Proposal:H.014935.6
Parish:Vernon
Description:SAFETY MEASURES AT LOWER ANACOCO DAM
Type Construction:CLEARING AND GRUBBING, FENCING, SIGNAGE, LAKE SAFETY BUOYS, TIMBER PILES AND RELATED WORK.
Estimated Construction Cost:$368,129.00
| Rank | License | Bidder | Construction Bid |
| 1 | 74077 | TLP Construction Co. LLC | $405,045.00 |
| 2 | 33325 | RIVER/GULF MARINE, L.L.C. | $425,368.00 |
| 3 | 26435 | C.E.C., Inc. | $566,565.00 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - TLP Construction Co. LLC | - 2 - RIVER/GULF MARINE, L.L.C. | - 3 - C.E.C., Inc. | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 201-01-00100 | Clearing and Grubbing | 0.3 | LUMP | 5,000.00 | 5,000.00 | 30,000.00 | 30,000.00 | 13,000.00 | 13,000.00 | | 0002 | 202-02-00030 | Removal of Handrail | 182 | LNFT | 15.00 | 2,730.00 | 20.00 | 3,640.00 | 32.00 | 5,824.00 | | 0003 | 202-02-12020 | Removal of Fence (Chain Link) | 332 | LNFT | 15.00 | 4,980.00 | 20.00 | 6,640.00 | 35.00 | 11,620.00 | | 0004 | 204-06-00100 | Temporary Silt Fencing | 574 | LNFT | 10.00 | 5,740.00 | 2.00 | 1,148.00 | 10.00 | 5,740.00 | | 0005 | 705-06-00100 | Chain Link Fence (4-Foot Height) | 182 | LNFT | 40.00 | 7,280.00 | 28.00 | 5,096.00 | 62.00 | 11,284.00 | | 0006 | 705-06-00300 | Chain Link Fence (6-Foot Height) | 323 | LNFT | 60.00 | 19,380.00 | 33.00 | 10,659.00 | 69.00 | 22,287.00 | | 0007 | 705-08-02040 | 6-Foot Double Gates for Chain Link Fence (6-Foot Height) | 1 | DBGT | 5,000.00 | 5,000.00 | 2,500.00 | 2,500.00 | 4,400.00 | 4,400.00 | | 0008 | 717-01-00100 | Seeding | 9 | LB | 225.00 | 2,025.00 | 35.00 | 315.00 | 200.00 | 1,800.00 | | 0009 | 718-01-00100 | Fertilizer | 180 | LB | 8.50 | 1,530.00 | 3.00 | 540.00 | 10.00 | 1,800.00 | | 0010 | 727-01-00100 | Mobilization | 1 | LUMP | 40,000.00 | 40,000.00 | 40,000.00 | 40,000.00 | 75,000.00 | 75,000.00 | | 0011 | 729-01-00100 | Sign (Type A) | 226 | SQFT | 80.00 | 18,080.00 | 100.00 | 22,600.00 | 75.00 | 16,950.00 | | 0012 | 729-22-00200 | Square Tubing Post with 2-1/4" Omni-Directional Anchor | 6 | EACH | 350.00 | 2,100.00 | 300.00 | 1,800.00 | 900.00 | 5,400.00 | | 0013 | 740-01-00100 | Construction Layout | 1 | LUMP | 40,000.00 | 40,000.00 | 40,000.00 | 40,000.00 | 7,000.00 | 7,000.00 | | 0014 | 804-02-00100 | Treated Timber Piles (Noncoastal Treatment) | 360 | LNFT | 250.00 | 90,000.00 | 300.00 | 108,000.00 | 550.00 | 198,000.00 | | 0015 | 810-04-00100 | Hand Railing | 182 | LNFT | 300.00 | 54,600.00 | 105.00 | 19,110.00 | 230.00 | 41,860.00 | | 0016 | NS-705-00004 | Chain Link Fence With Barbed Wire Extension | 40 | LNFT | 40.00 | 1,600.00 | 40.00 | 1,600.00 | 240.00 | 9,600.00 | | 0017 | NS-705-00005 | Single Gates for Chain Link Fence w/Barbed Wire Extension | 1 | EACH | 5,000.00 | 5,000.00 | 2,500.00 | 2,500.00 | 5,000.00 | 5,000.00 | | 0018 | TS-MSC-30050 | Lake Safety Buoys approximately 645 LNFT of lake safety buoys | 1 | LUMP | 100,000.00 | 100,000.00 | 129,220.00 | 129,220.00 | 130,000.00 | 130,000.00 | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 405,045.00 | | 425,368.00 | | 566,565.00 |
|