Proposal:H.013267.6-R1
Parish:East Baton Rouge
Routes:US 61, US 61-X
Description:SCOTLANDVILLE PKWY TO DWTN BR TRAIL - PH 1
Type Construction:CLEARING AND GRUBBING, GRADING, DRAINAGE STRUCTURES, MILLING ASPHALT CONCRETE, CLASS II BASE COURSE, ASPHALT CONCRETE OVERLAY, SHARED-USE PATH (ASPHALT), SHARED USED PATH (PORTLAND CEMENT CONCRETE), TRAFFIC SIGNALIZATION, AND RELATED WORK.
Estimated Construction Cost:$5,838,072.10
| Rank | License | Bidder | Construction Bid |
| 1 | 46747 | Triumph Construction, LLC | $5,277,000.00 |
| 2 | 48896 | Command Construction Industries LLC | $6,348,055.07 |
| 3 | 00046 | Barber Bros. Contracting Co., L.L.C | $6,367,502.00 |
| 4 | 68237 | GULF STATES SERVICES, LLC | $6,422,850.37 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Triumph Construction, LLC | - 2 - Command Construction Industries LLC | - 3 - Barber Bros. Contracting Co., L.L.C | - 4 - GULF STATES SERVICES, LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 85,090.00 | 85,090.00 | 100,000.00 | 100,000.00 | 25,000.00 | 25,000.00 | 88,000.00 | 88,000.00 | | 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 28,570.00 | 28,570.00 | 50,000.00 | 50,000.00 | 10,000.00 | 10,000.00 | 33,000.00 | 33,000.00 | | 0003 | 202-02-00010 | Removal of Gate | 1 | EACH | 450.00 | 450.00 | 500.00 | 500.00 | 400.00 | 400.00 | 700.00 | 700.00 | | 0004 | 202-02-00030 | Removal of Pipe Rail/Bollards | 352 | LNFT | 13.75 | 4,840.00 | 10.00 | 3,520.00 | 15.00 | 5,280.00 | 15.00 | 5,280.00 | | 0005 | 202-02-02020 | Removal of Asphalt Pavement | 188 | SQYD | 31.65 | 5,950.20 | 25.00 | 4,700.00 | 15.00 | 2,820.00 | 35.00 | 6,580.00 | | 0006 | 202-02-03000 | Removal of Base – Soil Cement, Asphalt, or BCS | 188 | SQYD | 31.65 | 5,950.20 | 50.00 | 9,400.00 | 15.00 | 2,820.00 | 35.00 | 6,580.00 | | 0007 | 202-02-06060 | Removal of Concrete Catch Basin | 1 | EACH | 1,360.00 | 1,360.00 | 500.00 | 500.00 | 1,000.00 | 1,000.00 | 1,500.00 | 1,500.00 | | 0008 | 202-02-06080 | Removal of Concrete Combination Curb and Gutter | 2,418 | LNFT | 2.90 | 7,012.20 | 25.00 | 60,450.00 | 12.00 | 29,016.00 | 15.00 | 36,270.00 | | 0009 | 202-02-06100 | Removal of Concrete Walks and Drives | 3,788 | SQYD | 14.20 | 53,789.60 | 25.00 | 94,700.00 | 19.00 | 71,972.00 | 35.00 | 132,580.00 | | 0010 | 202-02-06140 | Removal of Curbs (Concrete) | 1,099 | LNFT | 5.38 | 5,912.62 | 10.00 | 10,990.00 | 12.00 | 13,188.00 | 15.00 | 16,485.00 | | 0011 | 202-02-12020 | Removal of Fence (Chain Link) | 45 | LNFT | 11.78 | 530.10 | 25.00 | 1,125.00 | 15.00 | 675.00 | 10.00 | 450.00 | | 0012 | 202-02-38240 | Removal of Signs and Supports | 37 | EACH | 17.03 | 630.11 | 100.00 | 3,700.00 | 27.00 | 999.00 | 25.00 | 925.00 | | 0013 | 202-03-38000 | Relocation of Sign (According to Plans) | 30 | EACH | 56.67 | 1,700.10 | 100.00 | 3,000.00 | 55.00 | 1,650.00 | 50.00 | 1,500.00 | | 0014 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 69,690.00 | 69,690.00 | 75,000.00 | 75,000.00 | 85,000.00 | 85,000.00 | 85,000.00 | 85,000.00 | | 0015 | 204-02-00100 | Temporary Hay Bales | 518 | EACH | 14.19 | 7,350.42 | 10.00 | 5,180.00 | 22.00 | 11,396.00 | 45.00 | 23,310.00 | | 0016 | 204-06-00100 | Temporary Silt Fencing | 24,472 | LNFT | 1.84 | 45,028.48 | 5.00 | 122,360.00 | 1.50 | 36,708.00 | 2.00 | 48,944.00 | | 0017 | 302-02-06000 | Class II Base Course (6" Thick) | 1,074.7 | SQYD | 36.70 | 39,441.49 | 40.00 | 42,988.00 | 55.00 | 59,108.50 | 65.00 | 69,855.50 | | 0018 | 302-02-08020 | Class II Base Course (8" Thick) (Crushed Stone) | 226.9 | SQYD | 49.54 | 11,240.63 | 75.00 | 17,017.50 | 85.00 | 19,286.50 | 75.00 | 17,017.50 | | 0019 | 402-01-00101 | Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) | 974.2 | CUYD | 113.03 | 110,113.83 | 100.00 | 97,420.00 | 25.00 | 24,355.00 | 1.00 | 974.20 | | 0020 | 502-01-00100 | Asphalt Concrete | 50.5 | TON | 340.00 | 17,170.00 | 500.00 | 25,250.00 | 425.00 | 21,462.50 | 450.00 | 22,725.00 | | 0021 | 509-01-00100 | Milling Asphalt Pavement | 1,680 | SQYD | 30.60 | 51,408.00 | 30.00 | 50,400.00 | 16.00 | 26,880.00 | 8.00 | 13,440.00 | | 0022 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -93.33 | CUYD | 0.64 | -59.73 | 0.01 | -0.93 | 0.00 | 0.00 | 0.01 | -0.93 | | 0023 | 701-03-01002 | Storm Drain Pipe (15" RCP/RPVCP) | 1,624 | LNFT | 83.44 | 135,506.56 | 130.00 | 211,120.00 | 100.00 | 162,400.00 | 115.00 | 186,760.00 | | 0024 | 701-03-01022 | Storm Drain Pipe (18" RCP/RPVCP) | 80 | LNFT | 95.38 | 7,630.40 | 150.00 | 12,000.00 | 125.00 | 10,000.00 | 135.00 | 10,800.00 | | 0025 | 701-03-01042 | Storm Drain Pipe (24" RCP/RPVCP) | 340 | LNFT | 119.68 | 40,691.20 | 175.00 | 59,500.00 | 140.00 | 47,600.00 | 150.00 | 51,000.00 | | 0026 | 701-05-01021 | Side Drain Pipe (15" RCP/RPVCP/CPEPDW/CMP) | 64 | LNFT | 100.63 | 6,440.32 | 130.00 | 8,320.00 | 110.00 | 7,040.00 | 121.00 | 7,744.00 | | 0027 | 701-07-00600 | Yard Drain Pipe (15") | 592 | LNFT | 43.41 | 25,698.72 | 65.00 | 38,480.00 | 95.00 | 56,240.00 | 115.00 | 68,080.00 | | 0028 | 701-07-00700 | Yard Drain Pipe (18") | 8 | LNFT | 557.50 | 4,460.00 | 100.00 | 800.00 | 215.00 | 1,720.00 | 135.00 | 1,080.00 | | 0029 | 701-17-00100 | Trench Excavation Safety Protection (Depth >5 feet) | 178 | LNFT | 10.22 | 1,819.16 | 1.00 | 178.00 | 5.00 | 890.00 | 1.00 | 178.00 | | 0030 | 702-03-00100 | Catch Basins (CB-01) | 29 | EACH | 4,935.52 | 143,130.08 | 7,500.00 | 217,500.00 | 4,500.00 | 130,500.00 | 5,000.00 | 145,000.00 | | 0031 | 702-04-00150 | Adjusting Manholes w/Manhole Adjustment Rings | 12 | EACH | 584.17 | 7,010.04 | 1,000.00 | 12,000.00 | 500.00 | 6,000.00 | 1,200.00 | 14,400.00 | | 0032 | 702-04-01000 | Capping Existing Catch Basin or Manhole | 38 | EACH | 725.53 | 27,570.14 | 1,000.00 | 38,000.00 | 1,000.00 | 38,000.00 | 3,000.00 | 114,000.00 | | 0033 | 706-02-00200 | Concrete Drive (6" Thick) | 2,922.7 | SQYD | 62.94 | 183,954.74 | 125.00 | 365,337.50 | 132.00 | 385,796.40 | 85.00 | 248,429.50 | | 0034 | 706-03-00100 | Incidental Concrete Paving (4" Thick) | 23.9 | SQYD | 85.36 | 2,040.10 | 100.00 | 2,390.00 | 450.00 | 10,755.00 | 150.00 | 3,585.00 | | 0035 | 706-04-00110 | Curb Ramps (Type 6) | 68.5 | SQYD | 63.94 | 4,379.89 | 225.00 | 15,412.50 | 125.00 | 8,562.50 | 185.00 | 12,672.50 | | 0036 | 706-04-00110 | Curb Ramps (Type 7) | 811.3 | SQYD | 60.24 | 48,872.71 | 225.00 | 182,542.50 | 125.00 | 101,412.50 | 185.00 | 150,090.50 | | 0037 | 707-01-00100 | Concrete Curb | 882 | LNFT | 21.96 | 19,368.72 | 25.00 | 22,050.00 | 50.00 | 44,100.00 | 40.00 | 35,280.00 | | 0038 | 707-03-00100 | Combination Concrete Curb and Gutter | 2,418 | LNFT | 24.28 | 58,709.04 | 40.00 | 96,720.00 | 50.00 | 120,900.00 | 50.00 | 120,900.00 | | 0039 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 106,109.00 | 106,109.00 | 100,000.00 | 100,000.00 | 200,000.00 | 200,000.00 | 550,000.00 | 550,000.00 | | 0040 | 714-01-00100 | Slab Sodding (Bermuda Grass) | 1,271 | SQYD | 10.77 | 13,688.67 | 10.00 | 12,710.00 | 15.00 | 19,065.00 | 10.00 | 12,710.00 | | 0041 | 726-01-00100 | Bedding Material | 248.3 | CUYD | 115.47 | 28,671.20 | 80.00 | 19,864.00 | 125.00 | 31,037.50 | 1.00 | 248.30 | | 0042 | 727-01-00100 | Mobilization | 1 | LUMP | 562,098.17 | 562,098.17 | 625,000.00 | 625,000.00 | 575,000.00 | 575,000.00 | 800,000.00 | 800,000.00 | | 0043 | 729-01-00100 | Sign (Type A) | 2,473.5 | SQFT | 23.44 | 57,978.84 | 40.00 | 98,940.00 | 45.00 | 111,307.50 | 42.00 | 103,887.00 | | 0044 | 729-04-00100 | Sign (Type D) | 72.4 | SQFT | 39.78 | 2,880.07 | 40.00 | 2,896.00 | 45.00 | 3,258.00 | 42.00 | 3,040.80 | | 0045 | 729-08-00200 | Mounting (3 1/2" Size Post) | 3 | EACH | 2,153.33 | 6,459.99 | 2,500.00 | 7,500.00 | 2,600.00 | 7,800.00 | 2,500.00 | 7,500.00 | | 0046 | 729-08-00600 | Mounting (W6 x 12 Size Post) | 5 | EACH | 2,266.00 | 11,330.00 | 3,500.00 | 17,500.00 | 3,500.00 | 17,500.00 | 3,400.00 | 17,000.00 | | 0047 | 729-21-00100 | U-Channel Post | 5 | EACH | 58.00 | 290.00 | 200.00 | 1,000.00 | 165.00 | 825.00 | 175.00 | 875.00 | | 0048 | 729-22-00100 | Square Tubing Post with 2-1/4" Anchor | 580 | EACH | 186.95 | 108,431.00 | 275.00 | 159,500.00 | 105.00 | 60,900.00 | 125.00 | 72,500.00 | | 0049 | 732-01-01000 | Plastic Pavement Striping (4" Width) (Thermoplastic 90 mil) | 384 | LNFT | 5.68 | 2,181.12 | 5.00 | 1,920.00 | 5.50 | 2,112.00 | 5.00 | 1,920.00 | | 0050 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 4,045 | LNFT | 14.16 | 57,277.20 | 12.00 | 48,540.00 | 13.50 | 54,607.50 | 13.00 | 52,585.00 | | 0051 | 732-04-02010 | Plastic Pavement Legends and Symbols (Shared Lane) | 162 | EACH | 492.90 | 79,849.80 | 500.00 | 81,000.00 | 450.00 | 72,900.00 | 475.00 | 76,950.00 | | 0052 | 736-01-00100 | Trenching and Backfilling | 800 | LNFT | 11.34 | 9,072.00 | 10.00 | 8,000.00 | 15.00 | 12,000.00 | 14.00 | 11,200.00 | | 0053 | 736-03-00100 | Jacking or Boring from Conduit | 2,055 | LNFT | 20.39 | 41,901.45 | 30.00 | 61,650.00 | 26.00 | 53,430.00 | 25.00 | 51,375.00 | | 0054 | 736-04-00001 | Signal Pole (Pedestal Pole) | 5 | EACH | 2,402.00 | 12,010.00 | 2,250.00 | 11,250.00 | 1,000.00 | 5,000.00 | 944.00 | 4,720.00 | | 0055 | 736-05-30004 | Signal Heads (3 Section, 12 inch Led Lens, R, R, Y) | 16 | EACH | 1,530.00 | 24,480.00 | 1,400.00 | 22,400.00 | 1,100.00 | 17,600.00 | 1,005.00 | 16,080.00 | | 0056 | 736-06-00300 | Signal Service with Separate Disconnect for Street Lights | 4 | EACH | 5,100.00 | 20,400.00 | 2,500.00 | 10,000.00 | 3,400.00 | 13,600.00 | 3,071.00 | 12,284.00 | | 0057 | 736-06-00500 | Signal Service Pedestal Disconnect | 4 | EACH | 3,797.50 | 15,190.00 | 2,500.00 | 10,000.00 | 3,700.00 | 14,800.00 | 3,400.00 | 13,600.00 | | 0058 | 736-08-00102 | Signal Controller (980 ATC, Type 2)(Furnish & Install) | 4 | EACH | 7,932.50 | 31,730.00 | 10,000.00 | 40,000.00 | 7,600.00 | 30,400.00 | 7,000.00 | 28,000.00 | | 0059 | 736-10-00200 | Underground Junction Box (Type E) | 3 | EACH | 1,813.33 | 5,439.99 | 2,000.00 | 6,000.00 | 1,300.00 | 3,900.00 | 1,200.00 | 3,600.00 | | 0060 | 736-10-00300 | Underground Junction Box (Type F) | 17 | EACH | 2,096.47 | 35,639.99 | 2,250.00 | 38,250.00 | 1,400.00 | 23,800.00 | 1,300.00 | 22,100.00 | | 0061 | 736-10-00400 | Underground Junction Box (Type G) | 4 | EACH | 2,872.50 | 11,490.00 | 2,500.00 | 10,000.00 | 2,400.00 | 9,600.00 | 2,200.00 | 8,800.00 | | 0062 | 736-10-00600 | Underground Junction Box (Type I) | 1 | EACH | 3,230.00 | 3,230.00 | 3,000.00 | 3,000.00 | 4,400.00 | 4,400.00 | 4,000.00 | 4,000.00 | | 0063 | 736-10-00700 | Underground Junction Box (Type J) | 4 | EACH | 3,542.50 | 14,170.00 | 3,000.00 | 12,000.00 | 4,200.00 | 16,800.00 | 3,800.00 | 15,200.00 | | 0064 | 736-11-00200 | Conduit (2" HDPE, Schedule 80) | 2,300 | LNFT | 6.91 | 15,893.00 | 10.00 | 23,000.00 | 8.00 | 18,400.00 | 8.00 | 18,400.00 | | 0065 | 736-11-00300 | Conduit (3" HDPE, Schedule 80) | 650 | LNFT | 14.17 | 9,210.50 | 12.00 | 7,800.00 | 11.00 | 7,150.00 | 11.00 | 7,150.00 | | 0066 | 736-12-02014 | Conductor (2c, #14 awg) | 850 | LNFT | 3.01 | 2,558.50 | 3.00 | 2,550.00 | 3.00 | 2,550.00 | 3.00 | 2,550.00 | | 0067 | 736-12-03006 | Conductor (3c, 6 gauge / #6 awg) | 1,080 | LNFT | 12.81 | 13,834.80 | 12.00 | 12,960.00 | 10.00 | 10,800.00 | 9.50 | 10,260.00 | | 0068 | 736-12-03014 | Conductor (3c, #14 awg) | 1,270 | LNFT | 3.69 | 4,686.30 | 3.00 | 3,810.00 | 3.00 | 3,810.00 | 3.00 | 3,810.00 | | 0069 | 736-12-06014 | Conductor (6c, #14 awg) | 2,425 | LNFT | 4.54 | 11,009.50 | 5.00 | 12,125.00 | 5.00 | 12,125.00 | 4.40 | 10,670.00 | | 0070 | 736-15-02400 | Signal Support (Foundation, 24 inch Minimum Diameter) | 5 | EACH | 924.00 | 4,620.00 | 1,000.00 | 5,000.00 | 1,900.00 | 9,500.00 | 1,725.00 | 8,625.00 | | 0071 | 736-21-00000 | LED Pedestrian Countdown Signal Head | 8 | EACH | 1,428.75 | 11,430.00 | 1,250.00 | 10,000.00 | 870.00 | 6,960.00 | 790.00 | 6,320.00 | | 0072 | 740-01-00100 | Construction Layout | 1 | LUMP | 71,690.00 | 71,690.00 | 100,000.00 | 100,000.00 | 45,000.00 | 45,000.00 | 55,000.00 | 55,000.00 | | 0073 | 741-20-01020 | Water Main (1" PVC) | 80 | LNFT | 18.38 | 1,470.40 | 25.00 | 2,000.00 | 200.00 | 16,000.00 | 50.00 | 4,000.00 | | 0074 | 741-35-00100 | Adjust Valve or Meter Box | 1 | EACH | 1,590.00 | 1,590.00 | 250.00 | 250.00 | 700.00 | 700.00 | 1,000.00 | 1,000.00 | | 0075 | 742-01-00000 | Sanitary Sewer Pipe (4" PVC) | 54 | LNFT | 27.41 | 1,480.14 | 50.00 | 2,700.00 | 65.00 | 3,510.00 | 250.00 | 13,500.00 | | 0076 | 805-01-01000 | Class A1 Concrete (Headwalls) (Sta. 30+81)(4.7' x 22.3') | 6.08 | CUYD | 1,008.22 | 6,129.98 | 2,000.00 | 12,160.00 | 3,000.00 | 18,240.00 | 2,500.00 | 15,200.00 | | 0077 | 806-01-00100 | Deformed Reinforcing Steel | 389 | LB | 3.01 | 1,170.89 | 5.00 | 1,945.00 | 10.00 | 3,890.00 | 1.50 | 583.50 | | 0078 | 810-04-00100 | Hand Railing (Sta. 30+13 to Sta. 32+23) | 210 | LNFT | 300.29 | 63,060.90 | 100.00 | 21,000.00 | 250.00 | 52,500.00 | 195.00 | 40,950.00 | | 0079 | NS-201-00001 | Tree and Stump Removal (<= 36" Diameter) | 2 | EACH | 3,970.00 | 7,940.00 | 1,000.00 | 2,000.00 | 6,000.00 | 12,000.00 | 3,000.00 | 6,000.00 | | 0080 | NS-500-00340 | Saw Cutting Asphalt Concrete Pavement | 856 | INLF | 0.69 | 590.64 | 2.00 | 1,712.00 | 1.00 | 856.00 | 1.00 | 856.00 | | 0081 | NS-500-00360 | Saw Cutting Asphalt Concrete Pavement Over Portland Cement Concrete Composite Pavement | 33,112 | INLF | 0.96 | 31,787.52 | 2.00 | 66,224.00 | 0.80 | 26,489.60 | 1.00 | 33,112.00 | | 0082 | NS-502-05100 | Shared-Use Path (Asphalt Concrete) (2" Thick) | 16,813 | SQYD | 21.92 | 368,540.96 | 25.00 | 420,325.00 | 25.00 | 420,325.00 | 20.00 | 336,260.00 | | 0083 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 5,938 | INLF | 0.96 | 5,700.48 | 3.00 | 17,814.00 | 1.00 | 5,938.00 | 1.25 | 7,422.50 | | 0084 | NS-706-00440 | Shared-Use Path (Portland Cement Concrete) (6" Thick) | 15,132 | SQYD | 63.93 | 967,388.76 | 85.00 | 1,286,220.00 | 125.00 | 1,891,500.00 | 92.50 | 1,399,710.00 | | 0085 | NS-719-00001 | Tree Protection Fencing | 1 | LUMP | 3,790.00 | 3,790.00 | 30,000.00 | 30,000.00 | 2,500.00 | 2,500.00 | 5,500.00 | 5,500.00 | | 0086 | NS-719-00002 | Tree Trimming | 1 | LUMP | 11,330.00 | 11,330.00 | 10,000.00 | 10,000.00 | 20,000.00 | 20,000.00 | 6,500.00 | 6,500.00 | | 0087 | NS-736-00001 | GPS | 4 | EACH | 737.50 | 2,950.00 | 750.00 | 3,000.00 | 475.00 | 1,900.00 | 500.00 | 2,000.00 | | 0088 | NS-736-00130 | TS-2 Traffic Signal Cabinet (Ground Mounted) | 4 | EACH | 30,972.50 | 123,890.00 | 30,000.00 | 120,000.00 | 32,000.00 | 128,000.00 | 28,600.00 | 114,400.00 | | 0089 | NS-736-00133 | Battery Back-up System for Traffic Signals | 4 | EACH | 11,275.00 | 45,100.00 | 10,000.00 | 40,000.00 | 12,000.00 | 48,000.00 | 10,600.00 | 42,400.00 | | 0090 | NS-736-00135 | 2-Wire Accessible Pedestrian Pushbutton Detectors | 8 | EACH | 1,416.25 | 11,330.00 | 1,250.00 | 10,000.00 | 1,200.00 | 9,600.00 | 1,200.00 | 9,600.00 | | 0091 | NS-736-00136 | 2-Wire Accessible Pedestrian Pushbutton Cabinet Control | 4 | EACH | 4,760.00 | 19,040.00 | 4,000.00 | 16,000.00 | 4,800.00 | 19,200.00 | 4,400.00 | 17,600.00 | | 0092 | NS-736-00210 | Rectangular Rapid Flashing Beacon Assembly Pair (Double Sided) | 10 | EACH | 13,030.00 | 130,300.00 | 12,500.00 | 125,000.00 | 14,500.00 | 145,000.00 | 12,950.00 | 129,500.00 | | 0093 | NS-ITS-04000 | Fiber Optic Marker | 5 | EACH | 568.00 | 2,840.00 | 500.00 | 2,500.00 | 320.00 | 1,600.00 | 330.00 | 1,650.00 | | 0094 | NS-ITS-04010 | Pulling Fiber Optic Cable Through Existing Conduit | 2,010 | LNFT | 4.08 | 8,200.80 | 5.00 | 10,050.00 | 3.50 | 7,035.00 | 3.25 | 6,532.50 | | 0095 | NS-ITS-04035 | Fiber Optic Fan Out Kits, SM, 12 Strand, Furnish & Install | 4 | EACH | 85.00 | 340.00 | 100.00 | 400.00 | 255.00 | 1,020.00 | 235.00 | 940.00 | | 0096 | NS-ITS-04180 | Fiber Optic Connection, Install, Splice | 48 | EACH | 28.33 | 1,359.84 | 30.00 | 1,440.00 | 37.00 | 1,776.00 | 34.00 | 1,632.00 | | 0097 | NS-ITS-04200 | Fiber Optic Connection, Termination, Furnish & Install | 48 | EACH | 56.67 | 2,720.16 | 50.00 | 2,400.00 | 31.00 | 1,488.00 | 28.00 | 1,344.00 | | 0098 | NS-ITS-04250 | Fiber Optic Drop Cable, SM, 12 Strand, Furnish & Install | 3,580 | LNFT | 4.53 | 16,217.40 | 5.00 | 17,900.00 | 4.00 | 14,320.00 | 3.45 | 12,351.00 | | 0099 | NS-ITS-04290 | Fiber Optic Patch Cord, SM, 2 Strand, Furnish & Install | 8 | EACH | 57.50 | 460.00 | 50.00 | 400.00 | 58.00 | 464.00 | 55.00 | 440.00 | | 0100 | NS-ITS-04360 | Fiber Optic Connection Splice Tray, Furnish & Install | 4 | EACH | 142.50 | 570.00 | 150.00 | 600.00 | 135.00 | 540.00 | 124.00 | 496.00 | | 0101 | NS-ITS-04425 | Fiber Optic Connection Patch Panel, Outdoor, Furnish & Install | 4 | EACH | 1,185.00 | 4,740.00 | 1,200.00 | 4,800.00 | 1,200.00 | 4,800.00 | 1,100.00 | 4,400.00 | | 0102 | NS-ITS-05025 | Splice Closure, Outdoor, Furnish & Install | 4 | EACH | 1,700.00 | 6,800.00 | 1,500.00 | 6,000.00 | 1,500.00 | 6,000.00 | 1,400.00 | 5,600.00 | | 0103 | NS-ITS-09080 | Local Ethernet Switch, Furnish & Install | 4 | EACH | 3,117.50 | 12,470.00 | 3,000.00 | 12,000.00 | 2,900.00 | 11,600.00 | 2,600.00 | 10,400.00 | | 0104 | NS-ITS-12000 | Communications System Integration | 1 | LUMP | 7,480.00 | 7,480.00 | 7,500.00 | 7,500.00 | 4,700.00 | 4,700.00 | 4,300.00 | 4,300.00 | | 0105 | TS-700-00020 | Bench | 6 | EACH | 3,321.67 | 19,930.02 | 3,500.00 | 21,000.00 | 4,000.00 | 24,000.00 | 3,000.00 | 18,000.00 | | 0106 | TS-729-00010 | Sign | 12 | EACH | 32,678.33 | 392,139.96 | 11,000.00 | 132,000.00 | 13,000.00 | 156,000.00 | 12,000.00 | 144,000.00 | | 0107 | TS-736-10500 | Signal Support (Mast Arm Standard w/ 50 ft arm) | 3 | EACH | 49,456.67 | 148,370.01 | 50,000.00 | 150,000.00 | 38,000.00 | 114,000.00 | 34,300.00 | 102,900.00 | | 0108 | TS-736-10550 | Signal Support (Mast Arm Standard w/ 55 ft arm) | 1 | EACH | 53,940.00 | 53,940.00 | 55,000.00 | 55,000.00 | 44,000.00 | 44,000.00 | 39,800.00 | 39,800.00 | | 0109 | TS-736-12015 | Luminaire Arm w/LED Luminaire (15 ft. arm) | 4 | EACH | 4,125.00 | 16,500.00 | 3,500.00 | 14,000.00 | 935.00 | 3,740.00 | 844.00 | 3,376.00 | | 0110 | TS-736-15002 | GPS Based Traffic Signal Preemption System (With Existing Fiber Communication) | 4 | EACH | 10,312.50 | 41,250.00 | 9,000.00 | 36,000.00 | 10,000.00 | 40,000.00 | 9,230.00 | 36,920.00 | | 0111 | TS-MSC-00010 | Trash Receptacle | 3 | EACH | 4,163.33 | 12,489.99 | 1,500.00 | 4,500.00 | 3,300.00 | 9,900.00 | 3,000.00 | 9,000.00 | | 0112 | TS-MSC-00120 | Drainage Structure (Dry Well) | 1 | EACH | 4,190.00 | 4,190.00 | 6,500.00 | 6,500.00 | 2,500.00 | 2,500.00 | 1,650.00 | 1,650.00 | | 0113 | TS-MSC-00300 | Bike Racks | 3 | EACH | 1,150.00 | 3,450.00 | 2,000.00 | 6,000.00 | 2,500.00 | 7,500.00 | 2,550.00 | 7,650.00 | | 0114 | TS-MSC-00310 | Public Bike Repair Stations | 3 | EACH | 2,283.33 | 6,849.99 | 4,000.00 | 12,000.00 | 3,500.00 | 10,500.00 | 5,100.00 | 15,300.00 | | 0115 | TS-MSC-00320 | Water Fountains | 2 | EACH | 15,865.00 | 31,730.00 | 5,000.00 | 10,000.00 | 7,500.00 | 15,000.00 | 7,000.00 | 14,000.00 | | | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 5,277,000.00 | | 6,348,055.07 | | 6,367,502.00 | | 6,422,850.37 |
|