Bid Tabulations for the Letting of 3/9/2022 LA DOTD Headquarters

Proposal:H.014476.6
Parish:Richland
Routes:LA 135
Description:LA 135: LA 15 - ANTIOCH ROAD
Type Construction:CLEARING AND GRUBBING, GRADING, DRAINAGE STRUCTURES, MILLING ASPHALT CONCRETE, LIME TREATMENT, IN-PLACE CEMENT STABILIZED BASE COURSE, ASPHALT CONCRETE PAVEMENT, AND RELATED WORK.
Estimated Construction Cost:$3,696,018.55
Rank License BidderConstruction Bid
105789D & J CONSTRUCTION CO., LLC$3,658,920.00
212487Diamond B Construction Co., L.L.C.$4,319,896.83
312312GILCHRIST CONSTRUCTION COMPANY, LLC$4,980,478.95


Line
Number
Item NumberItem DescriptionQuantityUnit of
Measure
- 1 -
D & J CONSTRUCTION CO., LLC
- 2 -
Diamond B Construction Co., L.L.C.
- 3 -
GILCHRIST CONSTRUCTION COMPANY, LLC
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001201-01-00200Clearing and Grubbing (Selective) APPROX. 2.373 ACRES2.373 LUMP18,000.0018,000.0026,000.0026,000.0026,000.0026,000.00
0002202-02-02020Removal of Asphalt Pavement 17,777.8   SQYD2.0035,555.603.0053,333.404.0071,111.20
0003202-02-06100Removal of Concrete Walks and Drives 201     SQYD16.003,216.0015.003,015.0071.0014,271.00
0004202-02-32100Removal of Pipe (Cross Drain) 24" RCP44     LNFT18.00792.0025.001,100.0055.002,420.00
0005203-01-00100General Excavation 2,423     CUYD15.0036,345.0040.0096,920.0030.0072,690.00
0006203-07-00100Borrow (Vehicular Measurement) 19,755     CUYD18.00355,590.0032.00632,160.0034.50681,547.50
0007204-06-00100Temporary Silt Fencing 200     LNFT5.001,000.006.001,200.002.00400.00
0008303-01-00200In-Place Cement Stabilized Base Course (8-1/2" Thick) 71,138     SQYD10.00711,380.008.50604,673.0010.00711,380.00
0009303-02-00100Removal of Existing Patches 587     SQYD20.0011,740.0014.508,511.5018.0010,566.00
0010304-01-00100Lime 470.4   TON260.00122,304.00320.00150,528.00275.00129,360.00
0011304-05-00100Lime Treatment (Type E) 21,333     SQYD4.5095,998.503.5074,665.506.50138,664.50
0012401-02-00100Aggregate Surface Course (Adjusted Vehicular Measurement) 1,441     CUYD25.0036,025.00105.00151,305.0085.00122,485.00
0013402-01-00100Mainline Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) 100     CUYD95.009,500.00159.0015,900.00140.0014,000.00
0014402-03-00100Non-Mainline Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) 330.5   CUYD65.0021,482.50105.0034,702.5085.0028,092.50
0015502-01-00100Asphalt Concrete 12,796.4   TON120.001,535,568.00130.001,663,532.00134.001,714,717.60
0016502-01-00200Asphalt Concrete, Drives, Turnouts and Miscellaneous 1,062.5   TON120.00127,500.00230.00244,375.00248.00263,500.00
0017509-01-00100Milling Asphalt Pavement 29,099     SQYD3.0087,297.003.2594,571.753.75109,121.25
0018509-02-00100Contractor Retained Reclaimed Asphalt Pavement -1,206     CUYD1.00-1,206.000.10-120.601.00-1,206.00
0019701-02-01000Cross Drain Pipe Arch (24" Equiv. RCPA) 44     LNFT240.0010,560.00265.0011,660.00480.0021,120.00
0020701-08-00100Relaying Pipe 24" RCP8     LNFT210.001,680.00385.003,080.00400.003,200.00
0021701-15-00100Concrete Collar 2     EACH1,200.002,400.003,000.006,000.003,600.007,200.00
0022701-17-00100Trench Excavation Safety Protection (Depth >5 feet) 44     LNFT5.00220.003.00132.0075.003,300.00
0023706-02-00200Concrete Drive (6" Thick) 185.4   SQYD100.0018,540.00135.0025,029.00175.0032,445.00
0024713-01-00100Temporary Signs and Barricades 1     LUMP54,000.0054,000.0051,000.0051,000.0065,000.0065,000.00
0025713-03-01000Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) 13.924 MILE300.004,177.20175.002,436.70300.004,177.20
0026713-03-02000Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) 7.827 MILE700.005,478.90725.005,674.581,000.007,827.00
0027713-04-01000Temporary Pavement Markings (Solid Line) (4" Width) 44.798 MILE100.004,479.801,150.0051,517.701,100.0049,277.80
0028716-01-00100Mulch (Vegetative) 7.3   TON650.004,745.00870.006,351.00750.005,475.00
0029717-01-00100Seeding 221     LB12.002,652.0015.003,315.0018.003,978.00
0030718-01-00100Fertilizer 3,682     LB0.652,393.300.602,209.200.501,841.00
0031722-02-00100Project Site Laboratory (Equipped) 1     EACH10,000.0010,000.0010,000.0010,000.0020,000.0020,000.00
0032726-01-00100Bedding Material 23.9   CUYD120.002,868.00185.004,421.50100.002,390.00
0033727-01-00100Mobilization 1     LUMP200,000.00200,000.00160,000.00160,000.00490,000.00490,000.00
0034729-16-00300Object Marker Assembly (Type 3) 21     EACH100.002,100.00120.002,520.00100.002,100.00
0035731-02-00100Reflectorized Raised Pavement Markers 939     EACH7.006,573.008.007,512.0012.0011,268.00
0036732-02-02000Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) 16.004 MILE4,600.0073,618.405,000.0080,020.005,600.0089,622.40
0037732-03-02000Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) 2.912 MILE1,400.004,076.801,300.003,785.603,000.008,736.00
0038735-01-00100Mailboxes 51     EACH5.00255.005.50280.501.0051.00
0039735-02-00100Mailbox Supports (Single) 41     EACH165.006,765.00230.009,430.00225.009,225.00
0040735-03-00100Mailbox Supports (Double) 5     EACH250.001,250.00230.001,150.00225.001,125.00
0041740-01-00100Construction Layout 1     LUMP32,000.0032,000.0016,000.0016,000.0032,000.0032,000.00
           
  CONTRACTOR TOTAL   3,658,920.00 4,319,896.83 4,980,478.95