Proposal:H.014490.6
Parish:St. Tammany
Routes:US 190
Description:US 190: LA 433 - US 11
Type Construction:MILLING ASPHALT CONCRETE, ASPHALT CONCRETE OVERLAY, TRAFFIC SIGNALIZATION, AND RELATED WORK
Estimated Construction Cost:$2,745,168.00
| Rank | License | Bidder | Construction Bid |
| 1 | 02179 | Boh Bros. Construction Co., LLC. | $3,135,512.99 |
| 2 | 62139 | Huey P. Stockstill, LLC | $4,287,954.47 |
| 3 | 06276 | Barriere Construction Co., LLC | $4,493,352.75 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Boh Bros. Construction Co., LLC. | - 2 - Huey P. Stockstill, LLC | - 3 - Barriere Construction Co., LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 202-02-06100 | Removal of Concrete Walks and Drives | 36 | SQYD | 50.00 | 1,800.00 | 30.00 | 1,080.00 | 85.00 | 3,060.00 | | 0002 | 202-02-14500 | Removal of Guard Rail | 1,561 | LNFT | 8.00 | 12,488.00 | 20.00 | 31,220.00 | 10.00 | 15,610.00 | | 0003 | 202-02-38300 | Removal of Sign and U-Channel Post | 12 | EACH | 85.00 | 1,020.00 | 13.00 | 156.00 | 90.00 | 1,080.00 | | 0004 | 203-07-00100 | Borrow (Vehicular Measurement) | 821 | CUYD | 10.00 | 8,210.00 | 50.00 | 41,050.00 | 70.00 | 57,470.00 | | 0005 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 12 | EACH | 150.00 | 1,800.00 | 165.00 | 1,980.00 | 230.00 | 2,760.00 | | 0006 | 204-06-00100 | Temporary Silt Fencing | 9,876 | LNFT | 1.00 | 9,876.00 | 2.00 | 19,752.00 | 2.00 | 19,752.00 | | 0007 | 502-01-00100 | Asphalt Concrete | 17,345.7 | TON | 95.00 | 1,647,841.50 | 115.00 | 1,994,755.50 | 140.00 | 2,428,398.00 | | 0008 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 1,711.7 | TON | 95.00 | 162,611.50 | 215.00 | 368,015.50 | 140.00 | 239,638.00 | | 0009 | 509-01-00100 | Milling Asphalt Pavement | 90,840 | SQYD | 3.50 | 317,940.00 | 3.50 | 317,940.00 | 4.50 | 408,780.00 | | 0010 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -7,453 | CUYD | 0.20 | -1,490.60 | 0.01 | -74.53 | 0.01 | -74.53 | | 0011 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 209 | SQYD | 140.00 | 29,260.00 | 136.00 | 28,424.00 | 120.00 | 25,080.00 | | 0012 | 602-02-00200 | Cleaning and Resealing Existing Longitudinal Pavement Joints | 705 | LNFT | 5.00 | 3,525.00 | 8.00 | 5,640.00 | 4.00 | 2,820.00 | | 0013 | 602-02-00300 | Cleaning and Resealing Existing Transverse Pavements Joints | 295 | LNFT | 5.00 | 1,475.00 | 11.00 | 3,245.00 | 4.00 | 1,180.00 | | 0014 | 602-08-00100 | Diamond Grinding Concrete Pavement | 100 | SQYD | 25.00 | 2,500.00 | 35.00 | 3,500.00 | 34.50 | 3,450.00 | | 0015 | 704-01-01000 | Guard Rail (Single Thrie Beam) (3'-1 1/2" post spacing) | 108 | LNFT | 125.00 | 13,500.00 | 170.00 | 18,360.00 | 140.00 | 15,120.00 | | 0016 | 704-01-01020 | Guard Rail (Single Thrie Beam) (6'-3" post spacing) | 664 | LNFT | 60.00 | 39,840.00 | 80.00 | 53,120.00 | 65.00 | 43,160.00 | | 0017 | 704-03-00200 | Blocked Out Guard Rail - 31", (6'-3" Post Spacing) | 343.8 | LNFT | 40.00 | 13,752.00 | 38.00 | 13,064.40 | 40.00 | 13,752.00 | | 0018 | 704-07-00200 | Guard Rail Transitions (Double Thrie Beam) | 200 | LNFT | 125.00 | 25,000.00 | 155.00 | 31,000.00 | 140.00 | 28,000.00 | | 0019 | 704-10-00310 | Guard Rail End Treatment, NCHRP 350 - 31" (TL-3 Flared) | 10 | EACH | 3,400.00 | 34,000.00 | 4,000.00 | 40,000.00 | 3,800.00 | 38,000.00 | | 0020 | 707-01-00100 | Concrete Curb | 135 | LNFT | 55.00 | 7,425.00 | 85.00 | 11,475.00 | 100.00 | 13,500.00 | | 0021 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 100,000.00 | 100,000.00 | 297,000.00 | 297,000.00 | 425,000.00 | 425,000.00 | | 0022 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 8,512 | LNFT | 1.00 | 8,512.00 | 1.00 | 8,512.00 | 0.60 | 5,107.20 | | 0023 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 3,714 | LNFT | 2.00 | 7,428.00 | 1.50 | 5,571.00 | 1.15 | 4,271.10 | | 0024 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 20.773 | MILE | 80.00 | 1,661.84 | 200.00 | 4,154.60 | 74.00 | 1,537.20 | | 0025 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 14.515 | MILE | 650.00 | 9,434.75 | 800.00 | 11,612.00 | 862.00 | 12,511.93 | | 0026 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 40.045 | MILE | 1,700.00 | 68,076.50 | 1,600.00 | 64,072.00 | 1,500.00 | 60,067.50 | | 0027 | 713-05-00190 | Temporary Pavement Legends & Symbols (Arrow - Straight) | 6 | EACH | 25.00 | 150.00 | 125.00 | 750.00 | 115.00 | 690.00 | | 0028 | 713-05-00200 | Temporary Pavement Legends & Symbols (Arrow - Double) | 6 | EACH | 25.00 | 150.00 | 125.00 | 750.00 | 115.00 | 690.00 | | 0029 | 713-05-00220 | Temporary Pavement Legends & Symbols (Arrow - Left Turn) | 141 | EACH | 25.00 | 3,525.00 | 60.00 | 8,460.00 | 57.50 | 8,107.50 | | 0030 | 713-05-00230 | Temporary Pavement Legends & Symbols (Arrow - Right Turn) | 114 | EACH | 25.00 | 2,850.00 | 60.00 | 6,840.00 | 57.50 | 6,555.00 | | 0031 | 713-05-00240 | Temporary Pavement Legends & Symbols (Arrow - Merge) | 6 | EACH | 25.00 | 150.00 | 125.00 | 750.00 | 115.00 | 690.00 | | 0032 | 713-05-00300 | Temporary Pavement Legends & Symbols (ONLY) | 12 | EACH | 25.00 | 300.00 | 60.00 | 720.00 | 57.50 | 690.00 | | 0033 | 713-05-00400 | Temporary Pavement Legends & Symbols (RR Crossing) | 12 | EACH | 25.00 | 300.00 | 125.00 | 1,500.00 | 115.00 | 1,380.00 | | 0034 | 724-01-00100 | Rumble Strips (Centerline) | 0.07 | MILE | 2,500.00 | 175.00 | 33,000.00 | 2,310.00 | 565.00 | 39.55 | | 0035 | 727-01-00100 | Mobilization | 1 | LUMP | 255,000.00 | 255,000.00 | 420,000.00 | 420,000.00 | 185,000.00 | 185,000.00 | | 0036 | 729-16-00300 | Object Marker Assembly (Type 3) | 12 | EACH | 80.00 | 960.00 | 120.00 | 1,440.00 | 90.00 | 1,080.00 | | 0037 | 731-02-00100 | Reflectorized Raised Pavement Markers | 1,641 | EACH | 12.00 | 19,692.00 | 13.00 | 21,333.00 | 12.00 | 19,692.00 | | 0038 | 732-01-02040 | Plastic Pavement Striping (8" Width) (Thermoplastic 125 mil) | 2,110 | LNFT | 4.25 | 8,967.50 | 8.00 | 16,880.00 | 7.00 | 14,770.00 | | 0039 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 1,278 | LNFT | 12.50 | 15,975.00 | 24.00 | 30,672.00 | 23.50 | 30,033.00 | | 0040 | 732-01-05000 | Plastic Pavement Striping (Dotted Line)(4" W)(2' L)(Thermo 125 mil) | 548 | LNFT | 1.50 | 822.00 | 3.00 | 1,644.00 | 3.00 | 1,644.00 | | 0041 | 732-01-05200 | Plastic Pavement Striping (Dotted Line)(8" W)(2' L)(Thermo 125 mil) | 1,127 | LNFT | 2.25 | 2,535.75 | 5.00 | 5,635.00 | 4.50 | 5,071.50 | | 0042 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 13.64 | MILE | 5,750.00 | 78,430.00 | 8,000.00 | 109,120.00 | 7,500.00 | 102,300.00 | | 0043 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 5.13 | MILE | 3,250.00 | 16,672.50 | 2,400.00 | 12,312.00 | 2,500.00 | 12,825.00 | | 0044 | 732-04-01020 | Plastic Pavement Legends and Symbols (Arrow - Straight) | 2 | EACH | 400.00 | 800.00 | 600.00 | 1,200.00 | 535.00 | 1,070.00 | | 0045 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 47 | EACH | 400.00 | 18,800.00 | 600.00 | 28,200.00 | 535.00 | 25,145.00 | | 0046 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 38 | EACH | 400.00 | 15,200.00 | 600.00 | 22,800.00 | 535.00 | 20,330.00 | | 0047 | 732-04-01120 | Plastic Pavement Legends and Symbols (Arrow - Merge) | 2 | EACH | 800.00 | 1,600.00 | 600.00 | 1,200.00 | 600.00 | 1,200.00 | | 0048 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 4 | EACH | 525.00 | 2,100.00 | 600.00 | 2,400.00 | 600.00 | 2,400.00 | | 0049 | 732-04-18000 | Plastic Pavement Legends and Symbols (RR Crossing) | 4 | EACH | 1,275.00 | 5,100.00 | 900.00 | 3,600.00 | 895.00 | 3,580.00 | | 0050 | 735-01-00100 | Mailboxes | 31 | EACH | 50.00 | 1,550.00 | 1.00 | 31.00 | 20.00 | 620.00 | | 0051 | 735-02-00100 | Mailbox Supports (Single) | 31 | EACH | 210.00 | 6,510.00 | 290.00 | 8,990.00 | 255.00 | 7,905.00 | | 0052 | 736-05-30000 | Signal Heads (3 Section, 12 inch Led Lens, R, Y, G) | 5 | EACH | 800.00 | 4,000.00 | 800.00 | 4,000.00 | 850.00 | 4,250.00 | | 0053 | 736-05-51000 | Signal Heads (5 Section, 12 inch Led Lens, R, LT. Y, Y, LT. G, G) | 1 | EACH | 1,200.00 | 1,200.00 | 1,200.00 | 1,200.00 | 1,200.00 | 1,200.00 | | 0054 | 736-05-55000 | Signal Heads (5 Section, 12 inch Led Lens, R, Y, RT. Y, G, RT. G) | 1 | EACH | 1,200.00 | 1,200.00 | 1,200.00 | 1,200.00 | 1,200.00 | 1,200.00 | | 0055 | 736-09-00100 | Loop Detector | 3,540 | LNFT | 32.00 | 113,280.00 | 35.00 | 123,900.00 | 34.00 | 120,360.00 | | 0056 | 736-10-00200 | Underground Junction Box (Type E) | 7 | EACH | 1,250.00 | 8,750.00 | 1,200.00 | 8,400.00 | 1,300.00 | 9,100.00 | | 0057 | 739-01-00100 | Hydro-Seeding | 1.7 | ACRE | 3,500.00 | 5,950.00 | 3,500.00 | 5,950.00 | 3,500.00 | 5,950.00 | | 0058 | 740-01-00100 | Construction Layout | 1 | LUMP | 10,000.00 | 10,000.00 | 50,000.00 | 50,000.00 | 25,000.00 | 25,000.00 | | 0059 | NS-500-00220 | Sawing and Sealing Longitudinal Joints in Asphalt Concrete Overlay | 705 | LNFT | 4.00 | 2,820.00 | 7.00 | 4,935.00 | 3.00 | 2,115.00 | | 0060 | NS-500-00240 | Sawing and Sealing Transverse Joints in Asphalt Concrete Overlay | 295 | LNFT | 4.25 | 1,253.75 | 10.00 | 2,950.00 | 3.00 | 885.00 | | 0061 | NS-500-00340 | Saw Cutting Asphalt Concrete Pavement | 389 | INLF | 2.00 | 778.00 | 2.00 | 778.00 | 1.20 | 466.80 | | 0062 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 240 | INLF | 2.00 | 480.00 | 2.00 | 480.00 | 1.20 | 288.00 | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 3,135,512.99 | | 4,287,954.47 | | 4,493,352.75 |
|