Bid Tabulations for the Letting of 3/13/2024 LA DOTD Headquarters

Proposal:H.014319.6
Parish:East Baton Rouge
Description:CEDARCREST AVENUE OVER WEINER CREEK
Type Construction:CLEARING AND GRUBBING, REMOVAL OF TIMBER SUPPORTED CONCRETE SLAB SPAN BRIDGE, GRADING, CLASS II BASE COURSE, SUBGRADE LAYER, ASPHALT CONCRETE PAVEMENT, REINFORCED CONCRETE BOX CULVERTS (PRECAST), AND RELATED WORK.
Estimated Construction Cost:$1,072,964.60
Rank License BidderConstruction Bid
112031R.J. Daigle & Sons Contractors, Inc$834,928.21
249356KORT's CONSTRUCTION SERVICES, INC.$894,636.10
368424Procivil, LLC$957,815.70
461167HENDRICK CONSTRUCTION, INC.$975,376.62
548896Command Construction Industries LLC$1,055,055.00
672429Arbour Construction, LLC$1,087,693.86
724901Hard Rock Construction LLC$1,297,992.78
814807Richard Price Contracting Co, LLC$1,426,131.82


Line
Number
Item NumberItem DescriptionQuantityUnit of
Measure
- 1 -
R.J. Daigle & Sons Contractors, Inc
- 2 -
KORT's CONSTRUCTION SERVICES, INC.
- 3 -
Procivil, LLC
- 4 -
HENDRICK CONSTRUCTION, INC.
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001201-01-00100Clearing and Grubbing 1     LUMP2,130.002,130.005,000.005,000.005,000.005,000.0012,492.8712,492.87
0002202-01-00100Removal of Structures and Obstructions 1     LUMP6,325.006,325.005,000.005,000.0010,000.0010,000.0011,784.0811,784.08
0003202-02-02000Removal of Asphalt Drives 23     SQYD50.001,150.0015.00345.0025.00575.0093.822,157.86
0004202-02-02020Removal of Asphalt Pavement 262.4   SQYD4.001,049.6015.003,936.0025.006,560.0022.175,817.41
0005202-02-03000Removal of Base – Soil Cement, Asphalt, or BCS 262.4   SQYD9.202,414.0815.003,936.0015.003,936.0084.0922,065.22
0006202-02-04501Removal of Bridge (STA. 50+00, 40' W x 96' L Timber Supported Concrete Slab Span, w/ curb and sidewalks)3,840     LUMP76,500.0076,500.0060,000.0060,000.00120,000.00120,000.0050,902.3450,902.34
0007202-02-06100Removal of Concrete Walks and Drives 53.94  SQYD21.301,148.9215.00809.1020.001,078.80104.245,622.71
0008203-02-00100Drainage Excavation 496     CUYD60.0029,760.0045.0022,320.0015.007,440.0040.2819,978.88
0009203-05-00100Excavation and Embankment 1     LUMP33,500.0033,500.0010,000.0010,000.0015,000.0015,000.0033,439.7433,439.74
0010204-03-00100Temporary Slope Drains 60     LNFT53.803,228.0045.002,700.0025.001,500.0098.015,880.60
0011204-05-00100Temporary Sediment Check Dams (Hay) 4     EACH296.001,184.00190.00760.00250.001,000.00305.101,220.40
0012204-06-00100Temporary Silt Fencing 522     LNFT4.402,296.803.001,566.003.001,566.006.103,184.20
0013302-02-08520Class II Base Course (8-1/2" Thick) (Crushed Stone) 589.6   SQYD41.3024,350.4840.0023,584.0050.0029,480.0066.0438,937.18
0014305-01-01040Subgrade Layer (6" Thick) (Stone) 589.6   SQYD1.00589.6030.0017,688.0030.0017,688.0043.8525,853.96
0015402-01-00101Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) 50     CUYD23.001,150.00350.0017,500.00100.005,000.00157.127,856.00
0016502-01-00100Asphalt Concrete 94.1   TON193.0018,161.30280.0026,348.00400.0037,640.00601.2156,573.86
0017502-01-00200Asphalt Concrete, Drives, Turnouts and Miscellaneous 7     TON248.001,736.00350.002,450.00400.002,800.00555.103,885.70
0018705-06-00300Chain Link Fence (6-Foot Height) 65.4   LNFT61.504,022.1095.006,213.0050.003,270.00236.5215,468.41
0019706-01-00100Concrete Walk (4" Thick) 168     SQYD58.009,744.0082.0013,776.0080.0013,440.00123.0620,674.08
0020706-02-00200Concrete Drive (6" Thick) 47.8   SQYD156.507,480.7090.004,302.0090.004,302.00174.378,334.89
0021706-03-00100Incidental Concrete Paving (4" Thick) 79.2   SQYD96.007,603.2075.005,940.0070.005,544.0096.127,612.70
0022707-03-00100Combination Concrete Curb and Gutter 302.1   LNFT36.0010,875.6045.0013,594.5045.0013,594.5053.4116,135.16
0023711-04-00100Geotextile Fabric 375     SQYD3.401,275.002.50937.505.001,875.009.963,735.00
0024713-01-00100Temporary Signs and Barricades 1     LUMP11,000.0011,000.0020,000.0020,000.0015,000.0015,000.0015,922.2715,922.27
0025713-07-00100Temporary Precast Concrete Barrier (Contractor Furnished) 4     EACH1,720.006,880.003,150.0012,600.002,500.0010,000.00610.202,440.80
0026716-01-00100Mulch (Vegetative) 0.4   TON6,900.002,760.009,000.003,600.005,000.002,000.006,712.212,684.88
0027717-01-00100Seeding 6     LB89.00534.0090.00540.00100.00600.00122.04732.24
0028718-01-00100Fertilizer 200     LB2.50500.006.001,200.003.00600.002.44488.00
0029726-01-00100Bedding Material 500     CUYD112.0056,000.00194.0097,000.00125.0062,500.0091.0645,530.00
0030727-01-00100Mobilization 1     LUMP68,300.0068,300.0045,000.0045,000.0050,000.0050,000.0085,837.5785,837.57
0031729-16-00300Object Marker Assembly (Type 3) 4     EACH115.00460.00120.00480.00125.00500.00103.73414.92
0032731-02-00100Reflectorized Raised Pavement Markers 11     EACH57.50632.5019.00209.0030.00330.0030.51335.61
0033732-01-01000Plastic Pavement Striping (4" Width) (Thermoplastic 90 mil) 543     LNFT3.501,900.508.004,344.0010.005,430.0019.2710,463.61
0034740-01-00100Construction Layout 1     LUMP11,200.0011,200.007,500.007,500.005,000.005,000.009,153.019,153.01
0035805-15-02000Reinforced Concrete Box Culverts (Precast) (10' x 7') 150     LNFT2,035.00305,250.001,995.00299,250.002,500.00375,000.001,933.55290,032.50
0036805-17-00100Reinforced Concrete Box Culvert Headwall (3-10' x 7' Openings)2     EACH54,500.00109,000.0066,500.00133,000.0050,000.00100,000.0054,476.76108,953.52
0037807-01-00200Structural Metalwork (Grade 50) (200 ibs.)200     LUMP810.00810.00750.00750.005,000.005,000.001,562.011,562.01
0038NS-500-00340Saw Cutting Asphalt Concrete Pavement 959     INLF1.00959.002.502,397.502.001,918.003.022,896.18
0039NS-600-00220Saw Cutting Portland Cement Concrete Pavement 824.2   INLF1.15947.832.502,060.502.001,648.403.272,695.13
0040NS-713-00009Portable Changeable Message Sign (with communications) 4     EACH2,530.0010,120.004,000.0016,000.003,500.0014,000.003,905.2815,621.12
             
  CONTRACTOR TOTAL   834,928.21 894,636.10 957,815.70 975,376.62



Line
Number
Item NumberItem DescriptionQuantityUnit of
Measure
- 5 -
Command Construction Industries LLC
- 6 -
Arbour Construction, LLC
- 7 -
Hard Rock Construction LLC
- 8 -
Richard Price Contracting Co, LLC
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001201-01-00100Clearing and Grubbing 1     LUMP39,128.0039,128.0025,000.0025,000.005,400.005,400.0039,000.0039,000.00
0002202-01-00100Removal of Structures and Obstructions 1     LUMP40,000.0040,000.0035,000.0035,000.008,000.008,000.00109,000.00109,000.00
0003202-02-02000Removal of Asphalt Drives 23     SQYD25.00575.00116.002,668.0021.00483.0021.25488.75
0004202-02-02020Removal of Asphalt Pavement 262.4   SQYD25.006,560.0015.003,936.0028.007,347.2021.255,576.00
0005202-02-03000Removal of Base – Soil Cement, Asphalt, or BCS 262.4   SQYD25.006,560.0015.003,936.0028.007,347.2018.604,880.64
0006202-02-04501Removal of Bridge (STA. 50+00, 40' W x 96' L Timber Supported Concrete Slab Span, w/ curb and sidewalks)3,840     LUMP50,000.0050,000.00110,000.00110,000.0072,000.0072,000.0028,600.0028,600.00
0007202-02-06100Removal of Concrete Walks and Drives 53.94  SQYD25.001,348.5070.003,775.8027.001,456.3818.601,003.28
0008203-02-00100Drainage Excavation 496     CUYD25.0012,400.0060.0029,760.00110.0054,560.0042.5021,080.00
0009203-05-00100Excavation and Embankment 1     LUMP50,000.0050,000.0090,000.0090,000.0013,000.0013,000.0041,500.0041,500.00
0010204-03-00100Temporary Slope Drains 60     LNFT50.003,000.0060.003,600.0019.001,140.00187.0011,220.00
0011204-05-00100Temporary Sediment Check Dams (Hay) 4     EACH500.002,000.00230.00920.00292.001,168.00420.001,680.00
0012204-06-00100Temporary Silt Fencing 522     LNFT10.005,220.002.301,200.602.251,174.507.003,654.00
0013302-02-08520Class II Base Course (8-1/2" Thick) (Crushed Stone) 589.6   SQYD50.0029,480.0064.0037,734.4052.0030,659.2049.5029,185.20
0014305-01-01040Subgrade Layer (6" Thick) (Stone) 589.6   SQYD25.0014,740.0045.0026,532.0038.0022,404.8036.5021,520.40
0015402-01-00101Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) 50     CUYD50.002,500.0093.004,650.00170.008,500.00200.0010,000.00
0016502-01-00100Asphalt Concrete 94.1   TON350.0032,935.00325.0030,582.50238.0022,395.80538.0050,625.80
0017502-01-00200Asphalt Concrete, Drives, Turnouts and Miscellaneous 7     TON400.002,800.00325.002,275.00450.003,150.00560.003,920.00
0018705-06-00300Chain Link Fence (6-Foot Height) 65.4   LNFT100.006,540.0093.006,082.2056.003,662.40200.0013,080.00
0019706-01-00100Concrete Walk (4" Thick) 168     SQYD75.0012,600.00115.0019,320.00124.0020,832.00103.0017,304.00
0020706-02-00200Concrete Drive (6" Thick) 47.8   SQYD125.005,975.00115.005,497.00125.005,975.00192.009,177.60
0021706-03-00100Incidental Concrete Paving (4" Thick) 79.2   SQYD75.005,940.00115.009,108.00135.0010,692.00115.009,108.00
0022707-03-00100Combination Concrete Curb and Gutter 302.1   LNFT75.0022,657.5050.0015,105.0060.0018,126.0046.5014,047.65
0023711-04-00100Geotextile Fabric 375     SQYD5.001,875.006.002,250.003.751,406.253.901,462.50
0024713-01-00100Temporary Signs and Barricades 1     LUMP50,000.0050,000.0030,000.0030,000.0044,000.0044,000.0094,000.0094,000.00
0025713-07-00100Temporary Precast Concrete Barrier (Contractor Furnished) 4     EACH2,500.0010,000.001,150.004,600.001,300.005,200.002,950.0011,800.00
0026716-01-00100Mulch (Vegetative) 0.4   TON5,000.002,000.007,000.002,800.006,800.002,720.006,300.002,520.00
0027717-01-00100Seeding 6     LB100.00600.00116.00696.0088.00528.00126.00756.00
0028718-01-00100Fertilizer 200     LB5.001,000.002.30460.002.65530.006.501,300.00
0029726-01-00100Bedding Material 500     CUYD50.0025,000.00100.0050,000.00125.0062,500.0056.7528,375.00
0030727-01-00100Mobilization 1     LUMP95,000.0095,000.0070,000.0070,000.00187,000.00187,000.00110,000.00110,000.00
0031729-16-00300Object Marker Assembly (Type 3) 4     EACH500.002,000.00145.00580.0075.00300.00126.00504.00
0032731-02-00100Reflectorized Raised Pavement Markers 11     EACH25.00275.006.0066.0017.00187.0031.50346.50
0033732-01-01000Plastic Pavement Striping (4" Width) (Thermoplastic 90 mil) 543     LNFT10.005,430.006.003,258.006.003,258.009.505,158.50
0034740-01-00100Construction Layout 1     LUMP50,000.0050,000.0050,000.0050,000.009,555.009,555.0067,000.0067,000.00
0035805-15-02000Reinforced Concrete Box Culverts (Precast) (10' x 7') 150     LNFT2,250.00337,500.001,900.00285,000.002,700.00405,000.002,400.00360,000.00
0036805-17-00100Reinforced Concrete Box Culvert Headwall (3-10' x 7' Openings)2     EACH50,000.00100,000.0051,650.00103,300.00115,000.00230,000.00102,000.00204,000.00
0037807-01-00200Structural Metalwork (Grade 50) (200 ibs.)200     LUMP2,500.002,500.002,300.002,300.001,500.001,500.0010,000.0010,000.00
0038NS-500-00340Saw Cutting Asphalt Concrete Pavement 959     INLF5.004,795.002.302,205.701.251,198.752.502,397.50
0039NS-600-00220Saw Cutting Portland Cement Concrete Pavement 824.2   INLF5.004,121.002.301,895.661.501,236.302.502,060.50
0040NS-713-00009Portable Changeable Message Sign (with communications) 4     EACH2,500.0010,000.002,900.0011,600.005,600.0022,400.0019,700.0078,800.00
             
  CONTRACTOR TOTAL   1,055,055.00 1,087,693.86 1,297,992.78 1,426,131.82