Bid Tabulations for the Letting of 12/7/2022 LA DOTD Headquarters

Proposal:H.013346.6
Parish:Jefferson
Description:MANHATTAN BLVD. PEDESTRIAN IMPROVEMENTS
Type Construction:CLEARING AND GRUBBING, CONCRETE SIDEWALKS, AND RELATED WORK.
Estimated Construction Cost:$1,749,483.75
Rank License BidderConstruction Bid
100046Barber Bros. Contracting Co., L.L.C$1,337,004.65
234263La Contracting Enterprise LLC$1,488,753.30
354663CAPE Construction, LLC$1,517,638.40
428190Buck Town Contractors & Co.$1,529,585.20
549356KORT's CONSTRUCTION SERVICES, INC.$1,574,966.95
670108LMB Services, LLC$1,686,753.09
770414Ti-Zack Concrete, Inc.$1,752,175.84
846747Triumph Construction, LLC$1,765,100.00
924901Hard Rock Construction LLC$1,996,203.15
1055950Brown Industrial Construction, LLC$2,881,676.63


Line
Number
Item NumberItem DescriptionQuantityUnit of
Measure
- 1 -
Barber Bros. Contracting Co., L.L.C
- 2 -
La Contracting Enterprise LLC
- 3 -
CAPE Construction, LLC
- 4 -
Buck Town Contractors & Co.
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001201-01-00100Clearing and Grubbing 1     LUMP20,000.0020,000.002,000.002,000.0030,000.0030,000.0029,200.0029,200.00
0002202-02-00020Removal of Concrete Walks and Drives5,075     SQYD25.00126,875.0030.00152,250.0033.00167,475.0015.0076,125.00
0003202-02-14500Removal of Guard Rail 299.65  LNFT13.003,895.4530.008,989.5013.804,135.1710.002,996.50
0004202-03-00010Relocation (Sign and Pole)13     EACH160.002,080.00240.003,120.001,500.0019,500.00130.001,690.00
0005704-03-00100Blocked Out Guard rail 100     LNFT42.004,200.00104.0010,400.00250.0025,000.0060.006,000.00
0006704-10-00205Guard Rail End Treatment, MASH, (TL-3 Tangent) 5     EACH4,250.0021,250.006,000.0030,000.003,762.7718,813.854,250.0021,250.00
0007706-01-00100Concrete Walk (4" Thick) 7,832.3   SQYD67.00524,764.10100.00783,230.0069.20541,995.1679.00618,751.70
0008706-02-00300Concrete Drive (8" Thick) 1,733.6   SQYD120.00208,032.00125.00216,700.00110.48191,528.13115.00199,364.00
0009706-03-00300Incidental Concrete Paving (6" Thick) 27.9   SQYD130.003,627.00140.003,906.00105.002,929.50150.004,185.00
0010706-04-00100Handicapped Curb Ramps Type 18     EACH2,500.0020,000.001,650.0013,200.003,000.0024,000.003,950.0031,600.00
0011706-04-00100Handicapped Curb Ramps Type 104     EACH3,000.0012,000.001,650.006,600.003,178.0012,712.003,700.0014,800.00
0012706-04-00100Handicapped Curb Ramps Type 29     EACH3,000.0027,000.001,700.0015,300.002,887.5025,987.503,450.0031,050.00
0013706-04-00100Handicapped Curb Ramps Type 510     EACH3,000.0030,000.001,700.0017,000.002,650.0026,500.004,350.0043,500.00
0014706-04-00100Handicapped Curb Ramps Type 61     EACH3,000.003,000.001,900.001,900.002,900.002,900.004,100.004,100.00
0015706-04-00100Handicapped Curb Ramps Type 746     EACH2,500.00115,000.001,700.0078,200.003,301.29151,859.343,650.00167,900.00
0016707-01-00100Concrete Curb 47.5   LNFT75.003,562.5072.003,420.0092.504,393.7540.001,900.00
0017713-01-00100Temporary Signs and Barricades 1     LUMP80,000.0080,000.0045,000.0045,000.0075,000.0075,000.00129,000.00129,000.00
0018727-01-00100Mobilization 1     LUMP80,000.0080,000.0046,000.0046,000.00120,000.00120,000.0084,400.0084,400.00
0019740-01-00100Construction Layout 1     LUMP15,000.0015,000.0023,000.0023,000.0060,000.0060,000.0024,000.0024,000.00
0020NS-600-00220Saw Cutting Portland Cement Concrete Pavement 362.4   INLF1.50543.602.00724.8010.003,624.005.001,812.00
0021TS-700-04000Drainage Grates (Replacement) (Furnish & Install)9     EACH3,000.0027,000.001,500.0013,500.00420.003,780.002,650.0023,850.00
0022TS-800-00210Safety Rail (Furnished and Installed) (Over Drainage Ditch)36.7   LNFT250.009,175.00390.0014,313.00150.005,505.00330.0012,111.00
             
  CONTRACTOR TOTAL   1,337,004.65 1,488,753.30 1,517,638.40 1,529,585.20



Line
Number
Item NumberItem DescriptionQuantityUnit of
Measure
- 5 -
KORT's CONSTRUCTION SERVICES, INC.
- 6 -
LMB Services, LLC
- 7 -
Ti-Zack Concrete, Inc.
- 8 -
Triumph Construction, LLC
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001201-01-00100Clearing and Grubbing 1     LUMP90,000.0090,000.00125,000.00125,000.0022,000.0022,000.0071,500.0071,500.00
0002202-02-00020Removal of Concrete Walks and Drives5,075     SQYD35.00177,625.0025.00126,875.0023.72120,379.0023.00116,725.00
0003202-02-14500Removal of Guard Rail 299.65  LNFT13.003,895.45115.0034,459.7522.006,592.3018.005,393.70
0004202-03-00010Relocation (Sign and Pole)13     EACH175.002,275.002,000.0026,000.00148.501,930.50238.253,097.25
0005704-03-00100Blocked Out Guard rail 100     LNFT40.004,000.0075.007,500.0082.508,250.0051.455,145.00
0006704-10-00205Guard Rail End Treatment, MASH, (TL-3 Tangent) 5     EACH4,000.0020,000.003,500.0017,500.004,950.0024,750.004,484.0022,420.00
0007706-01-00100Concrete Walk (4" Thick) 7,832.3   SQYD75.00587,422.5082.00642,248.60120.20941,442.4692.70726,054.21
0008706-02-00300Concrete Drive (8" Thick) 1,733.6   SQYD110.00190,696.00100.00173,360.00144.43250,383.85120.50208,898.80
0009706-03-00300Incidental Concrete Paving (6" Thick) 27.9   SQYD105.002,929.50100.002,790.00105.452,942.06242.006,751.80
0010706-04-00100Handicapped Curb Ramps Type 18     EACH2,900.0023,200.001,275.0010,200.001,358.2110,865.683,252.0026,016.00
0011706-04-00100Handicapped Curb Ramps Type 104     EACH4,000.0016,000.001,275.005,100.001,358.215,432.843,242.0012,968.00
0012706-04-00100Handicapped Curb Ramps Type 29     EACH2,900.0026,100.001,275.0011,475.001,358.2112,223.893,236.0029,124.00
0013706-04-00100Handicapped Curb Ramps Type 510     EACH2,900.0029,000.001,275.0012,750.001,358.2113,582.103,231.0032,310.00
0014706-04-00100Handicapped Curb Ramps Type 61     EACH2,900.002,900.001,275.001,275.001,358.211,358.213,375.003,375.00
0015706-04-00100Handicapped Curb Ramps Type 746     EACH3,000.00138,000.001,275.0058,650.001,358.2162,477.663,232.00148,672.00
0016707-01-00100Concrete Curb 47.5   LNFT35.001,662.50185.008,787.5077.353,674.1372.003,420.00
0017713-01-00100Temporary Signs and Barricades 1     LUMP75,000.0075,000.00116,000.00116,000.0055,000.0055,000.0080,000.0080,000.00
0018727-01-00100Mobilization 1     LUMP95,000.0095,000.00168,000.00168,000.00144,482.52144,482.52172,304.22172,304.22
0019740-01-00100Construction Layout 1     LUMP24,000.0024,000.00116,284.92116,284.9244,000.0044,000.0063,000.0063,000.00
0020NS-600-00220Saw Cutting Portland Cement Concrete Pavement 362.4   INLF2.50906.001.80652.321.10398.644.801,739.52
0021TS-700-04000Drainage Grates (Replacement) (Furnish & Install)9     EACH4,500.0040,500.001,000.009,000.001,000.009,000.001,625.0014,625.00
0022TS-800-00210Safety Rail (Furnished and Installed) (Over Drainage Ditch)36.7   LNFT650.0023,855.00350.0012,845.00300.0011,010.00315.0011,560.50
             
  CONTRACTOR TOTAL   1,574,966.95 1,686,753.09 1,752,175.84 1,765,100.00



Line
Number
Item NumberItem DescriptionQuantityUnit of
Measure
- 9 -
Hard Rock Construction LLC
- 10 -
Brown Industrial Construction, LLC
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001201-01-00100Clearing and Grubbing 1     LUMP59,000.0059,000.0050,000.0050,000.00
0002202-02-00020Removal of Concrete Walks and Drives5,075     SQYD38.00192,850.0050.00253,750.00
0003202-02-14500Removal of Guard Rail 299.65  LNFT15.004,494.7521.006,292.65
0004202-03-00010Relocation (Sign and Pole)13     EACH177.002,301.00262.003,406.00
0005704-03-00100Blocked Out Guard rail 100     LNFT45.004,500.0066.006,600.00
0006704-10-00205Guard Rail End Treatment, MASH, (TL-3 Tangent) 5     EACH4,400.0022,000.006,537.0032,685.00
0007706-01-00100Concrete Walk (4" Thick) 7,832.3   SQYD113.00885,049.90122.25957,498.68
0008706-02-00300Concrete Drive (8" Thick) 1,733.6   SQYD161.00279,109.60228.00395,260.80
0009706-03-00300Incidental Concrete Paving (6" Thick) 27.9   SQYD180.005,022.00464.0012,945.60
0010706-04-00100Handicapped Curb Ramps Type 18     EACH3,000.0024,000.006,470.0051,760.00
0011706-04-00100Handicapped Curb Ramps Type 104     EACH3,000.0012,000.008,114.0032,456.00
0012706-04-00100Handicapped Curb Ramps Type 29     EACH3,000.0027,000.005,206.0046,854.00
0013706-04-00100Handicapped Curb Ramps Type 510     EACH3,000.0030,000.003,812.0038,120.00
0014706-04-00100Handicapped Curb Ramps Type 61     EACH3,000.003,000.003,650.003,650.00
0015706-04-00100Handicapped Curb Ramps Type 746     EACH3,000.00138,000.006,622.00304,612.00
0016707-01-00100Concrete Curb 47.5   LNFT75.003,562.50500.0023,750.00
0017713-01-00100Temporary Signs and Barricades 1     LUMP85,000.0085,000.00225,000.00225,000.00
0018727-01-00100Mobilization 1     LUMP179,000.00179,000.00280,000.00280,000.00
0019740-01-00100Construction Layout 1     LUMP10,000.0010,000.00125,000.00125,000.00
0020NS-600-00220Saw Cutting Portland Cement Concrete Pavement 362.4   INLF3.501,268.403.501,268.40
0021TS-700-04000Drainage Grates (Replacement) (Furnish & Install)9     EACH1,800.0016,200.002,705.0024,345.00
0022TS-800-00210Safety Rail (Furnished and Installed) (Over Drainage Ditch)36.7   LNFT350.0012,845.00175.006,422.50
         
  CONTRACTOR TOTAL   1,996,203.15 2,881,676.63