Bid Tabulations for the Letting of 12/13/2023 LA DOTD Headquarters

Proposal:H.015594.6
Parish:Jackson, Lincoln, Madison, Morehouse, Ouachita, Richland, Union, West Carroll
Routes:LA 17 & LA 609, LA 588, VARIOUS
Description:D05 RUMBLE STRIPS AND STRIPING PH 1
Type Construction:RUMBLE STRIPS, STRIPING, AND RELATED WORK.
Estimated Construction Cost:$7,454,652.82
Rank License BidderConstruction Bid
124518HIGHWAY GRAPHICS LLC$3,598,510.40
2C0009Arkansas Sign & Barricade, Inc.$3,862,927.72


Line
Number
Item NumberItem DescriptionQuantityUnit of
Measure
- 1 -
HIGHWAY GRAPHICS LLC
- 2 -
Arkansas Sign & Barricade, Inc.
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001706-03-00100Incidental Concrete Paving (4" Thick) 102.2   SQYD175.0017,885.0090.949,294.07
0002707-01-00100Concrete Curb 291     LNFT50.0014,550.0028.008,148.00
0003713-01-00100Temporary Signs and Barricades 1     LUMP15,000.0015,000.00150,000.00150,000.00
0004724-01-00100Rumble Strips (Centerline) 61.914 MILE750.0046,435.50600.0037,148.40
0005724-02-00100Rumble Strips (Shoulder/Edge) 338.376 MILE750.00253,782.00600.00203,025.60
0006727-01-00100Mobilization 1     LUMP15,000.0015,000.00125,000.00125,000.00
0007731-02-00100Reflectorized Raised Pavement Markers 35,764     EACH3.50125,174.006.00214,584.00
0008732-01-01000Plastic Pavement Striping (4" Width) (Thermoplastic 90 mil) 91     LNFT20.001,820.000.2522.75
0009732-01-01040Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) 2,683     LNFT8.0021,464.002.005,366.00
0010732-01-01080Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) 287     LNFT25.007,175.007.502,152.50
0011732-01-02080Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) 156     LNFT30.004,680.007.501,170.00
0012732-02-02020Plastic Pavement Striping (Solid Line) (6" Width) (Thermoplastic 90 mil) 569.218 MILE5,000.002,846,090.004,300.002,447,637.40
0013732-03-02020Plastic Pavement Striping (Broken Line) (6" Width) (Thermoplastic 90 mil) 98.128 MILE1,700.00166,817.604,500.00441,576.00
0014732-03-02040Plastic Pavement Striping (Dotted Line)(8" W)(3' L)(Thermo 90 mil) 0.082 MILE20,000.001,640.0015,000.001,230.00
0015732-04-01020Plastic Pavement Legends and Symbols (Arrow - Straight) 2     EACH750.001,500.00400.00800.00
0016732-04-01080Plastic Pavement Legends and Symbols (Arrow - Left Turn) 10     EACH750.007,500.00400.004,000.00
0017732-04-01100Plastic Pavement Legends and Symbols (Arrow - Right Turn) 2     EACH750.001,500.00400.00800.00
0018732-04-15020Plastic Pavement Legends and Symbols (ONLY) 10     EACH750.007,500.00500.005,000.00
0019732-04-18000Plastic Pavement Legends and Symbols (RR Crossing) 10     EACH1,500.0015,000.001,100.0011,000.00
0020732-05-00100Removal of Existing Markings 179.973 MILE100.0017,997.301,000.00179,973.00
0021740-01-00100Construction Layout 1     LUMP10,000.0010,000.0015,000.0015,000.00
         
  CONTRACTOR TOTAL   3,598,510.40 3,862,927.72