Proposal:H.006538.6
Parish:Lafayette
Description:LAFAYETTE CONSOLIDATED GOVT SIDEWALKS
Type Construction:CLEARING AND GRUBBING, GRADING, DRAINAGE STRUCTURES, CONCRETE WALKS, AND RELATED WORK.
Estimated Construction Cost:$950,689.50
| Rank | License | Bidder | Construction Bid |
| 1 | 30774 | Progressive Construction Co., LLC | $1,559,931.10 |
| 2 | 46747 | Triumph Construction, LLC | $1,763,000.00 |
| 3 | 54663 | CAPE Construction, LLC | $1,949,835.85 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Progressive Construction Co., LLC | - 2 - Triumph Construction, LLC | - 3 - CAPE Construction, LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 201-01-00100 | Clearing and Grubbing | 2 | LUMP | 7,500.00 | 7,500.00 | 23,050.00 | 23,050.00 | 5,000.00 | 5,000.00 | | 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 6,500.00 | 6,500.00 | 23,050.00 | 23,050.00 | 10,000.00 | 10,000.00 | | 0003 | 202-02-06060 | Removal of Concrete Catch Basin | 1 | EACH | 1,750.00 | 1,750.00 | 4,610.00 | 4,610.00 | 1,200.00 | 1,200.00 | | 0004 | 202-02-06100 | Removal of Concrete Walks and Drives | 1,958 | SQYD | 14.00 | 27,412.00 | 24.90 | 48,754.20 | 29.22 | 57,212.76 | | 0005 | 202-02-06140 | Removal of Curbs (Concrete) | 90 | LNFT | 18.60 | 1,674.00 | 52.50 | 4,725.00 | 32.12 | 2,890.80 | | 0006 | 202-02-12020 | Removal of Fence (Chain Link) | 257 | LNFT | 12.00 | 3,084.00 | 53.40 | 13,723.80 | 35.66 | 9,164.62 | | 0007 | 202-02-32120 | Removal of Pipe (Side Drain) (15" - 24")(RCP - RCPA) | 589 | LNFT | 28.50 | 16,786.50 | 50.55 | 29,773.95 | 110.49 | 65,078.61 | | 0008 | 202-03-00010 | Relocation (Large Multi-Mailbox Cabinet) | 4 | EACH | 1,500.00 | 6,000.00 | 2,670.00 | 10,680.00 | 1,500.00 | 6,000.00 | | 0009 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 112,000.00 | 112,000.00 | 69,400.00 | 69,400.00 | 35,000.00 | 35,000.00 | | 0010 | 204-02-00100 | Temporary Hay Bales | 60 | EACH | 40.00 | 2,400.00 | 38.00 | 2,280.00 | 50.92 | 3,055.20 | | 0011 | 204-06-00100 | Temporary Silt Fencing | 5,058 | LNFT | 5.00 | 25,290.00 | 3.10 | 15,679.80 | 13.03 | 65,905.74 | | 0012 | 402-03-00100 | Non-Mainline Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) | 466 | CUYD | 145.00 | 67,570.00 | 82.15 | 38,281.90 | 180.92 | 84,308.72 | | 0013 | 701-03-01002 | Storm Drain Pipe (15" RCP/RPVCP) | 259 | LNFT | 85.00 | 22,015.00 | 112.00 | 29,008.00 | 207.80 | 53,820.20 | | 0014 | 701-03-01022 | Storm Drain Pipe (18" RCP/RPVCP) | 529 | LNFT | 90.00 | 47,610.00 | 112.00 | 59,248.00 | 160.92 | 85,126.68 | | 0015 | 701-03-01042 | Storm Drain Pipe (24" RCP/RPVCP) | 77 | LNFT | 105.00 | 8,085.00 | 150.00 | 11,550.00 | 180.76 | 13,918.52 | | 0016 | 701-04-01040 | Storm Drain Pipe Arch (24" Equiv. RCPA) | 962 | LNFT | 140.00 | 134,680.00 | 187.00 | 179,894.00 | 200.72 | 193,092.64 | | 0017 | 701-10-01040 | Reinforced Concrete Pipe (Extension) (18") | 18 | LNFT | 285.00 | 5,130.00 | 190.00 | 3,420.00 | 278.32 | 5,009.76 | | 0018 | 701-10-01060 | Reinforced Concrete Pipe (Extension) (24") | 12 | LNFT | 250.00 | 3,000.00 | 230.00 | 2,760.00 | 300.23 | 3,602.76 | | 0019 | 701-11-01020 | Reinforced Concrete Pipe Arch (Extension) (18" Equiv.) | 12 | LNFT | 250.00 | 3,000.00 | 190.00 | 2,280.00 | 288.19 | 3,458.28 | | 0020 | 701-15-00100 | Concrete Collar | 5 | EACH | 1,550.00 | 7,750.00 | 3,550.00 | 17,750.00 | 2,561.18 | 12,805.90 | | 0021 | 702-02-00100 | Manholes (MH-06) | 2 | EACH | 5,000.00 | 10,000.00 | 5,610.00 | 11,220.00 | 6,734.54 | 13,469.08 | | 0022 | 702-03-00100 | Catch Basins (CB-01) | 30 | EACH | 5,100.00 | 153,000.00 | 5,540.00 | 166,200.00 | 5,585.69 | 167,570.70 | | 0023 | 702-04-00200 | Adjusting Catch Basins 1965 | 2 | EACH | 4,900.00 | 9,800.00 | 2,515.00 | 5,030.00 | 8,656.89 | 17,313.78 | | 0024 | 705-05-00100 | Double Swinging Driveway Gates | 1 | DBGT | 1,800.00 | 1,800.00 | 2,330.00 | 2,330.00 | 1,832.23 | 1,832.23 | | 0025 | 705-06-00100 | Chain Link Fence (4-Foot Height) | 215 | LNFT | 41.00 | 8,815.00 | 77.00 | 16,555.00 | 38.70 | 8,320.50 | | 0026 | 706-01-00100 | Concrete Walk (4" Thick) | 3,380.3 | SQYD | 78.00 | 263,663.40 | 78.40 | 265,015.52 | 72.06 | 243,584.42 | | 0027 | 706-02-00200 | Concrete Drive (6" Thick) | 1,762.5 | SQYD | 110.00 | 193,875.00 | 99.40 | 175,192.50 | 95.40 | 168,142.50 | | 0028 | 706-04-00100 | Handicapped Curb Ramps (Type 10) | 1 | EACH | 2,600.00 | 2,600.00 | 3,271.00 | 3,271.00 | 3,584.53 | 3,584.53 | | 0029 | 706-04-00100 | Handicapped Curb Ramps (Type 2) | 7 | EACH | 2,275.00 | 15,925.00 | 3,015.00 | 21,105.00 | 3,500.00 | 24,500.00 | | 0030 | 706-04-00100 | Handicapped Curb Ramps (Type 7) | 19 | EACH | 2,300.00 | 43,700.00 | 3,006.00 | 57,114.00 | 3,000.00 | 57,000.00 | | 0031 | 706-04-00100 | Handicapped Curb Ramps (Type 8) | 1 | EACH | 2,560.00 | 2,560.00 | 3,143.00 | 3,143.00 | 3,200.00 | 3,200.00 | | 0032 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 33,000.00 | 33,000.00 | 77,250.00 | 77,250.00 | 125,000.00 | 125,000.00 | | 0033 | 714-01-00600 | Slab Sodding (St. Augustine) | 2,674 | SQYD | 10.00 | 26,740.00 | 18.60 | 49,736.40 | 16.54 | 44,227.96 | | 0034 | 726-01-00100 | Bedding Material | 407.3 | CUYD | 114.00 | 46,432.20 | 126.80 | 51,645.64 | 90.14 | 36,714.02 | | 0035 | 727-01-00100 | Mobilization | 1 | LUMP | 150,000.00 | 150,000.00 | 140,547.09 | 140,547.09 | 200,000.00 | 200,000.00 | | 0036 | 729-01-00103 | Sign (Type A)(Relocate) | 63 | SQFT | 135.00 | 8,505.00 | 17.20 | 1,083.60 | 150.32 | 9,470.16 | | 0037 | 729-21-00100 | U-Channel Post | 10 | EACH | 129.50 | 1,295.00 | 171.30 | 1,713.00 | 183.87 | 1,838.70 | | 0038 | 735-01-00100 | Mailboxes | 26 | EACH | 1.50 | 39.00 | 28.60 | 743.60 | 300.75 | 7,819.50 | | 0039 | 735-02-00100 | Mailbox Supports (Single) | 26 | EACH | 300.00 | 7,800.00 | 257.00 | 6,682.00 | 275.26 | 7,156.76 | | 0040 | 740-01-00100 | Construction Layout | 1 | LUMP | 15,000.00 | 15,000.00 | 18,500.00 | 18,500.00 | 40,000.00 | 40,000.00 | | 0041 | 741-06-00100 | Relocating Fire Hydrant | 1 | EACH | 8,000.00 | 8,000.00 | 4,500.00 | 4,500.00 | 2,500.00 | 2,500.00 | | 0042 | 741-11-00100 | Adjusting Water Valve | 4 | EACH | 850.00 | 3,400.00 | 1,000.00 | 4,000.00 | 1,726.38 | 6,905.52 | | 0043 | NS-700-00100 | Trench Drains | 7 | EACH | 3,735.00 | 26,145.00 | 3,950.00 | 27,650.00 | 2,847.70 | 19,933.90 | | 0044 | NS-719-00002 | Tree Trimming | 1 | LUMP | 7,500.00 | 7,500.00 | 27,125.00 | 27,125.00 | 5,000.00 | 5,000.00 | | 0045 | NS-719-00003 | Root Pruning | 1 | LUMP | 7,500.00 | 7,500.00 | 27,125.00 | 27,125.00 | 6,000.00 | 6,000.00 | | 0046 | NS-719-00005 | Gravel Bed and Filter Cloth over Tree Roots | 120 | SQYD | 30.00 | 3,600.00 | 71.70 | 8,604.00 | 109.17 | 13,100.40 | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 1,559,931.10 | | 1,763,000.00 | | 1,949,835.85 |
|