT24.001,080.0023.001,035.0016.90760.5038.001,710.00
0062732-02-02000Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) 2.368 MILE7,800.0018,470.407,500.0017,760.005,950.0014,089.6012,750.0030,192.00
0063732-03-02000Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) 0.653 MILE2,400.001,567.202,300.001,501.903,363.002,196.043,750.002,448.75
0064735-01-00100Mailboxes 2     EACH100.00200.0023.0046.0056.00112.00100.00200.00
0065735-02-00100Mailbox Supports (Single) 2     EACH250.00500.00289.00578.00168.00336.00200.00400.00
0066740-01-00100Construction Layout 1     LUMP200,000.00200,000.00170,000.00170,000.00216,100.00216,100.00250,000.00250,000.00
0067802-03-00500Temporary Sheeting (PZ 35)37,000     SQFT40.001,480,000.0047.001,739,000.0050.001,850,000.0066.502,460,500.00
0068805-01-01000Class A1 Concrete (Headwalls) (3'-0" x 18'-11")3.93  CUYD7,500.0029,475.0014,000.0055,020.002,027.007,966.114,500.0017,685.00
0069805-01-01000Class A1 Concrete (Headwalls) (3'-5" x 22'-1")4.93  CUYD7,500.0036,975.0014,000.0069,020.002,027.009,993.114,750.0023,417.50
0070806-01-00100Deformed Reinforcing Steel 498     LB10.004,980.006.002,988.005.202,589.602.00996.00
0071807-01-00800Structural Metalwork (Bollards)1,075     LUMP15,000.0015,000.0010,000.0010,000.009,000.009,000.0012,500.0012,500.00
0072NS-203-00014Wick Drains 678,022     LNFT0.45305,109.900.45305,109.900.50339,011.000.70474,615.40
0073NS-300-00060Geogrid 10,082.7   SQYD5.0050,413.504.0040,330.801.9019,157.133.0030,248.10
0074NS-500-00240Sawing and Sealing Transverse Joints in Asphalt Concrete Overlay 216     LNFT20.004,320.0017.003,672.0011.252,430.0010.002,160.00
0075NS-500-00260Sawcuts in Asphalt Concrete Lifts 144     LNFT12.001,728.0012.001,728.009.001,296.0010.001,440.00
0076NS-500-00300Traffic Maintenance Asphalt Concrete 101     TON200.0020,200.00232.0023,432.00225.0022,725.00575.0058,075.00
0077NS-500-00340Saw Cutting Asphalt Concrete Pavement 20,415     INLF0.7515,311.251.0020,415.000.5511,228.250.7515,311.25
0078NS-700-00810Impact Attenuator (Construction Zone)(Test Level 3) 2     EACH10,000.0020,000.0011,000.0022,000.0012,100.0024,200.009,950.0019,900.00
0079TS-741-00100Fire Hydrant Assembly 5     EACH10,000.0050,000.0011,500.0057,500.0016,900.0084,500.0017,500.0087,500.00
0080TS-741-01100Water Main (8" PVC) (PVC/C-900 Pipe) 175     LNFT120.0021,000.00375.0065,625.00260.0045,500.00400.0070,000.00
0081TS-741-01120Water Main (14") (PVC/C-900 Pipe) 202     LNFT150.0030,300.00421.0085,042.00225.0045,450.00500.00101,000.00
0082TS-741-02090Water Main (14") (Ductile Iron Pipe) 50     LF250.0012,500.00625.0031,250.00305.0015,250.00570.0028,500.00
0083TS-741-02091Water Main (16") (HDPE Pipe SDR 17) 2,416     LF150.00362,400.00308.00744,128.00289.00698,224.00325.00785,200.00
0084TS-741-11201Ductile Iron Fittings 1,000     LB20.0020,000.0012.0012,000.0022.0022,000.0025.0025,000.00
0085TS-741-60058Gate Valve and Valve Box (8") 4     EACH2,500.0010,000.005,900.0023,600.003,941.0015,764.005,750.0023,000.00
0086TS-741-60059Butterfly Valve and Valve Box (14") 2     EACH6,500.0013,000.009,800.0019,600.009,234.0018,468.0025,000.0050,000.00
0087TS-741-70103Removal and Disposal of Existing AC Waterline (14")60     LNFT300.0018,000.00345.0020,700.00112.006,720.00200.0012,000.00
0088TS-741-70112Pipe Restraints (8") 12     EACH750.009,000.00550.006,600.00225.002,700.001,000.0012,000.00
0089TS-741-70115Pipe Restraints (14") 14     EACH1,250.0017,500.001,100.0015,400.00675.009,450.001,500.0021,000.00
0090TS-741-70122Transitional Coupling (8") 2     EACH3,500.007,000.001,900.003,800.00563.001,126.001,250.002,500.00
0091TS-741-70125Transitional Coupling (14") 2     EACH8,000.0016,000.004,350.008,700.002,250.004,500.003,750.007,500.00
0092TS-741-70126Transitional Couplings HDPE to PVC (16"x14") 4     EACH4,000.0016,000.006,100.0024,400.002,250.009,000.003,500.0014,000.00
             
  CONTRACTOR TOTAL   7,869,881.09 10,064,567.59 10,257,122.07 12,967,860.99