Proposal:H.013083.6
Parish:Iberia
Routes:LA 675
Description:JEFFERSON ISLAND SIDEWALK
Type Construction:CLEARING AND GRUBBING, DRAINAGE STRUCTURES, CONCRETE SIDEWALKS, AND RELATED WORK.
Estimated Construction Cost:$684,129.00
| Rank | License | Bidder | Construction Bid |
| 1 | 46747 | Triumph Construction, LLC | $547,000.00 |
| 2 | 52306 | SIEMA CONSTRUCTION, LLC | $642,261.00 |
| 3 | 34263 | La Contracting Enterprise LLC | $663,000.00 |
| 4 | 54206 | Southern Constructors, LLC | $777,171.00 |
| 5 | 30774 | Progressive Construction Co., LLC | $800,585.00 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Triumph Construction, LLC | - 2 - SIEMA CONSTRUCTION, LLC | - 3 - La Contracting Enterprise LLC | - 4 - Southern Constructors, LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 201-01-00100 | Clearing and Grubbing | 1.17 | LUMP | 25,450.00 | 25,450.00 | 4,720.00 | 4,720.00 | 12,000.00 | 12,000.00 | 10,000.00 | 10,000.00 | | 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 8,160.00 | 8,160.00 | 7,740.00 | 7,740.00 | 6,000.00 | 6,000.00 | 8,000.00 | 8,000.00 | | 0003 | 202-02-06100 | Removal of Concrete Walks and Drives | 380 | SQYD | 45.45 | 17,271.00 | 16.25 | 6,175.00 | 45.00 | 17,100.00 | 35.00 | 13,300.00 | | 0004 | 202-02-32140 | Removal of Pipe (Storm Drain) 24" RCP, 12" CMP | 261 | LNFT | 49.04 | 12,799.44 | 35.00 | 9,135.00 | 34.00 | 8,874.00 | 70.00 | 18,270.00 | | 0005 | 202-02-38240 | Removal of Signs and Supports | 1 | EACH | 200.00 | 200.00 | 31.00 | 31.00 | 162.15 | 162.15 | 1,000.00 | 1,000.00 | | 0006 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 26,380.00 | 26,380.00 | 105,800.00 | 105,800.00 | 57,000.00 | 57,000.00 | 45,000.00 | 45,000.00 | | 0007 | 204-02-00100 | Temporary Hay Bales | 28 | EACH | 27.14 | 759.92 | 77.50 | 2,170.00 | 36.50 | 1,022.00 | 100.00 | 2,800.00 | | 0008 | 204-06-00100 | Temporary Silt Fencing | 1,847 | LNFT | 1.59 | 2,936.73 | 2.59 | 4,783.73 | 2.75 | 5,079.25 | 5.00 | 9,235.00 | | 0009 | 701-04-01000 | Storm Drain Pipe Arch (15" Equiv. RCPA) | 43 | LNFT | 151.63 | 6,520.09 | 253.00 | 10,879.00 | 160.00 | 6,880.00 | 200.00 | 8,600.00 | | 0010 | 701-04-01040 | Storm Drain Pipe Arch (24" Equiv. RCPA) | 795 | LNFT | 96.97 | 77,091.15 | 129.00 | 102,555.00 | 195.00 | 155,025.00 | 210.00 | 166,950.00 | | 0011 | 701-15-00100 | Concrete Collar | 3 | EACH | 1,083.33 | 3,249.99 | 912.00 | 2,736.00 | 2,400.00 | 7,200.00 | 1,500.00 | 4,500.00 | | 0012 | 702-02-00100 | Manholes (MH-06) | 7 | EACH | 4,377.14 | 30,639.98 | 5,275.00 | 36,925.00 | 5,250.00 | 36,750.00 | 8,000.00 | 56,000.00 | | 0013 | 702-03-00100 | Catch Basins (CB-01) | 4 | EACH | 8,065.00 | 32,260.00 | 7,410.00 | 29,640.00 | 8,450.00 | 33,800.00 | 10,500.00 | 42,000.00 | | 0014 | 702-08-00100 | Side Drain Safety End (Type 1) | 6 | EACH | 4,298.33 | 25,789.98 | 3,400.00 | 20,400.00 | 4,200.00 | 25,200.00 | 7,500.00 | 45,000.00 | | 0015 | 706-01-00100 | Concrete Walk (4" Thick) | 938.3 | SQYD | 50.43 | 47,318.47 | 106.00 | 99,459.80 | 92.00 | 86,323.60 | 110.00 | 103,213.00 | | 0016 | 706-02-00300 | Concrete Drive (8" Thick) | 485.4 | SQYD | 80.22 | 38,938.79 | 126.00 | 61,160.40 | 120.00 | 58,248.00 | 130.00 | 63,102.00 | | 0017 | 706-03-00300 | Incidental Concrete Paving (6" Thick) | 48 | SQYD | 93.54 | 4,489.92 | 87.00 | 4,176.00 | 120.00 | 5,760.00 | 205.00 | 9,840.00 | | 0018 | 706-04-00110 | Curb Ramps (Type 3) | 8.1 | SQYD | 444.44 | 3,599.96 | 300.00 | 2,430.00 | 625.00 | 5,062.50 | 600.00 | 4,860.00 | | 0019 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 57,142.93 | 57,142.93 | 25,500.00 | 25,500.00 | 19,000.00 | 19,000.00 | 25,000.00 | 25,000.00 | | 0020 | 714-01-00700 | Slab Sodding (Centipede) | 823 | SQYD | 7.05 | 5,802.15 | 19.00 | 15,637.00 | 16.00 | 13,168.00 | 12.00 | 9,876.00 | | 0021 | 716-01-00100 | Mulch (Vegetative) | 0.08 | TON | 20,000.00 | 1,600.00 | 41,367.00 | 3,309.36 | 29,500.00 | 2,360.00 | 20,000.00 | 1,600.00 | | 0022 | 726-01-00100 | Bedding Material | 182.5 | CUYD | 92.60 | 16,899.50 | 151.00 | 27,557.50 | 195.00 | 35,587.50 | 130.00 | 23,725.00 | | 0023 | 727-01-00100 | Mobilization | 1 | LUMP | 54,700.00 | 54,700.00 | 43,000.06 | 43,000.06 | 32,000.00 | 32,000.00 | 77,000.00 | 77,000.00 | | 0024 | 729-01-00100 | Sign (Type A) | 16 | SQFT | 32.50 | 520.00 | 26.00 | 416.00 | 28.00 | 448.00 | 250.00 | 4,000.00 | | 0025 | 729-22-00100 | Square Tubing Post with 2-1/4" Anchor | 4 | EACH | 387.50 | 1,550.00 | 311.00 | 1,244.00 | 350.00 | 1,400.00 | 250.00 | 1,000.00 | | 0026 | 739-01-00100 | Hydro-Seeding | 0.13 | ACRE | 3,923.00 | 509.99 | 25,855.00 | 3,361.15 | 15,000.00 | 1,950.00 | 10,000.00 | 1,300.00 | | 0027 | 740-01-00100 | Construction Layout | 1 | LUMP | 30,000.00 | 30,000.00 | 6,820.00 | 6,820.00 | 15,000.00 | 15,000.00 | 10,000.00 | 10,000.00 | | 0028 | 741-35-00100 | Adjust Valve or Meter Box | 2 | EACH | 855.00 | 1,710.00 | 450.00 | 900.00 | 1,300.00 | 2,600.00 | 1,500.00 | 3,000.00 | | 0029 | NS-700-00100 | Trench Drains | 3 | EACH | 4,236.67 | 12,710.01 | 1,200.00 | 3,600.00 | 4,000.00 | 12,000.00 | 3,000.00 | 9,000.00 | | | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 547,000.00 | | 642,261.00 | | 663,000.00 | | 777,171.00 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 5 - Progressive Construction Co., LLC | | Unit Price | Total Amount | | 0001 | 201-01-00100 | Clearing and Grubbing | 1.17 | LUMP | 30,000.00 | 30,000.00 | | 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 5,000.00 | 5,000.00 | | 0003 | 202-02-06100 | Removal of Concrete Walks and Drives | 380 | SQYD | 20.00 | 7,600.00 | | 0004 | 202-02-32140 | Removal of Pipe (Storm Drain) 24" RCP, 12" CMP | 261 | LNFT | 35.00 | 9,135.00 | | 0005 | 202-02-38240 | Removal of Signs and Supports | 1 | EACH | 450.00 | 450.00 | | 0006 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 57,000.00 | 57,000.00 | | 0007 | 204-02-00100 | Temporary Hay Bales | 28 | EACH | 35.00 | 980.00 | | 0008 | 204-06-00100 | Temporary Silt Fencing | 1,847 | LNFT | 4.00 | 7,388.00 | | 0009 | 701-04-01000 | Storm Drain Pipe Arch (15" Equiv. RCPA) | 43 | LNFT | 185.00 | 7,955.00 | | 0010 | 701-04-01040 | Storm Drain Pipe Arch (24" Equiv. RCPA) | 795 | LNFT | 235.00 | 186,825.00 | | 0011 | 701-15-00100 | Concrete Collar | 3 | EACH | 2,500.00 | 7,500.00 | | 0012 | 702-02-00100 | Manholes (MH-06) | 7 | EACH | 6,700.00 | 46,900.00 | | 0013 | 702-03-00100 | Catch Basins (CB-01) | 4 | EACH | 9,000.00 | 36,000.00 | | 0014 | 702-08-00100 | Side Drain Safety End (Type 1) | 6 | EACH | 5,000.00 | 30,000.00 | | 0015 | 706-01-00100 | Concrete Walk (4" Thick) | 938.3 | SQYD | 120.00 | 112,596.00 | | 0016 | 706-02-00300 | Concrete Drive (8" Thick) | 485.4 | SQYD | 125.00 | 60,675.00 | | 0017 | 706-03-00300 | Incidental Concrete Paving (6" Thick) | 48 | SQYD | 115.00 | 5,520.00 | | 0018 | 706-04-00110 | Curb Ramps (Type 3) | 8.1 | SQYD | 350.00 | 2,835.00 | | 0019 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 28,000.00 | 28,000.00 | | 0020 | 714-01-00700 | Slab Sodding (Centipede) | 823 | SQYD | 12.00 | 9,876.00 | | 0021 | 716-01-00100 | Mulch (Vegetative) | 0.08 | TON | 15,000.00 | 1,200.00 | | 0022 | 726-01-00100 | Bedding Material | 182.5 | CUYD | 200.00 | 36,500.00 | | 0023 | 727-01-00100 | Mobilization | 1 | LUMP | 80,000.00 | 80,000.00 | | 0024 | 729-01-00100 | Sign (Type A) | 16 | SQFT | 50.00 | 800.00 | | 0025 | 729-22-00100 | Square Tubing Post with 2-1/4" Anchor | 4 | EACH | 300.00 | 1,200.00 | | 0026 | 739-01-00100 | Hydro-Seeding | 0.13 | ACRE | 15,000.00 | 1,950.00 | | 0027 | 740-01-00100 | Construction Layout | 1 | LUMP | 10,000.00 | 10,000.00 | | 0028 | 741-35-00100 | Adjust Valve or Meter Box | 2 | EACH | 850.00 | 1,700.00 | | 0029 | NS-700-00100 | Trench Drains | 3 | EACH | 5,000.00 | 15,000.00 | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 800,585.00 |
|