Proposal:H.015330.6
Parish:Grant
Routes:LA 472
Description:LA 472: LINCECUM VILLAGE RD - LA 500
Type Construction:MILLING ASPHALT CONCRETE, PAVEMENT PATCHING, ASPHALT CONCRETE OVERLAY, AND RELATED WORK.
Estimated Construction Cost:$1,408,390.85
| Rank | License | Bidder | Construction Bid |
| 1 | 12487 | Diamond B Construction Co., L.L.C. | $1,476,617.38 |
| 2 | 12312 | GILCHRIST CONSTRUCTION COMPANY, LLC | $1,517,607.71 |
| 3 | 05789 | D & J CONSTRUCTION CO., LLC | $1,650,165.80 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Diamond B Construction Co., L.L.C. | - 2 - GILCHRIST CONSTRUCTION COMPANY, LLC | - 3 - D & J CONSTRUCTION CO., LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 202-02-14500 | Removal of Guard Rail | 346 | LNFT | 15.00 | 5,190.00 | 11.00 | 3,806.00 | 35.00 | 12,110.00 | | 0002 | 202-02-32100 | Removal of Pipe (Cross Drain) (18" CMP) | 40 | LNFT | 22.00 | 880.00 | 100.00 | 4,000.00 | 20.00 | 800.00 | | 0003 | 203-07-00100 | Borrow (Vehicular Measurement) | 150 | CUYD | 16.00 | 2,400.00 | 130.00 | 19,500.00 | 60.00 | 9,000.00 | | 0004 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 562 | CUYD | 96.00 | 53,952.00 | 88.00 | 49,456.00 | 75.00 | 42,150.00 | | 0005 | 502-01-00100 | Asphalt Concrete | 5,967.1 | TON | 140.00 | 835,394.00 | 144.00 | 859,262.40 | 158.00 | 942,801.80 | | 0006 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 242.6 | TON | 255.00 | 61,863.00 | 260.00 | 63,076.00 | 235.00 | 57,011.00 | | 0007 | 509-01-00100 | Milling Asphalt Pavement | 27,470 | SQYD | 2.50 | 68,675.00 | 3.00 | 82,410.00 | 4.00 | 109,880.00 | | 0008 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -832 | CUYD | 1.00 | -832.00 | 1.00 | -832.00 | 1.00 | -832.00 | | 0009 | 510-01-00300 | Pavement Patching (18" Minimum Thickness) | 372 | SQYD | 210.00 | 78,120.00 | 220.00 | 81,840.00 | 280.00 | 104,160.00 | | 0010 | 701-02-01000 | Cross Drain Pipe Arch (24" Equiv. RCPA) | 40 | LNFT | 310.00 | 12,400.00 | 400.00 | 16,000.00 | 300.00 | 12,000.00 | | 0011 | 701-17-00100 | Trench Excavation Safety Protection (Depth >5 feet) | 40 | LNFT | 15.00 | 600.00 | 200.00 | 8,000.00 | 3.00 | 120.00 | | 0012 | 704-01-01020 | Guard Rail (Single Thrie Beam) (6'-3" post spacing) | 200 | LNFT | 77.00 | 15,400.00 | 61.00 | 12,200.00 | 85.00 | 17,000.00 | | 0013 | 704-03-00200 | Blocked Out Guard Rail - 31", (6'-3" Post Spacing) | 25 | LNFT | 35.00 | 875.00 | 39.00 | 975.00 | 40.00 | 1,000.00 | | 0014 | 704-07-00200 | Guard Rail Transitions (Double Thrie Beam) | 100 | LNFT | 130.00 | 13,000.00 | 127.00 | 12,700.00 | 135.00 | 13,500.00 | | 0015 | 704-10-00310 | Guard Rail End Treatment, NCHRP 350 - 31" (TL-3 Flared) | 4 | EACH | 3,900.00 | 15,600.00 | 3,500.00 | 14,000.00 | 4,500.00 | 18,000.00 | | 0016 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 55,000.00 | 55,000.00 | 32,000.00 | 32,000.00 | 30,000.00 | 30,000.00 | | 0017 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 6.785 | MILE | 155.00 | 1,051.68 | 300.00 | 2,035.50 | 300.00 | 2,035.50 | | 0018 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 3.341 | MILE | 700.00 | 2,338.70 | 710.00 | 2,372.11 | 2,000.00 | 6,682.00 | | 0019 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 23.021 | MILE | 1,100.00 | 25,323.10 | 1,100.00 | 25,323.10 | 2,500.00 | 57,552.50 | | 0020 | 726-01-00100 | Bedding Material | 8.8 | CUYD | 165.00 | 1,452.00 | 110.00 | 968.00 | 130.00 | 1,144.00 | | 0021 | 727-01-00100 | Mobilization | 1 | LUMP | 140,000.00 | 140,000.00 | 150,000.00 | 150,000.00 | 100,000.00 | 100,000.00 | | 0022 | 729-16-00200 | Object Marker Assembly (Type 2) | 2 | EACH | 115.00 | 230.00 | 62.00 | 124.00 | 120.00 | 240.00 | | 0023 | 729-16-00300 | Object Marker Assembly (Type 3) | 4 | EACH | 125.00 | 500.00 | 105.00 | 420.00 | 130.00 | 520.00 | | 0024 | 731-02-00100 | Reflectorized Raised Pavement Markers | 460 | EACH | 9.00 | 4,140.00 | 9.00 | 4,140.00 | 16.00 | 7,360.00 | | 0025 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 12 | LNFT | 25.00 | 300.00 | 26.00 | 312.00 | 55.00 | 660.00 | | 0026 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 7.83 | MILE | 6,200.00 | 48,546.00 | 6,300.00 | 49,329.00 | 8,000.00 | 62,640.00 | | 0027 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 1.114 | MILE | 3,100.00 | 3,453.40 | 2,900.00 | 3,230.60 | 3,000.00 | 3,342.00 | | 0028 | 732-05-00100 | Removal of Existing Markings | 0.039 | MILE | 12,000.00 | 468.00 | 12,000.00 | 468.00 | 60,000.00 | 2,340.00 | | 0029 | 735-01-00100 | Mailboxes | 5 | EACH | 25.00 | 125.00 | 26.00 | 130.00 | 25.00 | 125.00 | | 0030 | 735-02-00100 | Mailbox Supports (Single) | 5 | EACH | 225.00 | 1,125.00 | 230.00 | 1,150.00 | 325.00 | 1,625.00 | | 0031 | 739-01-00100 | Hydro-Seeding | 3.29 | ACRE | 2,750.00 | 9,047.50 | 2,800.00 | 9,212.00 | 3,100.00 | 10,199.00 | | 0032 | 740-01-00100 | Construction Layout | 1 | LUMP | 20,000.00 | 20,000.00 | 10,000.00 | 10,000.00 | 25,000.00 | 25,000.00 | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 1,476,617.38 | | 1,517,607.71 | | 1,650,165.80 |
|