Proposal:H.002424.6
Parish:St. James
Routes:LA 70
Description:LA 70: SUNSHINE BRIDGE - LA 22
Type Construction:CLEARING AND GRUBBING, GRADING, MILLING ASPHALT PAVEMENT, CLASS II BASE COURSE, SUBGRADE TREATMENT, DRAINAGE STRUCTURES, PAVEMENT PATCHING, ASPHALT CONCRETE, PRECAST CONCRETE PILES, CONCRETE SLAB SPAN BRIDGE, PORTLAND CEMENT CONCRETE PAVEMENT, SIGNALIZATION, DRILLED SHAFTS, INTELLIGENT TRANSPORTATION SYSTEM, ALTERNATE AA1: ASPHALT CONCRETE PAVEMENT; ALTERNATE AA2: PORTLAND CEMENT CONCRETE PAVEMENT, AND RELATED WORK.
Estimated Construction Cost:$53,207,904.04
Maximum Number of Days Allowed for Construction:9999
Calculated Daily User Cost:$14,000.00
| Rank | License | Bidder | Construction Bid | Bidder's Proposed Contract Time | Total Bid |
| 1 | 12312 | GILCHRIST CONSTRUCTION COMPANY, LLC | $50,182,110.02 | 700.00 | $59,982,110.02 |
| 2 | 34567 | James Construction Group LLC | $54,399,449.34 | 796.00 | $65,543,449.34 |
| 3 | 00046 | Barber Bros. Contracting Co., L.L.C | $53,676,629.71 | 1100.00 | $69,076,629.71 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - GILCHRIST CONSTRUCTION COMPANY, LLC | - 2 - James Construction Group LLC | - 3 - Barber Bros. Contracting Co., L.L.C | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 201-01-00100 | Clearing and Grubbing | 4 | LUMP | 3,500,000.00 | 3,500,000.00 | 2,328,792.00 | 2,328,792.00 | 2,400,000.00 | 2,400,000.00 | | 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 237,000.00 | 237,000.00 | 123,563.00 | 123,563.00 | 250,000.00 | 250,000.00 | | 0003 | 202-02-02000 | Removal of Asphalt Drives | 113 | SQYD | 28.00 | 3,164.00 | 625.00 | 70,625.00 | 25.00 | 2,825.00 | | 0004 | 202-02-02000 | Removal of Asphalt Drives | 613 | SQYD | 30.00 | 18,390.00 | 225.00 | 137,925.00 | 25.00 | 15,325.00 | | 0005 | 202-02-03030 | Removal of Pavement Structure | 17,145.8 | SQYD | 15.00 | 257,187.00 | 20.00 | 342,916.00 | 25.00 | 428,645.00 | | 0006 | 202-02-03030 | Removal of Pavement Structure | 9,137.9 | SQYD | 20.00 | 182,758.00 | 50.00 | 456,895.00 | 25.00 | 228,447.50 | | 0007 | 202-02-03030 | Removal of Pavement Structure | 1,164.4 | SQYD | 45.00 | 52,398.00 | 25.00 | 29,110.00 | 25.00 | 29,110.00 | | 0008 | 202-02-03030 | Removal of Pavement Structure | 373.3 | SQYD | 75.00 | 27,997.50 | 40.00 | 14,932.00 | 25.00 | 9,332.50 | | 0009 | 202-02-06040 | Removal of Concrete Box Headwall . | 7 | EACH | 7,000.00 | 49,000.00 | 6,851.00 | 47,957.00 | 8,000.00 | 56,000.00 | | 0010 | 202-02-06100 | Removal of Concrete Walks and Drives | 614 | SQYD | 30.00 | 18,420.00 | 50.00 | 30,700.00 | 25.00 | 15,350.00 | | 0011 | 202-02-12000 | Removal of Fence | 443 | LNFT | 12.00 | 5,316.00 | 20.00 | 8,860.00 | 5.00 | 2,215.00 | | 0012 | 202-02-14500 | Removal of Guard Rail | 911.1 | LNFT | 8.00 | 7,288.80 | 10.25 | 9,338.78 | 8.00 | 7,288.80 | | 0013 | 202-02-32180 | Removal of Pipe Headwalls | 7 | EACH | 5,000.00 | 35,000.00 | 4,404.00 | 30,828.00 | 3,500.00 | 24,500.00 | | 0014 | 202-02-40100 | Removal of Traffic Signal Equipment | 1 | LUMP | 8,500.00 | 8,500.00 | 7,826.00 | 7,826.00 | 8,500.00 | 8,500.00 | | 0015 | 202-02-40120 | Removal of Traffic Detectors and Associated Equipment | 1 | LUMP | 400.00 | 400.00 | 350.00 | 350.00 | 350.00 | 350.00 | | 0016 | 203-01-00100 | General Excavation | 32,944 | CUYD | 14.00 | 461,216.00 | 35.00 | 1,153,040.00 | 14.00 | 461,216.00 | | 0017 | 203-02-00100 | Drainage Excavation | 52 | CUYD | 65.00 | 3,380.00 | 190.00 | 9,880.00 | 70.00 | 3,640.00 | | 0018 | 203-03-00100 | Embankment | 228,723 | CUYD | 35.00 | 8,005,305.00 | 55.00 | 12,579,765.00 | 40.00 | 9,148,920.00 | | 0019 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 360 | EACH | 200.00 | 72,000.00 | 397.00 | 142,920.00 | 185.00 | 66,600.00 | | 0020 | 204-05-00200 | Temporary Sediment Check Dams (Stone) | 2 | EACH | 1,600.00 | 3,200.00 | 359.00 | 718.00 | 5,500.00 | 11,000.00 | | 0021 | 204-06-00100 | Temporary Silt Fencing | 29,334 | LNFT | 3.00 | 88,002.00 | 3.00 | 88,002.00 | 2.10 | 61,601.40 | | 0022 | 302-02-04070 | Class II Base Course (4" Thick) (Crushed Stone or Recycled Portland Cement Concrete) (Stone or Recycled PCCP) | 44,272.2 | SQYD | 19.00 | 841,171.80 | 20.00 | 885,444.00 | 26.00 | 1,151,077.20 | | 0023 | 302-02-04070 | Class II Base Course (4" Thick) (Crushed Stone or Recycled Portland Cement Concrete) (Stone or Recycled PCCP) | 85,126.1 | SQYD | 19.00 | 1,617,395.90 | 20.00 | 1,702,522.00 | 26.00 | 2,213,278.60 | | 0024 | 302-02-04070 | Class II Base Course (4" Thick) (Crushed Stone or Recycled Portland Cement Concrete) (Stone or Recycled PCCP) | 507.8 | SQYD | 19.00 | 9,648.20 | 40.00 | 20,312.00 | 26.00 | 13,202.80 | | 0025 | 302-02-06010 | Class II Base Course (6" Thick) (Soil Cement) | 129,906.1 | SQYD | 23.00 | 2,987,840.30 | 30.00 | 3,897,183.00 | 26.00 | 3,377,558.60 | | 0026 | 302-03-00100 | Base Drain Outlet | 98 | EACH | 1,750.00 | 171,500.00 | 2,000.00 | 196,000.00 | 1,000.00 | 98,000.00 | | 0027 | 305-01-04020 | Subgrade Layer (12" Thick) (Treated) | 130,244 | SQYD | 25.00 | 3,256,100.00 | 21.00 | 2,735,124.00 | 24.00 | 3,125,856.00 | | 0028 | 401-01-00100 | Aggregate Surface Course (Net Section) | 260 | CUYD | 170.00 | 44,200.00 | 415.00 | 107,900.00 | 145.00 | 37,700.00 | | 0029 | 402-01-00100 | Mainline Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) | 3,500 | CUYD | 75.00 | 262,500.00 | 189.00 | 661,500.00 | 50.00 | 175,000.00 | | 0030 | 402-02-00100 | Mainline Traffic Maintenance Surfacing (Hard) | 3,000 | SQYD | 65.00 | 195,000.00 | 25.00 | 75,000.00 | 65.00 | 195,000.00 | | 0031 | 402-03-00100 | Non-Mainline Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) | 1,000 | CUYD | 100.00 | 100,000.00 | 189.00 | 189,000.00 | 50.00 | 50,000.00 | | 0032 | 502-01-00100 | Asphalt Concrete | 13,196.7 | TON | 150.00 | 1,979,505.00 | 145.00 | 1,913,521.50 | 130.00 | 1,715,571.00 | | 0033 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 572.8 | TON | 310.00 | 177,568.00 | 300.00 | 171,840.00 | 200.00 | 114,560.00 | | 0034 | 502-04-00100 | Asphalt Concrete (SMA) Wearing Course | 2,359.3 | TON | 200.00 | 471,860.00 | 218.00 | 514,327.40 | 160.00 | 377,488.00 | | 0035 | 509-01-00100 | Milling Asphalt Pavement | 2,266.3 | SQYD | 12.00 | 27,195.60 | 10.00 | 22,663.00 | 7.00 | 15,864.10 | | 0036 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -125.9 | CUYD | 1.00 | -125.90 | 0.01 | -1.26 | 0.10 | -12.59 | | 0037 | 510-01-00300 | Pavement Patching (18" Minimum Thickness) | 58 | SQYD | 300.00 | 17,400.00 | 500.00 | 29,000.00 | 225.00 | 13,050.00 | | 0038 | 601-01-10000 | Portland Cement Concrete Pavement (Colored) 9" Thick | 612.6 | SQYD | 200.00 | 122,520.00 | 175.00 | 107,205.00 | 225.00 | 137,835.00 | | 0039 | 701-01-01004 | Cross Drain Pipe (24" RCP/RPVCP) | 588 | LNFT | 160.00 | 94,080.00 | 155.00 | 91,140.00 | 195.00 | 114,660.00 | | 0040 | 701-01-01024 | Cross Drain Pipe (30" RCP/RPVCP) | 72 | LNFT | 210.00 | 15,120.00 | 202.00 | 14,544.00 | 250.00 | 18,000.00 | | 0041 | 701-01-01043 | Cross Drain Pipe (36" RCP/RPVCP) | 90 | LNFT | 240.00 | 21,600.00 | 231.00 | 20,790.00 | 315.00 | 28,350.00 | | 0042 | 701-01-01063 | Cross Drain Pipe (42" RCP/RPVCP) | 220 | LNFT | 305.00 | 67,100.00 | 286.00 | 62,920.00 | 430.00 | 94,600.00 | | 0043 | 701-05-01045 | Side Drain Pipe (18" RCP/RPVCP/CPEPDW) | 450 | LNFT | 120.00 | 54,000.00 | 111.00 | 49,950.00 | 175.00 | 78,750.00 | | 0044 | 701-05-01064 | Side Drain Pipe (24" RCP/RPVCP/CPEPDW) | 406 | LNFT | 135.00 | 54,810.00 | 125.00 | 50,750.00 | 185.00 | 75,110.00 | | 0046 | 701-05-01081 | Side Drain Pipe (30" RCP/RPVCP/CPEPDW/CMP) | 38 | LNFT | 190.00 | 7,220.00 | 183.50 | 6,973.00 | 250.00 | 9,500.00 | | 0047 | 701-05-01101 | Side Drain Pipe (36" RCP/RPVCP/CPEPDW/CMP) | 298 | LNFT | 210.00 | 62,580.00 | 200.00 | 59,600.00 | 300.00 | 89,400.00 | | 0048 | 701-05-02041 | Side Drain Pipe (Erosion) (18" RPVCP/CPEPDW/CMP) | 60 | LNFT | 110.00 | 6,600.00 | 102.00 | 6,120.00 | 150.00 | 9,000.00 | | 0049 | 701-06-01080 | Side Drain Pipe Arch (36" Equiv. RCPA/CMPA) | 34 | LNFT | 300.00 | 10,200.00 | 285.00 | 9,690.00 | 400.00 | 13,600.00 | | 0050 | 701-10-01060 | Reinforced Concrete Pipe (Extension) (24") | 156 | LNFT | 200.00 | 31,200.00 | 183.00 | 28,548.00 | 210.00 | 32,760.00 | | 0051 | 701-10-01100 | Reinforced Concrete Pipe (Extension) (36") | 1,142 | LNFT | 300.00 | 342,600.00 | 286.00 | 326,612.00 | 325.00 | 371,150.00 | | 0052 | 701-14-00100 | Cleaning Existing Pipes | 3,316 | LNFT | 30.00 | 99,480.00 | 95.00 | 315,020.00 | 16.00 | 53,056.00 | | 0053 | 701-15-00100 | Concrete Collar | 12 | EACH | 1,500.00 | 18,000.00 | 1,319.00 | 15,828.00 | 3,000.00 | 36,000.00 | | 0054 | 701-17-00100 | Trench Excavation Safety Protection (Depth >5 feet) | 2,369 | LNFT | 8.00 | 18,952.00 | 6.50 | 15,398.50 | 25.00 | 59,225.00 | | 0055 | 702-03-00100 | Catch Basins (CB-01) | 19 | EACH | 6,000.00 | 114,000.00 | 5,690.00 | 108,110.00 | 7,500.00 | 142,500.00 | | 0056 | 704-03-00200 | Blocked Out Guard Rail - 31", (6'-3" Post Spacing) | 535.8 | LNFT | 37.00 | 19,824.60 | 37.00 | 19,824.60 | 40.00 | 21,432.00 | | 0057 | 704-07-00200 | Guard Rail Transitions (Double Thrie Beam) | 100 | LNFT | 115.00 | 11,500.00 | 117.00 | 11,700.00 | 115.00 | 11,500.00 | | 0058 | 704-10-00205 | Guard Rail End Treatment, MASH, (TL-3 Tangent) | 1 | EACH | 4,000.00 | 4,000.00 | 3,800.00 | 3,800.00 | 4,000.00 | 4,000.00 | | 0059 | 704-10-00305 | Guard Rail End Treatment, MASH, (TL-3 Bi-Directional) | 2 | EACH | 15,000.00 | 30,000.00 | 13,932.00 | 27,864.00 | 14,000.00 | 28,000.00 | | 0060 | 704-10-00310 | Guard Rail End Treatment, NCHRP 350 - 31" (TL-3 Flared) | 1 | EACH | 3,300.00 | 3,300.00 | 3,257.00 | 3,257.00 | 3,500.00 | 3,500.00 | | 0061 | 705-01-00100 | Barbed Wire Fence | 443 | LNFT | 13.00 | 5,759.00 | 12.00 | 5,316.00 | 14.00 | 6,202.00 | | 0062 | 705-04-00100 | Single Swinging Driveway Gates | 1 | EACH | 1,300.00 | 1,300.00 | 808.00 | 808.00 | 850.00 | 850.00 | | 0063 | 705-05-00100 | Double Swinging Driveway Gates | 3 | DBGT | 1,350.00 | 4,050.00 | 1,558.00 | 4,674.00 | 1,700.00 | 5,100.00 | | 0064 | 706-02-00200 | Concrete Drive (6" Thick) | 164.8 | SQYD | 135.00 | 22,248.00 | 139.11 | 22,925.33 | 175.00 | 28,840.00 | | 0065 | 706-03-00100 | Incidental Concrete Paving (4" Thick) | 422.3 | SQYD | 105.00 | 44,341.50 | 107.01 | 45,190.32 | 120.00 | 50,676.00 | | 0066 | 706-03-10000 | Incidental Concrete Paving (Colored)(inch Thick) 5" THICK | 1,512.8 | SQYD | 120.00 | 181,536.00 | 123.06 | 186,165.17 | 250.00 | 378,200.00 | | 0067 | 707-01-00100 | Concrete Curb | 1,407.6 | LNFT | 32.00 | 45,043.20 | 30.00 | 42,228.00 | 37.00 | 52,081.20 | | 0068 | 707-03-00100 | Combination Concrete Curb and Gutter | 3,868.6 | LNFT | 38.00 | 147,006.80 | 37.45 | 144,879.07 | 75.00 | 290,145.00 | | 0069 | 708-01-00100 | Right-of-Way Monument | 23 | EACH | 500.00 | 11,500.00 | 450.00 | 10,350.00 | 850.00 | 19,550.00 | | 0070 | 708-02-00100 | Right-of-Way Monument Witness Post | 23 | EACH | 500.00 | 11,500.00 | 450.00 | 10,350.00 | 75.00 | 1,725.00 | | 0071 | 711-01-03000 | Riprap (30 lb, 14" Thick) | 364 | SQYD | 100.00 | 36,400.00 | 165.00 | 60,060.00 | 130.00 | 47,320.00 | | 0072 | 712-04-00100 | Flexible Revetment | 975 | SQYD | 130.00 | 126,750.00 | 165.00 | 160,875.00 | 290.00 | 282,750.00 | | 0073 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 2,000,000.00 | 2,000,000.00 | 1,100,000.00 | 1,100,000.00 | 2,000,000.00 | 2,000,000.00 | | 0074 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 0.345 | MILE | 2,000.00 | 690.00 | 1,435.00 | 495.08 | 500.00 | 172.50 | | 0075 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 0.859 | MILE | 5,000.00 | 4,295.00 | 5,005.00 | 4,299.30 | 6,000.00 | 5,154.00 | | 0076 | 720-01-01000 | Erosion Control System (Slope Protection) (Type A) | 2,892 | SQYD | 3.00 | 8,676.00 | 3.00 | 8,676.00 | 3.00 | 8,676.00 | | 0077 | 722-02-00100 | Project Site Laboratory (Equipped) | 1 | EACH | 100,000.00 | 100,000.00 | 75,000.00 | 75,000.00 | 50,000.00 | 50,000.00 | | 0078 | 724-02-00100 | Rumble Strips (Shoulder/Edge) | 17.735 | MILE | 1,200.00 | 21,282.00 | 265.00 | 4,699.78 | 400.00 | 7,094.00 | | 0079 | 725-01-00100 | Temporary Detour Roads | 4,651.6 | SQYD | 150.00 | 697,740.00 | 240.00 | 1,116,384.00 | 135.00 | 627,966.00 | | 0080 | 726-01-00100 | Bedding Material | 1,082.2 | CUYD | 150.00 | 162,330.00 | 125.00 | 135,275.00 | 195.00 | 211,029.00 | | 0081 | 727-01-00100 | Mobilization | 1 | LUMP | 5,000,000.00 | 5,000,000.00 | 5,400,000.00 | 5,400,000.00 | 5,300,000.00 | 5,300,000.00 | | 0082 | 729-01-00100 | Sign (Type A) | 355.3 | SQFT | 23.00 | 8,171.90 | 25.00 | 8,882.50 | 30.00 | 10,659.00 | | 0083 | 729-02-00100 | Sign (Type B) | 83.3 | SQFT | 32.00 | 2,665.60 | 30.00 | 2,499.00 | 28.00 | 2,332.40 | | 0084 | 729-16-00300 | Object Marker Assembly (Type 3) | 10 | EACH | 100.00 | 1,000.00 | 99.00 | 990.00 | 110.00 | 1,100.00 | | 0085 | 729-22-00100 | Square Tubing Post with 2-1/4" Anchor | 33 | EACH | 180.00 | 5,940.00 | 175.00 | 5,775.00 | 200.00 | 6,600.00 | | 0086 | 731-02-00100 | Reflectorized Raised Pavement Markers | 1,357 | EACH | 12.00 | 16,284.00 | 14.00 | 18,998.00 | 9.00 | 12,213.00 | | 0087 | 732-01-01060 | Plastic Pavement Striping (12" Width) (Thermoplastic 90 mil) | 3,586 | LNFT | 11.00 | 39,446.00 | 8.00 | 28,688.00 | 9.00 | 32,274.00 | | 0088 | 732-01-01080 | Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) | 2,787 | LNFT | 21.00 | 58,527.00 | 15.00 | 41,805.00 | 20.00 | 55,740.00 | | 0089 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 18.806 | MILE | 8,000.00 | 150,448.00 | 5,505.00 | 103,527.03 | 5,800.00 | 109,074.80 | | 0090 | 732-02-02040 | Plastic Pavement Striping (Solid Line) (8" Width) (Thermoplastic 90 mil) | 0.773 | MILE | 26,000.00 | 20,098.00 | 12,452.00 | 9,625.40 | 25,000.00 | 19,325.00 | | 0091 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 6.571 | MILE | 2,100.00 | 13,799.10 | 3,032.00 | 19,923.27 | 1,600.00 | 10,513.60 | | 0092 | 732-03-02010 | Plastic Pavement Striping (Dotted Line)(4" W)(2' L)(Thermo 90 mil) Type B | 0.411 | MILE | 5,200.00 | 2,137.20 | 4,421.00 | 1,817.03 | 8,500.00 | 3,493.50 | | 0093 | 732-03-02030 | Plastic Pavement Striping (Dotted Line)(8" W)(2' L)(Thermo 90 mil) Type B | 0.188 | MILE | 10,200.00 | 1,917.60 | 9,182.00 | 1,726.22 | 10,000.00 | 1,880.00 | | 0094 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 32 | EACH | 500.00 | 16,000.00 | 429.00 | 13,728.00 | 700.00 | 22,400.00 | | 0095 | 732-05-00100 | Removal of Existing Markings | 3.29 | MILE | 22,000.00 | 72,380.00 | 18,225.00 | 59,960.25 | 10,000.00 | 32,900.00 | | 0096 | 735-01-00100 | Mailboxes | 4 | EACH | 27.00 | 108.00 | 25.00 | 100.00 | 22.00 | 88.00 | | 0097 | 735-02-00100 | Mailbox Supports (Single) | 4 | EACH | 210.00 | 840.00 | 200.00 | 800.00 | 275.00 | 1,100.00 | | 0098 | 736-01-00100 | Trenching and Backfilling | 1,560 | LNFT | 16.00 | 24,960.00 | 8.50 | 13,260.00 | 15.00 | 23,400.00 | | 0099 | 736-03-00100 | Jacking or Boring | 425 | LNFT | 50.00 | 21,250.00 | 36.00 | 15,300.00 | 52.00 | 22,100.00 | | 0100 | 736-04-00001 | Signal Pole (Pedestal Pole) | 1 | EACH | 1,800.00 | 1,800.00 | 2,228.00 | 2,228.00 | 1,800.00 | 1,800.00 | | 0101 | 736-04-10450 | Signal Pole (Single Mast Arm, 45ft) | 1 | EACH | 19,500.00 | 19,500.00 | 22,913.00 | 22,913.00 | 20,000.00 | 20,000.00 | | 0102 | 736-04-10500 | Signal Pole (Single Mast Arm, 50ft) | 1 | EACH | 21,000.00 | 21,000.00 | 24,696.00 | 24,696.00 | 22,000.00 | 22,000.00 | | 0103 | 736-05-30000 | Signal Heads (3 Section, 12 inch Led Lens, R, Y, G) | 2 | EACH | 1,600.00 | 3,200.00 | 1,341.00 | 2,682.00 | 1,700.00 | 3,400.00 | | 0104 | 736-05-31001 | Signal Heads (3 Sec, 12 inch Led Lens, LT. R, LT. Y, LT. G) | 3 | EACH | 1,700.00 | 5,100.00 | 1,341.00 | 4,023.00 | 1,700.00 | 5,100.00 | | 0105 | 736-06-00100 | Signal Service | 1 | EACH | 3,200.00 | 3,200.00 | 3,112.00 | 3,112.00 | 3,200.00 | 3,200.00 | | 0106 | 736-06-00500 | Signal Service Pedestal Disconnect | 1 | EACH | 3,200.00 | 3,200.00 | 2,641.00 | 2,641.00 | 3,400.00 | 3,400.00 | | 0107 | 736-08-00102 | Signal Controller (980 ATC, Type 2)(Furnish & Install) | 1 | EACH | 6,800.00 | 6,800.00 | 8,072.00 | 8,072.00 | 7,200.00 | 7,200.00 | | 0108 | 736-09-00100 | Loop Detector | 315 | LNFT | 40.00 | 12,600.00 | 24.00 | 7,560.00 | 40.00 | 12,600.00 | | 0109 | 736-10-00200 | Underground Junction Box (Type E) | 4 | EACH | 1,600.00 | 6,400.00 | 1,155.00 | 4,620.00 | 1,600.00 | 6,400.00 | | 0110 | 736-10-00300 | Underground Junction Box (Type F) | 2 | EACH | 1,800.00 | 3,600.00 | 1,654.00 | 3,308.00 | 2,800.00 | 5,600.00 | | 0111 | 736-10-00400 | Underground Junction Box (Type G) | 1 | EACH | 4,000.00 | 4,000.00 | 2,603.00 | 2,603.00 | 4,200.00 | 4,200.00 | | 0112 | 736-11-00050 | Conduit (1/2" HDPE, Schedule 80) | 55 | LNFT | 12.00 | 660.00 | 14.00 | 770.00 | 10.00 | 550.00 | | 0113 | 736-11-00200 | Conduit (2" HDPE, Schedule 80) | 1,835 | LNFT | 17.00 | 31,195.00 | 11.00 | 20,185.00 | 17.00 | 31,195.00 | | 0114 | 736-11-00300 | Conduit (3" HDPE, Schedule 80) | 375 | LNFT | 15.00 | 5,625.00 | 19.00 | 7,125.00 | 15.00 | 5,625.00 | | 0115 | 736-11-00400 | Conduit (4" HDPE, Schedule 80) | 250 | LNFT | 33.00 | 8,250.00 | 75.00 | 18,750.00 | 34.00 | 8,500.00 | | 0116 | 736-12-00000 | Conductor (2c, Loop Lead in, imsa 50-2, #14 awg, Twisted Pair) | 940 | LNFT | 4.25 | 3,995.00 | 3.00 | 2,820.00 | 4.00 | 3,760.00 | | 0117 | 736-12-01002 | Conductor (1c, #2 awg) | 7,600 | LNFT | 7.00 | 53,200.00 | 5.00 | 38,000.00 | 7.00 | 53,200.00 | | 0118 | 736-12-03006 | Conductor (3c, 6 gauge / #6 awg) | 150 | LNFT | 11.00 | 1,650.00 | 7.50 | 1,125.00 | 10.00 | 1,500.00 | | 0119 | 736-12-06014 | Conductor (6c, #14 awg) | 115 | LNFT | 7.25 | 833.75 | 4.00 | 460.00 | 8.00 | 920.00 | | 0120 | 736-12-10014 | Conductor (10c, #14 awg) | 595 | LNFT | 8.00 | 4,760.00 | 4.00 | 2,380.00 | 8.20 | 4,879.00 | | 0121 | 736-15-02400 | Signal Support (Foundation, 24 inch Minimum Diameter) | 1 | EACH | 1,600.00 | 1,600.00 | 1,155.00 | 1,155.00 | 1,600.00 | 1,600.00 | | 0122 | 736-15-03600 | Signal Support (Foundation, 36 inch Minimum Diameter) | 2 | EACH | 6,000.00 | 12,000.00 | 6,036.00 | 12,072.00 | 3,400.00 | 6,800.00 | | 0123 | 736-16-00000 | Temporary Traffic Signal Installation (Intersection) | 1 | EACH | 11,000.00 | 11,000.00 | 67,935.00 | 67,935.00 | 100,000.00 | 100,000.00 | | 0124 | 739-01-00100 | Hydro-Seeding | 37 | ACRE | 3,000.00 | 111,000.00 | 2,800.00 | 103,600.00 | 2,800.00 | 103,600.00 | | 0125 | 740-01-00100 | Construction Layout | 1 | LUMP | 750,000.00 | 750,000.00 | 500,000.00 | 500,000.00 | 2,300,000.00 | 2,300,000.00 | | 0126 | 803-01-00600 | Drilled Shaft (48" Diameter) | 29 | LNFT | 2,200.00 | 63,800.00 | 3,196.00 | 92,684.00 | 2,400.00 | 69,600.00 | | 0127 | 803-08-00600 | Crosshole Sonic Log Test (48" Diameter) | 1 | EACH | 5,200.00 | 5,200.00 | 6,837.00 | 6,837.00 | 6,000.00 | 6,000.00 | | 0128 | 804-01-00400 | Precast Concrete Piles (18") | 2,176 | LNFT | 135.00 | 293,760.00 | 124.00 | 269,824.00 | 170.00 | 369,920.00 | | 0129 | 804-05-00400 | Precast Concrete Test Piles (18") | 1 | EACH | 125,000.00 | 125,000.00 | 55,000.00 | 55,000.00 | 23,000.00 | 23,000.00 | | 0130 | 804-09-00400 | Static Load Test (Precast Concrete Piles (18")) | 1 | EACH | 125,000.00 | 125,000.00 | 90,000.00 | 90,000.00 | 115,000.00 | 115,000.00 | | 0131 | 804-14-00100 | Dynamic Monitoring Assistance | 7 | EACH | 8,000.00 | 56,000.00 | 15,125.00 | 105,875.00 | 2,250.00 | 15,750.00 | | 0132 | 805-01-00100 | Class A1 Concrete (Slab Span) | 246.54 | CUYD | 1,700.00 | 419,118.00 | 2,500.00 | 616,350.00 | 1,800.00 | 443,772.00 | | 0133 | 805-01-00300 | Class A1 Concrete (Bent Cap) | 68.92 | CUYD | 3,500.00 | 241,220.00 | 2,300.00 | 158,516.00 | 3,500.00 | 241,220.00 | | 0134 | 805-16-00100 | Reinforced Concrete Box Culverts (Extension) (4' x 4') | 880 | LNFT | 720.00 | 633,600.00 | 880.00 | 774,400.00 | 800.00 | 704,000.00 | | 0135 | 805-16-00600 | Reinforced Concrete Box Culverts (Extension) (5' x 5') | 560 | LNFT | 925.00 | 518,000.00 | 1,315.00 | 736,400.00 | 1,000.00 | 560,000.00 | | 0136 | 805-16-01200 | Reinforced Concrete Box Culverts (Extension) (6' x 6') | 204 | LNFT | 1,050.00 | 214,200.00 | 1,415.00 | 288,660.00 | 1,150.00 | 234,600.00 | | 0137 | 805-16-02700 | Reinforced Concrete Box Culverts (Extension) (6' x 4') | 204 | LNFT | 1,200.00 | 244,800.00 | 1,511.00 | 308,244.00 | 1,250.00 | 255,000.00 | | 0138 | 805-18-00100 | Concrete Finish (Class 2 Rubbed Finish) | 1,920 | SQFT | 3.00 | 5,760.00 | 2.00 | 3,840.00 | 8.20 | 15,744.00 | | 0139 | 805-18-00200 | Concrete Finish (Class 3 Special Finish) | 1,920 | SQFT | 3.00 | 5,760.00 | 1.00 | 1,920.00 | 2.70 | 5,184.00 | | 0140 | 806-01-00100 | Deformed Reinforcing Steel | 61,708 | LB | 2.00 | 123,416.00 | 2.00 | 123,416.00 | 2.20 | 135,757.60 | | 0141 | 810-01-00120 | Concrete Bridge Railing (36 inch Height) | 280 | LNFT | 175.00 | 49,000.00 | 210.00 | 58,800.00 | 360.00 | 100,800.00 | | 0142 | 813-01-00100 | Concrete Approach Slabs (Cast-in-Place) | 2,880 | SQFT | 125.00 | 360,000.00 | 155.00 | 446,400.00 | 135.00 | 388,800.00 | | 0143 | 814-01-00100 | Elastomeric Bearing Pads (Non-Reinforced) | 189 | SFIN | 130.00 | 24,570.00 | 150.00 | 28,350.00 | 165.00 | 31,185.00 | | 0144 | 815-03-00300 | Joint Seal (Poured) | 308 | LNFT | 28.00 | 8,624.00 | 15.00 | 4,620.00 | 7.00 | 2,156.00 | | 0145 | 822-02-07900 | Conduit w Conductors (PULLING CONDUCTORS THROUGH EXISTING CONDUIT) | 950 | LNFT | 5.00 | 4,750.00 | 11.00 | 10,450.00 | 5.00 | 4,750.00 | | 0146 | 822-11-00100 | Removal and Disposal of Electrical Equipment | 1 | LUMP | 4,000.00 | 4,000.00 | 10,925.00 | 10,925.00 | 3,500.00 | 3,500.00 | | 0147 | NS-500-00240 | Sawing and Sealing Transverse Joints in Asphalt Concrete Overlay | 216 | LNFT | 20.00 | 4,320.00 | 28.00 | 6,048.00 | 5.00 | 1,080.00 | | 0148 | NS-500-00260 | Sawcuts in Asphalt Concrete Lifts | 36 | LNFT | 100.00 | 3,600.00 | 31.00 | 1,116.00 | 2.00 | 72.00 | | 0149 | NS-500-00340 | Saw Cutting Asphalt Concrete Pavement | 37,992.5 | INLF | 0.55 | 20,895.88 | 1.00 | 37,992.50 | 0.80 | 30,394.00 | | 0150 | NS-500-00340 | Saw Cutting Asphalt Concrete Pavement | 64,547.7 | INLF | 0.78 | 50,347.21 | 0.82 | 52,929.11 | 0.80 | 51,638.16 | | 0151 | NS-500-00340 | Saw Cutting Asphalt Concrete Pavement | 10,131.3 | INLF | 0.83 | 8,408.98 | 0.82 | 8,307.67 | 0.80 | 8,105.04 | | 0152 | NS-702-00003 | Cleaning Existing Junction Box | 3 | EACH | 6,000.00 | 18,000.00 | 1,000.00 | 3,000.00 | 1,400.00 | 4,200.00 | | 0153 | NS-702-00100 | Paved Gutter Drain | 23 | EACH | 5,500.00 | 126,500.00 | 4,500.00 | 103,500.00 | 8,500.00 | 195,500.00 | | 0154 | NS-729-00031 | Breakaway Square Tubing Sign Support (Surface Mount) | 10 | EACH | 550.00 | 5,500.00 | 500.00 | 5,000.00 | 550.00 | 5,500.00 | | 0155 | NS-736-00001 | GPS | 1 | EACH | 525.00 | 525.00 | 682.00 | 682.00 | 550.00 | 550.00 | | 0156 | NS-736-00130 | TS-2 Traffic Signal Cabinet (Ground Mounted) | 1 | EACH | 25,000.00 | 25,000.00 | 26,494.00 | 26,494.00 | 26,000.00 | 26,000.00 | | 0157 | NS-ITS-01121 | CCTV Camera Assembly, Furnish and Install with PTZ, Digital | 1 | EACH | 15,000.00 | 15,000.00 | 20,006.00 | 20,006.00 | 15,500.00 | 15,500.00 | | 0158 | NS-ITS-03501 | CCTV Camera Site, Remove | 1 | EACH | 3,200.00 | 3,200.00 | 15,005.00 | 15,005.00 | 3,400.00 | 3,400.00 | | 0159 | NS-ITS-04005 | Tracer Wire (THWN #10 AWG Green Copper Conductor) | 110 | LNFT | 1.00 | 110.00 | 1.50 | 165.00 | 1.00 | 110.00 | | 0160 | NS-ITS-04035 | Fiber Optic Fan Out Kits, SM, 12 Strand, Furnish & Install | 1 | EACH | 135.00 | 135.00 | 189.00 | 189.00 | 150.00 | 150.00 | | 0161 | NS-ITS-04200 | Fiber Optic Connection, Termination, Furnish & Install | 12 | EACH | 72.00 | 864.00 | 100.00 | 1,200.00 | 78.00 | 936.00 | | 0162 | NS-ITS-04250 | Fiber Optic Drop Cable, SM, 12 Strand, Furnish & Install | 210 | LNFT | 6.00 | 1,260.00 | 9.00 | 1,890.00 | 7.00 | 1,470.00 | | 0163 | NS-ITS-04290 | Fiber Optic Patch Cord, SM, 2 Strand, Furnish & Install | 2 | EACH | 65.00 | 130.00 | 89.00 | 178.00 | 70.00 | 140.00 | | 0164 | NS-ITS-04425 | Fiber Optic Connection Patch Panel, Outdoor, Furnish & Install | 1 | EACH | 900.00 | 900.00 | 1,286.00 | 1,286.00 | 900.00 | 900.00 | | 0165 | NS-ITS-06020 | Pullbox, In-ground, Furnish & Install (TYPE F) | 5 | EACH | 2,800.00 | 14,000.00 | 2,730.00 | 13,650.00 | 3,000.00 | 15,000.00 | | 0166 | NS-ITS-06020 | Pullbox, In-ground, Furnish & Install (TYPE K) | 1 | EACH | 7,500.00 | 7,500.00 | 6,048.00 | 6,048.00 | 8,000.00 | 8,000.00 | | 0168 | NS-ITS-06060 | Pullbox, In-ground, Install Adjusting and Cleaning Existing Pullbox | 4 | EACH | 4,200.00 | 16,800.00 | 1,685.00 | 6,740.00 | 4,000.00 | 16,000.00 | | 0169 | NS-ITS-07040 | ITS Controller Cabinet, Pole Mount, Install | 1 | EACH | 9,200.00 | 9,200.00 | 4,001.00 | 4,001.00 | 10,000.00 | 10,000.00 | | 0170 | NS-ITS-08062 | Pole & Lowering Device, >= 60', Install | 1 | EACH | 15,000.00 | 15,000.00 | 9,501.00 | 9,501.00 | 14,000.00 | 14,000.00 | | 0171 | NS-ITS-08240 | Lowering Device, Install | 1 | EACH | 1,200.00 | 1,200.00 | 9,717.00 | 9,717.00 | 1,200.00 | 1,200.00 | | 0172 | NS-ITS-10060 | Electrical Service (MODIFICATION TO EXISTING SERVICE DISCONNECT) | 1 | EACH | 2,700.00 | 2,700.00 | 2,892.00 | 2,892.00 | 2,800.00 | 2,800.00 | | 0173 | NS-ITS-10401 | Power Surge Protector, Furnish & Install | 2 | EACH | 250.00 | 500.00 | 314.00 | 628.00 | 250.00 | 500.00 | | 0174 | NS-ITS-10407 | Data Surge Protector, Furnish & Install | 2 | EACH | 265.00 | 530.00 | 407.00 | 814.00 | 300.00 | 600.00 | | 0175 | NS-ITS-10410 | Power Surge Protector (ITS Cabinet), Furnish & Install | 1 | EACH | 1,000.00 | 1,000.00 | 1,429.00 | 1,429.00 | 1,100.00 | 1,100.00 | | 0176 | NS-ITS-12000 | Communications System Integration | 1 | LUMP | 13,000.00 | 13,000.00 | 17,319.00 | 17,319.00 | 14,000.00 | 14,000.00 | | 0177 | NS-ITS-12020 | TMC Integration | 1 | LUMP | 20,000.00 | 20,000.00 | 27,122.00 | 27,122.00 | 21,000.00 | 21,000.00 | | 0178 | NS-ITS-13200 | As-Builts | 1 | LUMP | 12,000.00 | 12,000.00 | 9,984.00 | 9,984.00 | 11,000.00 | 11,000.00 | | 0179 | NS-ITS-16002 | Power Distribution Unit, Rackmount, Furnish and Install | 1 | EACH | 2,300.00 | 2,300.00 | 1,858.00 | 1,858.00 | 2,500.00 | 2,500.00 | | 0187 | 805-01-01000 | Class A1 Concrete (Headwalls) 36" Cross Drain Pipe @ 90° skew | 6.08 | CUYD | 4,500.00 | 27,360.00 | 4,238.00 | 25,767.04 | 4,000.00 | 24,320.00 | | 0188 | 805-01-01000 | Class A1 Concrete (Headwalls) 24" Cross Drain Pipe @ 90° skew | 3.8 | CUYD | 4,500.00 | 17,100.00 | 4,238.00 | 16,104.40 | 4,000.00 | 15,200.00 | | 0189 | 805-01-01000 | Class A1 Concrete (Headwalls) 2-24" Cross Drain Pipe @ 75° skew | 4.77 | CUYD | 4,500.00 | 21,465.00 | 4,238.00 | 20,215.26 | 4,000.00 | 19,080.00 | | 0190 | 805-01-01000 | Class A1 Concrete (Headwalls) 36" Cross Drain Pipe @ 60° skew | 7.01 | CUYD | 4,500.00 | 31,545.00 | 4,238.00 | 29,708.38 | 4,000.00 | 28,040.00 | | 0191 | 805-01-01000 | Class A1 Concrete (Headwalls) 4-36" Cross Drain Pipe @ 75° skew "Sta. 246+08" | 10 | CUYD | 4,500.00 | 45,000.00 | 4,238.00 | 42,380.00 | 4,700.00 | 47,000.00 | | 0192 | 805-01-01000 | Class A1 Concrete (Headwalls) 3-36" Cross Drain Pipe @ 75° skew | 8.78 | CUYD | 4,600.00 | 40,388.00 | 4,434.00 | 38,930.52 | 4,900.00 | 43,022.00 | | 0193 | 805-01-01000 | Class A1 Concrete (Headwalls) 4-36" Cross Drain Pipe @ 75° skew "Sta. 295+98" | 10 | CUYD | 4,600.00 | 46,000.00 | 4,410.00 | 44,100.00 | 4,900.00 | 49,000.00 | | 0194 | 805-01-01000 | Class A1 Concrete (Headwalls) 3-36" Cross Drain Pipe @ 45° skew | 11.93 | CUYD | 4,500.00 | 53,685.00 | 4,383.00 | 52,289.19 | 4,900.00 | 58,457.00 | | 0195 | 805-16-02700 | Reinforced Concrete Box Culverts (Extension) (8' x 7') | 248 | LNFT | 1,500.00 | 372,000.00 | 1,580.00 | 391,840.00 | 1,500.00 | 372,000.00 | | 0196 | 805-17-00100 | Reinforced Concrete Box Culvert Headwall 2-8' x 7' @ 45° skew: steel quantity = 1,310 LB; concrete quantity = 19.91 CUYD | 1 | EACH | 55,000.00 | 55,000.00 | 49,338.00 | 49,338.00 | 55,000.00 | 55,000.00 | | 0197 | 805-17-00100 | Reinforced Concrete Box Culvert Headwall 2-6' x 6' @ 45° skew: steel quantity = 1,521 LB; concrete quantity = 13.71 CUYD | 1 | EACH | 45,000.00 | 45,000.00 | 42,586.00 | 42,586.00 | 48,000.00 | 48,000.00 | | 0198 | 805-17-00100 | Reinforced Concrete Box Culvert Headwall 3-5' x 5' @ 75° skew: steel quantity = 797 LB; concrete quantity = 8.82 CUYD | 1 | EACH | 38,000.00 | 38,000.00 | 35,426.00 | 35,426.00 | 40,000.00 | 40,000.00 | | 0199 | 805-17-00100 | Reinforced Concrete Box Culvert Headwall 3-5' x 5' @ 90° skew: steel quantity = 519 LB; concrete quantity = 7.56 CUYD | 1 | EACH | 35,000.00 | 35,000.00 | 33,580.00 | 33,580.00 | 38,000.00 | 38,000.00 | | 0200 | 805-17-00100 | Reinforced Concrete Box Culvert Headwall 3-6' x 4' @ 90° skew: steel quantity = 452 LB; concrete quantity = 6.21 CUYD | 1 | EACH | 35,000.00 | 35,000.00 | 32,659.00 | 32,659.00 | 37,000.00 | 37,000.00 | | 0201 | 805-17-00100 | Reinforced Concrete Box Culvert Headwall 6-4' x 4' @ 75° skew: steel quantity = 941 LB; concrete quantity = 8.82 CUYD | 1 | EACH | 38,000.00 | 38,000.00 | 37,378.00 | 37,378.00 | 42,000.00 | 42,000.00 | | 0202 | 805-17-00100 | Reinforced Concrete Box Culvert Headwall 5-5' x 5' @ 75° skew: steel quantity = 1,108 LB; concrete quantity = 11.13 CUYD | 1 | EACH | 42,000.00 | 42,000.00 | 39,065.00 | 39,065.00 | 44,000.00 | 44,000.00 | | 0203 | 805-17-00100 | Reinforced Concrete Box Culvert Headwall 4-4' x 4' @ 75° skew: steel quantity = 697 LB; concrete quantity = 7.54 CUYD | 1 | EACH | 42,000.00 | 42,000.00 | 35,679.00 | 35,679.00 | 40,000.00 | 40,000.00 | | 0205 | 713-07-00100 | Temporary Precast Concrete Barrier (Contractor Furnished) | 176 | EACH | 700.00 | 123,200.00 | 500.00 | 88,000.00 | 1,700.00 | 299,200.00 | | 0206 | 713-10-00100 | Temporary Precast Concrete Barrier Movement | 67 | EACH | 200.00 | 13,400.00 | 150.00 | 10,050.00 | 225.00 | 15,075.00 | | | | SUBTOTAL GENERAL | | | | 41,625,104 | | 47,496,110 | | 45,297,219 | | | | | | | | | | | | | | | Alternate AA1 | Alternate AA1 (Asphalt Concrete) | | | | | | | | | | | | | | | | | | | | | | 0181 | 502-01-00100 | Asphalt Concrete | 49,488.3 | TON | 130.00 | 6,433,479.00 | 101.00 | 4,998,318.30 | 130.00 | 6,433,479.00 | | 0182 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 257.9 | TON | 200.00 | 51,580.00 | 225.00 | 58,027.50 | 200.00 | 51,580.00 | | 0183 | 502-04-00100 | Asphalt Concrete (SMA) Wearing Course | 11,839.7 | TON | 175.00 | 2,071,947.50 | 156.00 | 1,846,993.20 | 160.00 | 1,894,352.00 | | | | SUBTOTAL ALT AA1 | | | | 8,557,006.50 | | 6,903,339.00 | | 8,379,411.00 | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 50,182,110.02 | | 54,399,449.34 | | 53,676,629.71 |
|