Proposal:H.011775.6
Parish:St. Tammany
Routes:US 11, US 190
Description:US 11 & US 190 BICYCLE & PED CROSSINGS
Type Construction:CLEARING AND GRUBBING, DRAINAGE STRUCTURES, MILLING ASPHALT CONCRETE, PAVEMENT PATCHING, CLASS II BASE COURSE, PORTLAND CEMENT CONCRETE PAVEMENT, ASPHALT CONCRETE OVERLAY, ASPHALT CONCRETE PAVEMENT AND RELATED WORK.
Estimated Construction Cost:$965,920.75
| Rank | License | Bidder | Construction Bid |
| 1 | 49356 | KORT's CONSTRUCTION SERVICES, INC. | $1,238,409.40 |
| 2 | 68424 | Procivil, LLC | $1,285,075.00 |
| 3 | 34263 | La Contracting Enterprise LLC | $1,313,000.00 |
| 4 | 68237 | GULF STATES SERVICES, LLC | $1,358,186.00 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - KORT's CONSTRUCTION SERVICES, INC. | - 2 - Procivil, LLC | - 3 - La Contracting Enterprise LLC | - 4 - GULF STATES SERVICES, LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 201-01-00100 | Clearing and Grubbing | 3 | LUMP | 5,000.00 | 5,000.00 | 5,000.00 | 5,000.00 | 10,000.00 | 10,000.00 | 1,000.00 | 1,000.00 | | 0002 | 202-02-03030 | Removal of Pavement Structure | 655 | SQYD | 20.00 | 13,100.00 | 35.00 | 22,925.00 | 38.00 | 24,890.00 | 50.00 | 32,750.00 | | 0003 | 202-02-06080 | Removal of Concrete Combination Curb and Gutter | 95.9 | LNFT | 10.00 | 959.00 | 5.00 | 479.50 | 30.00 | 2,877.00 | 50.00 | 4,795.00 | | 0004 | 202-02-06100 | Removal of Concrete Walks and Drives | 395 | SQYD | 15.00 | 5,925.00 | 35.00 | 13,825.00 | 37.00 | 14,615.00 | 50.00 | 19,750.00 | | 0005 | 202-02-06140 | Removal of Curbs (Concrete) | 445.2 | LNFT | 10.00 | 4,452.00 | 5.00 | 2,226.00 | 28.00 | 12,465.60 | 20.00 | 8,904.00 | | 0006 | 202-02-40100 | Removal of Traffic Signal Equipment | 1 | LUMP | 7,500.00 | 7,500.00 | 6,000.00 | 6,000.00 | 6,340.00 | 6,340.00 | 7,500.00 | 7,500.00 | | 0007 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 15,000.00 | 15,000.00 | 25,000.00 | 25,000.00 | 50,000.00 | 50,000.00 | 35,000.00 | 35,000.00 | | 0008 | 204-02-00100 | Temporary Hay Bales | 60 | EACH | 25.00 | 1,500.00 | 50.00 | 3,000.00 | 50.00 | 3,000.00 | 2.00 | 120.00 | | 0009 | 302-02-08000 | Class II Base Course (8" Thick) | 572.7 | SQYD | 185.00 | 105,949.50 | 175.00 | 100,222.50 | 160.00 | 91,632.00 | 150.00 | 85,905.00 | | 0010 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 30.5 | CUYD | 185.00 | 5,642.50 | 150.00 | 4,575.00 | 240.00 | 7,320.00 | 200.00 | 6,100.00 | | 0011 | 402-01-00101 | Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) | 100 | CUYD | 185.00 | 18,500.00 | 100.00 | 10,000.00 | 200.00 | 20,000.00 | 1.00 | 100.00 | | 0012 | 502-01-00100 | Asphalt Concrete | 302.9 | TON | 345.00 | 104,500.50 | 325.00 | 98,442.50 | 300.00 | 90,870.00 | 275.00 | 83,297.50 | | 0013 | 509-01-00100 | Milling Asphalt Pavement | 2,630 | SQYD | 15.00 | 39,450.00 | 15.00 | 39,450.00 | 13.50 | 35,505.00 | 14.00 | 36,820.00 | | 0014 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -146 | CUYD | 1.00 | -146.00 | 25.00 | -3,650.00 | 22.00 | -3,212.00 | 1.00 | -146.00 | | 0015 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 15 | SQYD | 500.00 | 7,500.00 | 350.00 | 5,250.00 | 600.00 | 9,000.00 | 400.00 | 6,000.00 | | 0016 | 601-01-00100 | Portland Cement Concrete Pavement (8" Thick) | 380.7 | SQYD | 105.00 | 39,973.50 | 255.00 | 97,078.50 | 120.00 | 45,684.00 | 175.00 | 66,622.50 | | 0017 | 601-04-00100 | Portland Cement Concrete Pavement Coring | 5 | EACH | 450.00 | 2,250.00 | 750.00 | 3,750.00 | 540.00 | 2,700.00 | 500.00 | 2,500.00 | | 0018 | 701-04-01000 | Storm Drain Pipe Arch (15" Equiv. RCPA) | 80 | LNFT | 150.00 | 12,000.00 | 225.00 | 18,000.00 | 250.00 | 20,000.00 | 225.00 | 18,000.00 | | 0019 | 701-07-00300 | Yard Drain Pipe (8") | 110 | LNFT | 85.00 | 9,350.00 | 60.00 | 6,600.00 | 60.00 | 6,600.00 | 125.00 | 13,750.00 | | 0020 | 701-07-00500 | Yard Drain Pipe (12") | 13 | LNFT | 95.00 | 1,235.00 | 90.00 | 1,170.00 | 115.00 | 1,495.00 | 165.00 | 2,145.00 | | 0021 | 702-02-00200 | Manholes (R-CB-11) | 1 | EACH | 5,800.00 | 5,800.00 | 6,000.00 | 6,000.00 | 7,500.00 | 7,500.00 | 8,500.00 | 8,500.00 | | 0022 | 702-03-00100 | Catch Basins (CB-01) | 1 | EACH | 5,800.00 | 5,800.00 | 5,000.00 | 5,000.00 | 9,000.00 | 9,000.00 | 6,500.00 | 6,500.00 | | 0023 | 702-03-00300 | Catch Basins (CB-04) | 1 | EACH | 2,000.00 | 2,000.00 | 3,000.00 | 3,000.00 | 4,000.00 | 4,000.00 | 4,500.00 | 4,500.00 | | 0024 | 702-03-00400 | Catch Basins (CB-05) | 3 | EACH | 1,000.00 | 3,000.00 | 2,000.00 | 6,000.00 | 4,500.00 | 13,500.00 | 3,500.00 | 10,500.00 | | 0025 | 702-03-00500 | Catch Basins (CB-06) | 2 | EACH | 5,300.00 | 10,600.00 | 7,000.00 | 14,000.00 | 13,000.00 | 26,000.00 | 8,000.00 | 16,000.00 | | 0026 | 702-04-00100 | Adjusting Manholes | 2 | EACH | 1,600.00 | 3,200.00 | 2,000.00 | 4,000.00 | 3,000.00 | 6,000.00 | 3,000.00 | 6,000.00 | | 0027 | 702-04-00210 | Convert Catch Basins to Manholes (CONVERT CB-01 TO MANHOLE) | 2 | EACH | 3,000.00 | 6,000.00 | 2,000.00 | 4,000.00 | 6,800.00 | 13,600.00 | 6,500.00 | 13,000.00 | | 0028 | 706-01-00200 | Concrete Walk (5" Thick) | 271.2 | SQYD | 75.00 | 20,340.00 | 135.00 | 36,612.00 | 92.00 | 24,950.40 | 100.00 | 27,120.00 | | 0029 | 706-02-00300 | Concrete Drive (8" Thick) | 104.8 | SQYD | 95.00 | 9,956.00 | 145.00 | 15,196.00 | 126.00 | 13,204.80 | 175.00 | 18,340.00 | | 0030 | 706-03-00500 | Incidental Concrete Paving (8" Thick) | 175.6 | SQYD | 100.00 | 17,560.00 | 135.00 | 23,706.00 | 125.00 | 21,950.00 | 175.00 | 30,730.00 | | 0031 | 706-04-00110 | Curb Ramps Type 1 | 57.3 | SQYD | 140.00 | 8,022.00 | 250.00 | 14,325.00 | 200.00 | 11,460.00 | 250.00 | 14,325.00 | | 0032 | 706-04-00110 | Curb Ramps Type 3 | 12.3 | SQYD | 215.00 | 2,644.50 | 250.00 | 3,075.00 | 300.00 | 3,690.00 | 350.00 | 4,305.00 | | 0033 | 706-04-00110 | Curb Ramps Type 7 | 13.7 | SQYD | 180.00 | 2,466.00 | 250.00 | 3,425.00 | 300.00 | 4,110.00 | 350.00 | 4,795.00 | | 0034 | 707-01-00100 | Concrete Curb | 252.4 | LNFT | 40.00 | 10,096.00 | 35.00 | 8,834.00 | 30.00 | 7,572.00 | 45.00 | 11,358.00 | | 0035 | 707-03-00100 | Combination Concrete Curb and Gutter | 70.4 | LNFT | 43.00 | 3,027.20 | 50.00 | 3,520.00 | 80.00 | 5,632.00 | 80.00 | 5,632.00 | | 0036 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 37,000.00 | 37,000.00 | 75,000.00 | 75,000.00 | 135,000.00 | 135,000.00 | 75,000.00 | 75,000.00 | | 0037 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 0.53 | MILE | 2,000.00 | 1,060.00 | 2,000.00 | 1,060.00 | 1,100.00 | 583.00 | 1,000.00 | 530.00 | | 0038 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 1.155 | MILE | 6,500.00 | 7,507.50 | 2,500.00 | 2,887.50 | 2,200.00 | 2,541.00 | 2,000.00 | 2,310.00 | | 0039 | 713-06-00100 | Temporary Reflectorized Raised Pavement Markers | 70 | EACH | 19.00 | 1,330.00 | 10.00 | 700.00 | 11.00 | 770.00 | 10.00 | 700.00 | | 0040 | 714-01-00700 | Slab Sodding (Centipede) | 272 | SQYD | 12.00 | 3,264.00 | 10.00 | 2,720.00 | 14.50 | 3,944.00 | 16.00 | 4,352.00 | | 0041 | 726-01-00100 | Bedding Material | 20.9 | CUYD | 135.00 | 2,821.50 | 150.00 | 3,135.00 | 275.00 | 5,747.50 | 100.00 | 2,090.00 | | 0042 | 727-01-00100 | Mobilization | 1 | LUMP | 120,000.00 | 120,000.00 | 125,000.00 | 125,000.00 | 130,000.00 | 130,000.00 | 275,000.00 | 275,000.00 | | 0043 | 729-01-00102 | Sign (Type A)(Furnish and Install) | 65.6 | SQFT | 65.00 | 4,264.00 | 50.00 | 3,280.00 | 49.00 | 3,214.40 | 35.00 | 2,296.00 | | 0044 | 729-02-00102 | Sign (Type B)(Furnish and Install) | 22 | SQFT | 45.00 | 990.00 | 50.00 | 1,100.00 | 27.50 | 605.00 | 40.00 | 880.00 | | 0045 | 729-22-00100 | Square Tubing Post with 2-1/4" Anchor | 6 | EACH | 320.00 | 1,920.00 | 300.00 | 1,800.00 | 247.50 | 1,485.00 | 275.00 | 1,650.00 | | 0046 | 731-02-00100 | Reflectorized Raised Pavement Markers | 149 | EACH | 8.00 | 1,192.00 | 8.00 | 1,192.00 | 11.00 | 1,639.00 | 10.00 | 1,490.00 | | 0047 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 129.7 | LNFT | 18.00 | 2,334.60 | 15.00 | 1,945.50 | 27.50 | 3,566.75 | 25.00 | 3,242.50 | | 0048 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 0.613 | MILE | 6,700.00 | 4,107.10 | 6,000.00 | 3,678.00 | 8,250.00 | 5,057.25 | 7,500.00 | 4,597.50 | | 0049 | 732-02-02040 | Plastic Pavement Striping (Solid Line) (8" Width) (Thermoplastic 90 mil) | 0.086 | MILE | 11,000.00 | 946.00 | 12,000.00 | 1,032.00 | 27,500.00 | 2,365.00 | 25,000.00 | 2,150.00 | | 0050 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.102 | MILE | 12,000.00 | 1,224.00 | 14,000.00 | 1,428.00 | 2,750.00 | 280.50 | 2,500.00 | 255.00 | | 0051 | 732-03-02010 | Plastic Pavement Striping (Dotted Line)(4" W)(2' L)(Thermo 90 mil) | 0.031 | MILE | 12,000.00 | 372.00 | 15,000.00 | 465.00 | 5,320.00 | 164.92 | 5,000.00 | 155.00 | | 0052 | 732-03-04001 | Plastic Pav't Striping (Broken) (7" Width) (Preformed Tape) (Retroreflectivity Level I) (Black and White Contrast) | 0.085 | MILE | 17,000.00 | 1,445.00 | 20,000.00 | 1,700.00 | 22,000.00 | 1,870.00 | 20,000.00 | 1,700.00 | | 0053 | 732-04-01040 | Plastic Pavement Legends and Symbols (Arrow - Double) | 2 | EACH | 600.00 | 1,200.00 | 600.00 | 1,200.00 | 825.00 | 1,650.00 | 750.00 | 1,500.00 | | 0054 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 2 | EACH | 550.00 | 1,100.00 | 600.00 | 1,200.00 | 550.00 | 1,100.00 | 500.00 | 1,000.00 | | 0055 | 732-04-08000 | Plastic Pavement Legends and Symbols (Handicap Markings) (4" Width - Blue) | 150 | LNFT | 25.00 | 3,750.00 | 25.00 | 3,750.00 | 4.40 | 660.00 | 4.00 | 600.00 | | 0056 | 732-04-08040 | Plastic Pavement Legends and Symbols (Handicap Parking) | 1 | EACH | 635.00 | 635.00 | 600.00 | 600.00 | 825.00 | 825.00 | 750.00 | 750.00 | | 0057 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 2 | EACH | 450.00 | 900.00 | 600.00 | 1,200.00 | 550.00 | 1,100.00 | 500.00 | 1,000.00 | | 0058 | 732-04-18000 | Plastic Pavement Legends and Symbols (RR Crossing) | 2 | EACH | 1,900.00 | 3,800.00 | 2,000.00 | 4,000.00 | 1,100.00 | 2,200.00 | 1,000.00 | 2,000.00 | | 0059 | 732-05-00100 | Removal of Existing Markings | 0.258 | MILE | 24,000.00 | 6,192.00 | 10,000.00 | 2,580.00 | 22,000.00 | 5,676.00 | 20,000.00 | 5,160.00 | | 0060 | 736-01-00100 | Trenching and Backfilling | 310 | LNFT | 10.00 | 3,100.00 | 20.00 | 6,200.00 | 8.80 | 2,728.00 | 9.00 | 2,790.00 | | 0061 | 736-03-00100 | Jacking or Boring | 1,050 | LNFT | 24.00 | 25,200.00 | 25.00 | 26,250.00 | 20.50 | 21,525.00 | 20.00 | 21,000.00 | | 0062 | 736-04-00001 | Signal Pole (Pedestal Pole) | 3 | EACH | 1,200.00 | 3,600.00 | 1,500.00 | 4,500.00 | 1,000.00 | 3,000.00 | 920.00 | 2,760.00 | | 0063 | 736-04-10300 | Signal Pole (Single Mast Arm, 30ft) | 3 | EACH | 21,000.00 | 63,000.00 | 20,000.00 | 60,000.00 | 18,620.00 | 55,860.00 | 17,000.00 | 51,000.00 | | 0064 | 736-04-10400 | Signal Pole (Single Mast Arm, 40ft) | 1 | EACH | 25,000.00 | 25,000.00 | 25,000.00 | 25,000.00 | 21,380.00 | 21,380.00 | 20,000.00 | 20,000.00 | | 0065 | 736-05-30000 | Signal Heads (3 Section, 12 inch Led Lens, R, Y, G) | 6 | EACH | 1,300.00 | 7,800.00 | 1,200.00 | 7,200.00 | 1,100.00 | 6,600.00 | 1,100.00 | 6,600.00 | | 0066 | 736-05-51000 | Signal Heads (5 Section, 12 inch Led Lens, R, LT. Y, Y, LT. G, G) | 1 | EACH | 1,800.00 | 1,800.00 | 1,500.00 | 1,500.00 | 1,550.00 | 1,550.00 | 1,500.00 | 1,500.00 | | 0067 | 736-05-55000 | Signal Heads (5 Section, 12 inch Led Lens, R, Y, RT. Y, G, RT. G) | 1 | EACH | 1,800.00 | 1,800.00 | 1,500.00 | 1,500.00 | 1,550.00 | 1,550.00 | 1,500.00 | 1,500.00 | | 0068 | 736-06-00100 | Signal Service | 1 | EACH | 2,200.00 | 2,200.00 | 2,500.00 | 2,500.00 | 1,900.00 | 1,900.00 | 1,800.00 | 1,800.00 | | 0069 | 736-08-00102 | Signal Controller (980 ATC, Type 2)(Furnish & Install) | 1 | EACH | 9,000.00 | 9,000.00 | 10,000.00 | 10,000.00 | 7,950.00 | 7,950.00 | 7,500.00 | 7,500.00 | | 0070 | 736-09-00100 | Loop Detector | 915 | LNFT | 30.00 | 27,450.00 | 30.00 | 27,450.00 | 26.00 | 23,790.00 | 24.00 | 21,960.00 | | 0071 | 736-10-00200 | Underground Junction Box (Type E) | 1 | EACH | 1,375.00 | 1,375.00 | 1,500.00 | 1,500.00 | 1,185.00 | 1,185.00 | 1,100.00 | 1,100.00 | | 0072 | 736-10-00300 | Underground Junction Box (Type F) | 12 | EACH | 1,650.00 | 19,800.00 | 1,600.00 | 19,200.00 | 1,415.00 | 16,980.00 | 1,300.00 | 15,600.00 | | 0073 | 736-10-00400 | Underground Junction Box (Type G) | 1 | EACH | 2,500.00 | 2,500.00 | 2,200.00 | 2,200.00 | 2,150.00 | 2,150.00 | 2,200.00 | 2,200.00 | | 0074 | 736-11-00050 | Conduit (1/2" HDPE, Schedule 80) | 50 | LNFT | 5.00 | 250.00 | 10.00 | 500.00 | 4.40 | 220.00 | 4.50 | 225.00 | | 0075 | 736-11-00200 | Conduit (2" HDPE, Schedule 80) | 800 | LNFT | 7.00 | 5,600.00 | 10.00 | 8,000.00 | 6.15 | 4,920.00 | 6.00 | 4,800.00 | | 0076 | 736-11-00300 | Conduit (3" HDPE, Schedule 80) | 600 | LNFT | 10.00 | 6,000.00 | 12.00 | 7,200.00 | 9.20 | 5,520.00 | 9.00 | 5,400.00 | | 0077 | 736-12-00000 | Conductor (2c, Loop Lead in, imsa 50-2, #14 awg, Twisted Pair) | 1,800 | LNFT | 4.00 | 7,200.00 | 5.00 | 9,000.00 | 3.35 | 6,030.00 | 3.10 | 5,580.00 | | 0078 | 736-12-02014 | Conductor (2c, #14 awg) | 1,200 | LNFT | 4.00 | 4,800.00 | 5.00 | 6,000.00 | 3.70 | 4,440.00 | 4.00 | 4,800.00 | | 0079 | 736-12-03006 | Conductor (3c, 6 gauge / #6 awg) | 60 | LNFT | 9.00 | 540.00 | 10.00 | 600.00 | 8.35 | 501.00 | 8.00 | 480.00 | | 0080 | 736-12-06014 | Conductor (6c, #14 awg) | 1,500 | LNFT | 5.00 | 7,500.00 | 5.00 | 7,500.00 | 4.40 | 6,600.00 | 4.05 | 6,075.00 | | 0081 | 736-12-10014 | Conductor (10c, #14 awg) | 700 | LNFT | 6.00 | 4,200.00 | 7.00 | 4,900.00 | 5.15 | 3,605.00 | 5.00 | 3,500.00 | | 0082 | 736-15-02400 | Signal Support (Foundation, 24 inch Minimum Diameter) | 3 | EACH | 5,000.00 | 15,000.00 | 5,000.00 | 15,000.00 | 4,360.00 | 13,080.00 | 4,000.00 | 12,000.00 | | 0083 | 736-15-03600 | Signal Support (Foundation, 36 inch Minimum Diameter) | 4 | EACH | 10,000.00 | 40,000.00 | 10,000.00 | 40,000.00 | 9,180.00 | 36,720.00 | 8,400.00 | 33,600.00 | | 0084 | 736-21-00000 | LED Pedestrian Countdown Signal Head | 4 | EACH | 950.00 | 3,800.00 | 1,000.00 | 4,000.00 | 745.00 | 2,980.00 | 800.00 | 3,200.00 | | 0085 | 740-01-00100 | Construction Layout | 1 | LUMP | 20,000.00 | 20,000.00 | 15,000.00 | 15,000.00 | 25,000.00 | 25,000.00 | 11,500.00 | 11,500.00 | | 0086 | 741-35-00100 | Adjust Valve or Meter Box | 1 | EACH | 900.00 | 900.00 | 1,000.00 | 1,000.00 | 1,150.00 | 1,150.00 | 1,000.00 | 1,000.00 | | 0087 | 822-04-00400 | Jacked or Bored Casing Rigid 4" | 65 | LNFT | 45.00 | 2,925.00 | 50.00 | 3,250.00 | 38.60 | 2,509.00 | 38.00 | 2,470.00 | | 0088 | NS-500-00360 | Saw Cutting Asphalt Concrete Pavement Over Portland Cement Concrete Composite Pavement | 794 | INLF | 2.00 | 1,588.00 | 3.00 | 2,382.00 | 1.00 | 794.00 | 2.00 | 1,588.00 | | 0089 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 2,941 | INLF | 2.00 | 5,882.00 | 3.00 | 8,823.00 | 1.50 | 4,411.50 | 2.00 | 5,882.00 | | 0090 | NS-736-00001 | GPS | 1 | EACH | 575.00 | 575.00 | 500.00 | 500.00 | 490.00 | 490.00 | 500.00 | 500.00 | | 0091 | NS-736-00130 | TS-2 Traffic Signal Cabinet (Ground Mounted) | 1 | EACH | 30,000.00 | 30,000.00 | 30,000.00 | 30,000.00 | 26,000.00 | 26,000.00 | 25,000.00 | 25,000.00 | | 0092 | NS-736-00135 | 2-Wire Accessible Pedestrian Pushbutton Detectors | 4 | EACH | 1,400.00 | 5,600.00 | 1,200.00 | 4,800.00 | 1,185.00 | 4,740.00 | 1,100.00 | 4,400.00 | | 0093 | NS-736-00136 | 2-Wire Accessible Pedestrian Pushbutton Cabinet Control | 1 | EACH | 4,800.00 | 4,800.00 | 5,000.00 | 5,000.00 | 4,130.00 | 4,130.00 | 3,800.00 | 3,800.00 | | 0094 | TS-707-00310 | Concrete Curb Barrier (Drilled and Doweled) | 241 | LNFT | 22.00 | 5,302.00 | 30.00 | 7,230.00 | 50.00 | 12,050.00 | 45.00 | 10,845.00 | | 0095 | TS-707-23060 | Wheel Stops | 2 | EACH | 200.00 | 400.00 | 125.00 | 250.00 | 596.69 | 1,193.38 | 250.00 | 500.00 | | 0096 | TS-719-00020 | Pavers (BRICK)(CONCRETE SIDEWALK WITH BRICK HEADERS) | 1,129 | SQFT | 135.00 | 152,415.00 | 50.00 | 56,450.00 | 37.00 | 41,773.00 | 45.00 | 50,805.00 | | | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 1,238,409.40 | | 1,285,075.00 | | 1,313,000.00 | | 1,358,186.00 |
|