Proposal:H.014754.6
Parish:Caddo
Routes:LA 523
Description:LA 523: LEFT TURN LANES AT ASHLEY RIDGE
Type Construction:GRADING, CLASS II BASE COURSE, PORTLAND CEMENT CONCRETE PAVEMENT, AND RELATED WORK.
Estimated Construction Cost:$645,854.73
| Rank | License | Bidder | Construction Bid |
| 1 | 30774 | Progressive Construction Co., LLC | $829,882.70 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Progressive Construction Co., LLC | | Unit Price | Total Amount | | 0001 | 202-02-06140 | Removal of Curbs (Concrete) | 1,500.6 | LNFT | 30.00 | 45,018.00 | | 0002 | 202-02-26300 | Removal of Median / Island | 882 | SQYD | 40.00 | 35,280.00 | | 0003 | 202-03-38000 | Relocation of Sign (Rail Road) | 1 | EACH | 1,000.00 | 1,000.00 | | 0004 | 202-03-38020 | Relocation of Sign Pole W10-1 | 1 | EACH | 1,000.00 | 1,000.00 | | 0005 | 203-01-00100 | General Excavation (13" DEPTH) | 318 | CUYD | 75.00 | 23,850.00 | | 0006 | 302-02-05010 | Class II Base Course (5" Thick) (Asphalt Concrete Base) | 881.6 | SQYD | 100.00 | 88,160.00 | | 0007 | 601-01-00100 | Portland Cement Concrete Pavement (8" Thick) | 891.1 | SQYD | 200.00 | 178,220.00 | | 0008 | 706-03-00100 | Incidental Concrete Paving (4" Thick) | 293.4 | SQYD | 150.00 | 44,010.00 | | 0009 | 707-01-00100 | Concrete Curb | 2,265.1 | LNFT | 21.00 | 47,567.10 | | 0010 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 50,000.00 | 50,000.00 | | 0011 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 1,037 | LNFT | 1.25 | 1,296.25 | | 0012 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 492 | LNFT | 6.25 | 3,075.00 | | 0013 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 0.463 | MILE | 13,000.00 | 6,019.00 | | 0014 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 0.838 | MILE | 8,700.00 | 7,290.60 | | 0015 | 713-05-00220 | Temporary Pavement Legends & Symbols (Arrow - Left Turn) | 9 | EACH | 250.00 | 2,250.00 | | 0016 | 713-05-00400 | Temporary Pavement Legends & Symbols (RR Crossing) | 2 | EACH | 1,250.00 | 2,500.00 | | 0017 | 713-06-00100 | Temporary Reflectorized Raised Pavement Markers | 199 | EACH | 13.00 | 2,587.00 | | 0018 | 727-01-00100 | Mobilization | 1 | LUMP | 83,000.00 | 83,000.00 | | 0019 | 729-01-00100 | Sign (Type A) | 7 | SQFT | 500.00 | 3,500.00 | | 0020 | 729-08-00100 | Mounting (2 1/2" Size Post) | 1 | EACH | 2,000.00 | 2,000.00 | | 0021 | 731-02-00100 | Reflectorized Raised Pavement Markers | 199 | EACH | 15.00 | 2,985.00 | | 0022 | 731-03-00100 | Removal of Raised Pavement Markers | 0.384 | MILE | 12,500.00 | 4,800.00 | | 0023 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 1,037 | LNFT | 7.00 | 7,259.00 | | 0024 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 492 | LNFT | 30.00 | 14,760.00 | | 0025 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 0.838 | MILE | 10,000.00 | 8,380.00 | | 0026 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.463 | MILE | 6,250.00 | 2,893.75 | | 0027 | 732-03-02010 | Plastic Pavement Striping (Dotted Line)(4" W)(2' L)(Thermo 90 mil) | 0.032 | MILE | 190,000.00 | 6,080.00 | | 0028 | 732-03-02030 | Plastic Pavement Striping (Dotted Line)(8" W)(2' L)(Thermo 90 mil) | 0.053 | MILE | 190,000.00 | 10,070.00 | | 0029 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 9 | EACH | 650.00 | 5,850.00 | | 0030 | 732-04-18000 | Plastic Pavement Legends and Symbols (RR Crossing) | 2 | EACH | 3,200.00 | 6,400.00 | | 0031 | 732-05-00100 | Removal of Existing Markings | 0.581 | MILE | 25,000.00 | 14,525.00 | | 0032 | 737-05-00002 | Painted Curbs | 2,265 | LNFT | 13.00 | 29,445.00 | | 0033 | 740-01-00100 | Construction Layout | 1 | LUMP | 60,000.00 | 60,000.00 | | 0034 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 12,005 | INLF | 2.40 | 28,812.00 | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 829,882.70 |
|