Bid Tabulations for the Letting of 10/11/2023 LA DOTD Headquarters

Proposal:H.013919.6
Parish:Concordia
Routes:LA 15
Description:LA 15: SLOCUM - DEER PARK
Type Construction:CLEARING AND GRUBBING, MILLING ASPHALT PAVEMENT, DRAINAGE STRUCTURES, ASPHALT SURFACE TREATMENT, PAVEMENT PATCHING, ASPHALT CONCRETE OVERLAY; ADDITIVE ALTERNATE 1: CLEARING AND GRUBBING; AND RELATED WORK.
Estimated Construction Cost:$6,246,728.23
Rank License BidderConstruction Bid
105789D & J CONSTRUCTION CO., LLC$5,538,693.55
218191Apac-Mississippi, Inc.$6,635,669.19
312312GILCHRIST CONSTRUCTION COMPANY, LLC$6,706,410.55
412487Diamond B Construction Co., L.L.C.$7,430,724.44


Line
Number
Item NumberItem DescriptionQuantityUnit of
Measure
- 1 -
D & J CONSTRUCTION CO., LLC
- 2 -
Apac-Mississippi, Inc.
- 3 -
GILCHRIST CONSTRUCTION COMPANY, LLC
- 4 -
Diamond B Construction Co., L.L.C.
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001201-01-00100Clearing and Grubbing 2.447 LUMP60,000.0060,000.00170,000.00170,000.00123,000.00123,000.00135,000.00135,000.00
0002202-02-14500Removal of Guard Rail 713     LNFT22.0015,686.0010.007,130.0011.007,843.0015.0010,695.00
0003202-02-32100Removal of Pipe (Cross Drain) 36" & 48"24     LNFT30.00720.00335.008,040.00150.003,600.0035.00840.00
0004203-07-00100Borrow (Vehicular Measurement) 155     CUYD55.008,525.00160.0024,800.0060.009,300.0022.003,410.00
0005204-02-00100Temporary Hay Bales 36     EACH15.00540.00200.007,200.0065.002,340.0075.002,700.00
0006204-06-00100Temporary Silt Fencing 34     LNFT12.00408.00235.007,990.0015.00510.0025.00850.00
0007401-02-00100Aggregate Surface Course (Adjusted Vehicular Measurement) 288     CUYD55.0015,840.00162.0046,656.00170.0048,960.00155.0044,640.00
0008502-01-00100Asphalt Concrete 22,130.5   TON125.002,766,312.50150.003,319,575.00140.003,098,270.00159.003,518,749.50
0009502-01-00200Asphalt Concrete, Drives, Turnouts and Miscellaneous 577.4   TON125.0072,175.00277.00159,939.80140.0080,836.00300.00173,220.00
0010507-01-00100Asphalt Material (CRS-2P Emulsion) 45,670     GAL4.00182,680.004.26194,554.204.00182,680.004.00182,680.00
0011507-02-00300Aggregate (S3) 147,327     SQYD1.50220,990.501.83269,608.411.60235,723.201.75257,822.25
0012509-01-00100Milling Asphalt Pavement 147,327     SQYD3.25478,812.753.30486,179.102.75405,149.253.00441,981.00
0013509-02-00100Contractor Retained Reclaimed Asphalt Pavement -4,100     CUYD1.00-4,100.000.10-410.001.00-4,100.001.00-4,100.00
0014510-01-00200Pavement Patching (12" Minimum Thickness) 5,500     SQYD132.00726,000.00125.00687,500.00175.00962,500.00164.30903,650.00
0015701-10-01100Reinforced Concrete Pipe (Extension) (36") 16     LNFT325.005,200.00520.008,320.001,400.0022,400.00376.006,016.00
0016701-10-01140Reinforced Concrete Pipe (Extension) (48") 32     LNFT400.0012,800.00380.0012,160.00900.0028,800.00455.0014,560.00
0017701-15-00100Concrete Collar 6     EACH1,500.009,000.002,400.0014,400.003,000.0018,000.005,000.0030,000.00
0018701-17-00100Trench Excavation Safety Protection (Depth >5 feet) 48     LNFT5.00240.0060.002,880.00100.004,800.0056.002,688.00
0019704-01-01020Guard Rail (Single Thrie Beam) (6'-3" post spacing) 283.8   LNFT180.0051,084.00128.0036,326.40140.0039,732.00180.0051,084.00
0020704-03-00200Blocked Out Guard Rail - 31", (6'-3" Post Spacing) 218.8   LNFT40.008,752.0036.007,876.8040.008,752.0036.007,876.80
0021704-07-00200Guard Rail Transitions (Double Thrie Beam) 100     LNFT135.0013,500.00127.0012,700.00137.0013,700.00132.0013,200.00
0022704-10-00120Guard Rail End Treatment, MASH, (TL-3 Flared) 7     EACH4,000.0028,000.003,675.0025,725.004,000.0028,000.004,000.0028,000.00
0023704-10-00204Guard Rail End Treatment, MASH, (TL-2 Tangent) 1     EACH3,900.003,900.003,750.003,750.004,100.004,100.004,000.004,000.00
0024711-01-04000Riprap (55 lb, 18" Thick) 44     SQYD140.006,160.00238.0010,472.00250.0011,000.00195.008,580.00
0025711-04-00100Geotextile Fabric 44     SQYD5.00220.0019.00836.001.0044.005.00220.00
0026713-01-00100Temporary Signs and Barricades 1     LUMP100,000.00100,000.00130,000.00130,000.0050,000.0050,000.0055,500.0055,500.00
0027713-03-01000Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) 21.698 MILE250.005,424.50500.0010,849.00300.006,509.40154.003,341.49
0028713-03-02000Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) 20.197 MILE800.0016,157.60600.0012,118.201,100.0022,216.701,100.0022,216.70
0029713-04-01000Temporary Pavement Markings (Solid Line) (4" Width) 47.045 MILE300.0014,113.501,200.0056,454.001,100.0051,749.501,900.0089,385.50
0030713-06-00200Temporary Reflectorized Raised Pavement Markers (Tabs) 2,558     EACH2.005,116.002.757,034.502.506,395.002.005,116.00
0031720-01-01000Erosion Control System (Slope Protection) (Type A) 960     SQYD5.004,800.0016.5015,840.001.751,680.002.502,400.00
0032724-02-00100Rumble Strips (Shoulder/Edge) 19.368 MILE300.005,810.40660.0012,782.881,200.0023,241.601,200.0023,241.60
0033726-01-00100Bedding Material 32.6   CUYD125.004,075.0086.002,803.60180.005,868.00115.003,749.00
0034727-01-00100Mobilization 1     LUMP315,000.00315,000.00300,000.00300,000.00670,000.00670,000.00690,000.00690,000.00
0035729-16-00200Object Marker Assembly (Type 2) 8     EACH115.00920.0055.00440.0060.00480.00115.00920.00
0036729-16-00300Object Marker Assembly (Type 3) 8     EACH130.001,040.0095.00760.00105.00840.00130.001,040.00
0037731-02-00100Reflectorized Raised Pavement Markers 1,378     EACH8.0011,024.008.0011,024.0011.0015,158.009.0012,402.00
0038732-02-02000Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) 21.193 MILE5,600.00118,680.805,500.00116,561.506,700.00141,993.107,000.00148,351.00
0039732-03-02000Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) 8.934 MILE1,600.0014,294.401,200.0010,720.804,000.0035,736.004,000.0035,736.00
0040735-01-00100Mailboxes 13     EACH30.00390.0050.00650.0021.00273.001.0013.00
0041735-02-00100Mailbox Supports (Single) 13     EACH300.003,900.00350.004,550.00260.003,380.00470.006,110.00
0042739-01-00100Hydro-Seeding 2.447 ACRE3,400.008,319.803,000.007,341.003,400.008,319.802,900.007,096.30
0043740-01-00100Construction Layout 1     LUMP20,000.0020,000.0016,900.0016,900.0050,000.0050,000.0025,000.0025,000.00
0044NS-719-00002Tree Trimming 1     LUMP42,000.0042,000.0078,000.0078,000.00100,000.00100,000.0080,000.0080,000.00
  SUBTOTAL GENERAL   5,374,512 6,319,038 6,529,780 7,049,981
             
 Additive Section 1ADDITIVE ALTERNATE 1 (CLEARING & GRUBBING)          
             
0045201-01-00100Clearing and Grubbing 8.877 LUMP134,000.00134,000.00290,000.00290,000.00150,000.00150,000.00355,000.00355,000.00
0046739-01-00100Hydro-Seeding 8.877 ACRE3,400.0030,181.803,000.0026,631.003,000.0026,631.002,900.0025,743.30
  SUBTOTAL ADDITIVE SECTION 1   164,181.80 316,631.00 176,631.00 380,743.30
             
  CONTRACTOR TOTAL   5,538,693.55 6,635,669.19 6,706,410.55 7,430,724.44