Proposal:H.011098.6
Parish:East Baton Rouge
Routes:LA 30, LA 3290-1, LA 3290-3, LA 3290-4
Description:LA 30: SOUTH BLVD TO W CHIMES ST
Type Construction:CLEARING AND GRUBBING, REMOVAL OF BRIDGE DECK, GRADING, DRAINAGE STRUCTURES, MILLING ASPHALT CONCRETE, PAVEMENT PATCHING, CLASS II BASE COURSE, ASPHALT SURFACE TREATMENT, ASPHALT CONCRETE OVERLAY, PORTLAND CEMENT CONCRETE PAVEMENT, PRECAST CONCRETE PILES, BRIDGE WIDENING, DRILLED SHAFT FOUNDATIONS, LANDSCAPING, TRAFFIC SIGNALIZATION, AND RELATED WORK.
Estimated Construction Cost:$13,505,428.75
Maximum Number of Days Allowed for Construction:525
Calculated Daily User Cost:$6,000.00
| Rank | License | Bidder | Construction Bid | Bidder's Proposed Contract Time | Total Bid |
| 1 | 48896 | Command Construction Industries LLC | $18,246,387.55 | 452.00 | $20,958,387.55 |
| 2 | 39462 | JB JAMES CONSTRUCTION LLC | $21,225,617.75 | 550.00 | $24,525,617.75 |
| 3 | 00009 | Coastal Contractors, LLC | $26,983,545.26 | 525.00 | $30,133,545.26 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Command Construction Industries LLC | - 2 - JB JAMES CONSTRUCTION LLC | - 3 - Coastal Contractors, LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 201-01-00100 | Clearing and Grubbing | 3.2 | LUMP | 250,000.00 | 250,000.00 | 1,350,000.00 | 1,350,000.00 | 210,000.00 | 210,000.00 | | 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 250,000.00 | 250,000.00 | 65,000.00 | 65,000.00 | 210,000.00 | 210,000.00 | | 0003 | 202-02-00030 | Removal of Concrete Bridge Cap | 3 | LNFT | 2,500.00 | 7,500.00 | 6,000.00 | 18,000.00 | 10,000.00 | 30,000.00 | | 0004 | 202-02-02000 | Removal of Asphalt Drives | 42 | SQYD | 50.00 | 2,100.00 | 35.00 | 1,470.00 | 120.00 | 5,040.00 | | 0005 | 202-02-04505 | Removal of Bridge Deck (Full Depth) Ramp segment | 2,115 | SQFT | 15.00 | 31,725.00 | 30.00 | 63,450.00 | 60.00 | 126,900.00 | | 0006 | 202-02-04510 | Removal of Bridge Deck (Hydrodemolition) Oklahoma St. | 2,340 | SFIN | 35.00 | 81,900.00 | 40.00 | 93,600.00 | 50.00 | 117,000.00 | | 0007 | 202-02-05000 | Removal of Building (Sta 307+60, Lt, Single Family Wood on Piers) Contains Asbestos | 1 | EACH | 50,000.00 | 50,000.00 | 28,000.00 | 28,000.00 | 7,500.00 | 7,500.00 | | 0008 | 202-02-06000 | Removal of Concrete Approach Slabs | 208.4 | SQYD | 50.00 | 10,420.00 | 80.00 | 16,672.00 | 125.00 | 26,050.00 | | 0009 | 202-02-06090 | Removal of Concrete Revetment | 1 | LUMP | 2,500.00 | 2,500.00 | 6,000.00 | 6,000.00 | 10,000.00 | 10,000.00 | | 0010 | 202-02-06100 | Removal of Concrete Walks and Drives | 4,712 | SQYD | 10.00 | 47,120.00 | 20.00 | 94,240.00 | 100.00 | 471,200.00 | | 0011 | 202-02-14500 | Removal of Guard Rail | 105 | LNFT | 5.00 | 525.00 | 7.00 | 735.00 | 30.00 | 3,150.00 | | 0012 | 202-02-32500 | Removal of Portland Cement Concrete Pavement | 16,150 | SQYD | 15.00 | 242,250.00 | 20.00 | 323,000.00 | 25.00 | 403,750.00 | | 0013 | 202-02-40100 | Removal of Traffic Signal Equipment | 1 | LUMP | 10,000.00 | 10,000.00 | 30,000.00 | 30,000.00 | 15,500.00 | 15,500.00 | | 0014 | 203-01-00100 | General Excavation | 14,976 | CUYD | 25.00 | 374,400.00 | 26.00 | 389,376.00 | 30.00 | 449,280.00 | | 0015 | 203-03-00100 | Embankment | 1,170 | CUYD | 25.00 | 29,250.00 | 100.00 | 117,000.00 | 75.00 | 87,750.00 | | 0016 | 204-02-00100 | Temporary Hay Bales | 91 | EACH | 15.00 | 1,365.00 | 23.00 | 2,093.00 | 28.00 | 2,548.00 | | 0017 | 204-06-00100 | Temporary Silt Fencing | 36,100 | LNFT | 1.00 | 36,100.00 | 3.00 | 108,300.00 | 3.00 | 108,300.00 | | 0018 | 302-02-06040 | Class II Base Course (6" Thick) (Portland Cement Concrete) | 23,696.1 | SQYD | 65.00 | 1,540,246.50 | 90.00 | 2,132,649.00 | 80.00 | 1,895,688.00 | | 0019 | 402-01-00100 | Mainline Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) | 3,000 | CUYD | 75.00 | 225,000.00 | 120.00 | 360,000.00 | 185.00 | 555,000.00 | | 0020 | 502-01-00100 | Asphalt Concrete | 5,521 | TON | 125.00 | 690,125.00 | 136.00 | 750,856.00 | 160.00 | 883,360.00 | | 0021 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 337 | TON | 250.00 | 84,250.00 | 270.00 | 90,990.00 | 280.00 | 94,360.00 | | 0022 | 507-01-00100 | Asphalt Material (CRS-2P Emulsion) | 27,808 | GAL | 5.00 | 139,040.00 | 3.00 | 83,424.00 | 3.70 | 102,889.60 | | 0023 | 507-02-00200 | Aggregate (S2) | 40,894 | SQYD | 5.00 | 204,470.00 | 3.20 | 130,860.80 | 3.90 | 159,486.60 | | 0024 | 507-02-00300 | Aggregate (S3) | 40,894 | SQYD | 5.00 | 204,470.00 | 3.00 | 122,682.00 | 3.90 | 159,486.60 | | 0025 | 509-01-00100 | Milling Asphalt Pavement | 50,762 | SQYD | 5.00 | 253,810.00 | 5.50 | 279,191.00 | 4.00 | 203,048.00 | | 0026 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -2,115 | CUYD | 0.01 | -21.15 | 0.01 | -21.15 | 0.01 | -21.15 | | 0027 | 601-01-00300 | Portland Cement Concrete Pavement (9" Thick) | 7,480.6 | SQYD | 120.00 | 897,672.00 | 120.00 | 897,672.00 | 280.00 | 2,094,568.00 | | 0028 | 601-01-00700 | Portland Cement Concrete Pavement (11" Thick) | 7,994.1 | SQYD | 125.00 | 999,262.50 | 180.00 | 1,438,938.00 | 320.00 | 2,558,112.00 | | 0029 | 601-04-00100 | Portland Cement Concrete Pavement Coring | 10 | EACH | 500.00 | 5,000.00 | 150.00 | 1,500.00 | 500.00 | 5,000.00 | | 0030 | 602-02-00200 | Cleaning and Resealing Existing Longitudinal Pavement Joints | 9,450 | LNFT | 3.00 | 28,350.00 | 3.00 | 28,350.00 | 3.40 | 32,130.00 | | 0031 | 602-02-00300 | Cleaning and Resealing Existing Transverse Pavements Joints | 9,502 | LNFT | 3.00 | 28,506.00 | 3.00 | 28,506.00 | 3.40 | 32,306.80 | | 0032 | 602-05-01200 | Full Depth Patching of Jointed Concrete Pavement (16.0 square yards and under) (10" Thick) | 3,800 | SQYD | 300.00 | 1,140,000.00 | 425.00 | 1,615,000.00 | 525.00 | 1,995,000.00 | | 0033 | 602-05-02200 | Full Depth Patching of Jointed Concrete Pavement (16.1 square yards to 48.0 square yards) (10" Thick) | 2,500 | SQYD | 250.00 | 625,000.00 | 325.00 | 812,500.00 | 400.00 | 1,000,000.00 | | 0034 | 602-05-03200 | Full Depth Patching of Jointed Concrete Pavement (48.1 square yards and over) (10" Thick) | 2,000 | SQYD | 225.00 | 450,000.00 | 325.00 | 650,000.00 | 400.00 | 800,000.00 | | 0035 | 701-03-01002 | Storm Drain Pipe (15" RCP/RPVCP) | 795 | LNFT | 100.00 | 79,500.00 | 140.00 | 111,300.00 | 90.00 | 71,550.00 | | 0036 | 701-03-01022 | Storm Drain Pipe (18" RCP/RPVCP) | 319 | LNFT | 115.00 | 36,685.00 | 150.00 | 47,850.00 | 105.00 | 33,495.00 | | 0037 | 701-03-01042 | Storm Drain Pipe (24" RCP/RPVCP) | 234 | LNFT | 130.00 | 30,420.00 | 160.00 | 37,440.00 | 115.00 | 26,910.00 | | 0038 | 701-03-02002 | Storm Drain Pipe (Outfall) (15" RPVCP or 18" CMP) | 55 | LNFT | 100.00 | 5,500.00 | 180.00 | 9,900.00 | 155.00 | 8,525.00 | | 0039 | 701-03-02042 | Storm Drain Pipe (Outfall) (24" RPVCP or 30" CMP) | 47 | LNFT | 130.00 | 6,110.00 | 200.00 | 9,400.00 | 185.00 | 8,695.00 | | 0040 | 701-04-01040 | Storm Drain Pipe Arch (24" Equiv. RCPA) | 202 | LNFT | 150.00 | 30,300.00 | 200.00 | 40,400.00 | 155.00 | 31,310.00 | | 0041 | 701-07-00100 | Yard Drain Pipe (4") | 500 | LNFT | 25.00 | 12,500.00 | 40.00 | 20,000.00 | 79.00 | 39,500.00 | | 0042 | 701-14-00100 | Cleaning Existing Pipes | 1,550 | LNFT | 15.00 | 23,250.00 | 24.00 | 37,200.00 | 70.00 | 108,500.00 | | 0043 | 701-17-00100 | Trench Excavation Safety Protection (Depth >5 feet) | 1,332 | LNFT | 1.00 | 1,332.00 | 2.00 | 2,664.00 | 50.00 | 66,600.00 | | 0044 | 702-03-00100 | Catch Basins (CB-01) | 1 | EACH | 5,000.00 | 5,000.00 | 6,000.00 | 6,000.00 | 4,300.00 | 4,300.00 | | 0045 | 702-03-00500 | Catch Basins (CB-06) | 8 | EACH | 6,000.00 | 48,000.00 | 10,000.00 | 80,000.00 | 6,000.00 | 48,000.00 | | 0046 | 702-03-00600 | Catch Basins (CB-07) | 1 | EACH | 7,500.00 | 7,500.00 | 11,000.00 | 11,000.00 | 10,550.00 | 10,550.00 | | 0047 | 702-03-00700 | Catch Basins (CB-08) | 12 | EACH | 8,000.00 | 96,000.00 | 13,000.00 | 156,000.00 | 12,200.00 | 146,400.00 | | 0048 | 702-03-00800 | Catch Basins (CB-09) | 5 | EACH | 8,500.00 | 42,500.00 | 15,000.00 | 75,000.00 | 18,200.00 | 91,000.00 | | 0049 | 702-04-00100 | Adjusting Manholes | 22 | EACH | 1,500.00 | 33,000.00 | 5,000.00 | 110,000.00 | 3,000.00 | 66,000.00 | | 0050 | 702-04-00150 | Adjusting Manholes w/Manhole Adjustment Rings | 41 | EACH | 250.00 | 10,250.00 | 2,400.00 | 98,400.00 | 3,600.00 | 147,600.00 | | 0051 | 702-04-00200 | Adjusting Catch Basins | 9 | EACH | 1,500.00 | 13,500.00 | 5,000.00 | 45,000.00 | 1,250.00 | 11,250.00 | | 0052 | 702-04-00210 | Convert Catch Basins to Manholes | 2 | EACH | 3,000.00 | 6,000.00 | 6,000.00 | 12,000.00 | 5,500.00 | 11,000.00 | | 0053 | 704-03-00200 | Blocked Out Guard Rail - 31", (6'-3" Post Spacing) | 75 | LNFT | 35.00 | 2,625.00 | 41.00 | 3,075.00 | 60.00 | 4,500.00 | | 0054 | 704-10-00205 | Guard Rail End Treatment, MASH, (TL-3 Tangent) | 2 | EACH | 4,000.00 | 8,000.00 | 3,350.00 | 6,700.00 | 4,200.00 | 8,400.00 | | 0055 | 705-06-00200 | Chain Link Fence (5-Foot Height) | 55 | LNFT | 45.00 | 2,475.00 | 85.00 | 4,675.00 | 100.00 | 5,500.00 | | 0056 | 705-06-00300 | Chain Link Fence (6-Foot Height) | 242 | LNFT | 50.00 | 12,100.00 | 75.00 | 18,150.00 | 100.00 | 24,200.00 | | 0057 | 705-09-00100 | Rebuilt Fence | 20 | LNFT | 35.00 | 700.00 | 85.00 | 1,700.00 | 100.00 | 2,000.00 | | 0058 | 706-01-00100 | Concrete Walk (4" Thick) | 4,219.1 | SQYD | 60.00 | 253,146.00 | 65.00 | 274,241.50 | 75.00 | 316,432.50 | | 0059 | 706-02-00200 | Concrete Drive (6" Thick) | 664.8 | SQYD | 75.00 | 49,860.00 | 75.00 | 49,860.00 | 85.00 | 56,508.00 | | 0060 | 706-02-00300 | Concrete Drive (8" Thick) | 2,160.5 | SQYD | 80.00 | 172,840.00 | 100.00 | 216,050.00 | 95.00 | 205,247.50 | | 0061 | 706-03-00100 | Incidental Concrete Paving (4" Thick) | 98.9 | SQYD | 60.00 | 5,934.00 | 65.00 | 6,428.50 | 100.00 | 9,890.00 | | 0062 | 706-03-00300 | Incidental Concrete Paving (6" Thick) | 683.3 | SQYD | 75.00 | 51,247.50 | 100.00 | 68,330.00 | 100.00 | 68,330.00 | | 0063 | 706-03-00500 | Incidental Concrete Paving (8" Thick) | 22.2 | SQYD | 100.00 | 2,220.00 | 300.00 | 6,660.00 | 150.00 | 3,330.00 | | 0064 | 706-04-00100 | Handicapped Curb Ramps | 58 | EACH | 1,000.00 | 58,000.00 | 1,800.00 | 104,400.00 | 2,000.00 | 116,000.00 | | 0065 | 707-01-00100 | Concrete Curb | 3,464.7 | LNFT | 1.00 | 3,464.70 | 10.00 | 34,647.00 | 35.00 | 121,264.50 | | 0066 | 707-03-00100 | Combination Concrete Curb and Gutter | 27,464.6 | LNFT | 25.00 | 686,615.00 | 35.00 | 961,261.00 | 45.00 | 1,235,907.00 | | 0067 | 708-01-00100 | Right-of-Way Monument | 31 | EACH | 300.00 | 9,300.00 | 800.00 | 24,800.00 | 950.00 | 29,450.00 | | 0068 | 710-01-00100 | Flowable Fill | 73 | CUYD | 200.00 | 14,600.00 | 400.00 | 29,200.00 | 750.00 | 54,750.00 | | 0069 | 712-01-00100 | Concrete Cast-in-Place Revetment (4" Thick) | 31 | SQYD | 200.00 | 6,200.00 | 250.00 | 7,750.00 | 500.00 | 15,500.00 | | 0070 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 250,000.00 | 250,000.00 | 800,000.00 | 800,000.00 | 850,000.00 | 850,000.00 | | 0071 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 1,628 | LNFT | 1.00 | 1,628.00 | 1.00 | 1,628.00 | 1.20 | 1,953.60 | | 0072 | 713-03-02020 | Temporary Pavement Markings (Broken Line) (4" W) (10' L) (Type 1 Removable) | 5.221 | MILE | 5,000.00 | 26,105.00 | 5,000.00 | 26,105.00 | 6,000.00 | 31,326.00 | | 0073 | 713-04-01020 | Temporary Pavement Markings (Solid Line) (4"Width) (Type 1 Removable) | 11.07 | MILE | 15,000.00 | 166,050.00 | 15,000.00 | 166,050.00 | 18,000.00 | 199,260.00 | | 0074 | 713-05-00220 | Temporary Pavement Legends & Symbols (Arrow - Left Turn) | 14 | EACH | 100.00 | 1,400.00 | 65.00 | 910.00 | 78.00 | 1,092.00 | | 0075 | 713-06-00100 | Temporary Reflectorized Raised Pavement Markers | 692 | EACH | 15.00 | 10,380.00 | 10.00 | 6,920.00 | 12.00 | 8,304.00 | | 0076 | 713-11-00100 | Portable Changeable Message Signs | 6 | EACH | 15,000.00 | 90,000.00 | 18,000.00 | 108,000.00 | 25,000.00 | 150,000.00 | | 0077 | 719-01-02020 | Plants (Tree) (Container) (1-1/2 inch cal) (MAGNOLIA GRANDIFLORA, 'LITTLE GEM') (MIN. 4'-5' HT., 30" SPREAD, 15 GAL.) | 5 | EACH | 500.00 | 2,500.00 | 740.00 | 3,700.00 | 900.00 | 4,500.00 | | 0078 | 719-01-02060 | Plants (Tree) (Container) (2-1/2 inch cal) (QUERCUS VIRGINIANA, LIVE OAK) (MIN. 9'-11' HT., 55" SPREAD, 30 GAL.) | 3 | EACH | 500.00 | 1,500.00 | 1,100.00 | 3,300.00 | 1,350.00 | 4,050.00 | | 0079 | 726-01-00100 | Bedding Material | 186.2 | CUYD | 100.00 | 18,620.00 | 80.00 | 14,896.00 | 200.00 | 37,240.00 | | 0080 | 727-01-00100 | Mobilization | 1 | LUMP | 1,750,000.00 | 1,750,000.00 | 2,000,000.00 | 2,000,000.00 | 1,365,000.00 | 1,365,000.00 | | 0081 | 729-01-00100 | Sign (Type A) | 739.5 | SQFT | 35.00 | 25,882.50 | 21.00 | 15,529.50 | 30.00 | 22,185.00 | | 0082 | 729-01-00103 | Sign (Type A)(Relocate) | 134 | SQFT | 35.00 | 4,690.00 | 21.00 | 2,814.00 | 30.00 | 4,020.00 | | 0083 | 729-04-00100 | Sign (Type D) | 90 | SQFT | 10.00 | 900.00 | 54.00 | 4,860.00 | 100.00 | 9,000.00 | | 0084 | 729-08-00100 | Mounting (2 1/2" Size Post) | 5 | EACH | 3,500.00 | 17,500.00 | 1,500.00 | 7,500.00 | 1,850.00 | 9,250.00 | | 0085 | 729-08-00600 | Mounting (W6 x 12 Size Post) | 6 | EACH | 4,500.00 | 27,000.00 | 2,950.00 | 17,700.00 | 3,700.00 | 22,200.00 | | 0086 | 729-16-00300 | Object Marker Assembly (Type 3) | 6 | EACH | 150.00 | 900.00 | 95.00 | 570.00 | 120.00 | 720.00 | | 0087 | 729-19-00100 | Dead End Road Installations (Type A) | 1 | EACH | 5,500.00 | 5,500.00 | 2,450.00 | 2,450.00 | 3,000.00 | 3,000.00 | | 0088 | 729-19-00200 | Dead End Road Installations (Type B) | 1 | EACH | 5,500.00 | 5,500.00 | 2,600.00 | 2,600.00 | 3,000.00 | 3,000.00 | | 0089 | 729-22-00100 | Square Tubing Post with 2-1/4" Anchor | 62 | EACH | 300.00 | 18,600.00 | 155.00 | 9,610.00 | 200.00 | 12,400.00 | | 0090 | 731-02-00100 | Reflectorized Raised Pavement Markers | 1,172 | EACH | 15.00 | 17,580.00 | 11.00 | 12,892.00 | 13.50 | 15,822.00 | | 0091 | 732-01-02040 | Plastic Pavement Striping (8" Width) (Thermoplastic 125 mil) | 1,250 | LNFT | 5.00 | 6,250.00 | 4.00 | 5,000.00 | 4.86 | 6,075.00 | | 0092 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 1,973 | LNFT | 20.00 | 39,460.00 | 16.00 | 31,568.00 | 20.00 | 39,460.00 | | 0093 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 7.347 | MILE | 6,000.00 | 44,082.00 | 5,500.00 | 40,408.50 | 6,600.00 | 48,490.20 | | 0094 | 732-02-02040 | Plastic Pavement Striping (Solid Line) (8" Width) (Thermoplastic 90 mil) | 0.523 | MILE | 15,000.00 | 7,845.00 | 11,000.00 | 5,753.00 | 14,000.00 | 7,322.00 | | 0095 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 2.754 | MILE | 3,000.00 | 8,262.00 | 3,000.00 | 8,262.00 | 3,600.00 | 9,914.40 | | 0096 | 732-03-02012 | Plastic Pavement Striping (Dotted Line)(4" W)(3' L)(Thermo 90 mil) | 0.059 | MILE | 4,000.00 | 236.00 | 4,000.00 | 236.00 | 4,900.00 | 289.10 | | 0097 | 732-03-02030 | Plastic Pavement Striping (Dotted Line)(8" W)(2' L)(Thermo 90 mil) | 0.332 | MILE | 5,000.00 | 1,660.00 | 5,000.00 | 1,660.00 | 6,000.00 | 1,992.00 | | 0098 | 732-03-02040 | Plastic Pavement Striping (Dotted Line)(8" W)(3' L)(Thermo 90 mil) | 0.099 | MILE | 5,000.00 | 495.00 | 5,000.00 | 495.00 | 6,100.00 | 603.90 | | 0099 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 28 | EACH | 500.00 | 14,000.00 | 375.00 | 10,500.00 | 450.00 | 12,600.00 | | 0100 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 27 | EACH | 500.00 | 13,500.00 | 375.00 | 10,125.00 | 450.00 | 12,150.00 | | 0101 | 732-04-25020 | Plastic Pavement Legends and Symbols (Yield Line) | 12 | EACH | 700.00 | 8,400.00 | 100.00 | 1,200.00 | 120.00 | 1,440.00 | | 0102 | 732-05-00100 | Removal of Existing Markings | 0.006 | MILE | 250,000.00 | 1,500.00 | 50,000.00 | 300.00 | 60,000.00 | 360.00 | | 0103 | 735-01-00100 | Mailboxes | 5 | EACH | 50.00 | 250.00 | 25.00 | 125.00 | 50.00 | 250.00 | | 0104 | 735-02-00100 | Mailbox Supports (Single) | 5 | EACH | 250.00 | 1,250.00 | 300.00 | 1,500.00 | 250.00 | 1,250.00 | | 0105 | 736-01-00100 | Trenching and Backfilling | 660 | LNFT | 8.00 | 5,280.00 | 7.00 | 4,620.00 | 8.00 | 5,280.00 | | 0106 | 736-03-00100 | Jacking or Boring | 1,725 | LNFT | 25.00 | 43,125.00 | 14.00 | 24,150.00 | 42.09 | 72,605.25 | | 0107 | 736-04-00001 | Signal Pole (Pedestal Pole) | 6 | EACH | 1,250.00 | 7,500.00 | 2,000.00 | 12,000.00 | 4,100.00 | 24,600.00 | | 0108 | 736-05-10005 | Signal Heads (1 Section, 12 inch Led Lens, Y) | 2 | EACH | 1,000.00 | 2,000.00 | 580.00 | 1,160.00 | 950.00 | 1,900.00 | | 0109 | 736-05-30000 | Signal Heads (3 Section, 12 inch Led Lens, R, Y, G) | 30 | EACH | 1,000.00 | 30,000.00 | 800.00 | 24,000.00 | 1,900.00 | 57,000.00 | | 0110 | 736-05-41200 | Signal Heads (4 Section, 12 inch Led Lens, LT. R, LT. Y, FLT. Y, LT. G) | 8 | EACH | 1,250.00 | 10,000.00 | 1,100.00 | 8,800.00 | 2,400.00 | 19,200.00 | | 0111 | 736-06-00100 | Signal Service | 1 | EACH | 9,000.00 | 9,000.00 | 2,000.00 | 2,000.00 | 5,940.00 | 5,940.00 | | 0112 | 736-06-00300 | Signal Service with Separate Disconnect for Street Lights | 3 | EACH | 11,000.00 | 33,000.00 | 2,700.00 | 8,100.00 | 4,200.00 | 12,600.00 | | 0113 | 736-06-00500 | Signal Service Pedestal Disconnect | 4 | EACH | 2,000.00 | 8,000.00 | 2,300.00 | 9,200.00 | 4,250.00 | 17,000.00 | | 0114 | 736-08-00102 | Signal Controller (980 ATC, Type 2)(Furnish & Install) | 4 | EACH | 8,000.00 | 32,000.00 | 6,000.00 | 24,000.00 | 9,300.00 | 37,200.00 | | 0115 | 736-10-00100 | Underground Junction Box (Type D) | 16 | EACH | 650.00 | 10,400.00 | 1,200.00 | 19,200.00 | 1,300.00 | 20,800.00 | | 0116 | 736-10-00200 | Underground Junction Box (Type E) | 1 | EACH | 750.00 | 750.00 | 1,300.00 | 1,300.00 | 1,400.00 | 1,400.00 | | 0117 | 736-10-00300 | Underground Junction Box (Type F) | 18 | EACH | 1,000.00 | 18,000.00 | 1,400.00 | 25,200.00 | 1,625.00 | 29,250.00 | | 0118 | 736-10-00400 | Underground Junction Box (Type G) | 4 | EACH | 1,500.00 | 6,000.00 | 1,800.00 | 7,200.00 | 1,610.00 | 6,440.00 | | 0119 | 736-11-00200 | Conduit (2" HDPE, Schedule 80) | 807 | LNFT | 6.00 | 4,842.00 | 5.00 | 4,035.00 | 12.00 | 9,684.00 | | 0120 | 736-11-00300 | Conduit (3" HDPE, Schedule 80) | 1,576 | LNFT | 10.00 | 15,760.00 | 11.00 | 17,336.00 | 21.00 | 33,096.00 | | 0121 | 736-12-02006 | Conductor (2c, #6 awg) | 651 | LNFT | 8.00 | 5,208.00 | 6.00 | 3,906.00 | 5.25 | 3,417.75 | | 0122 | 736-12-02014 | Conductor (2c, #14 awg) | 2,553 | LNFT | 5.00 | 12,765.00 | 1.00 | 2,553.00 | 2.50 | 6,382.50 | | 0123 | 736-12-03006 | Conductor (3c, 6 gauge / #6 awg) | 500 | LNFT | 10.00 | 5,000.00 | 6.00 | 3,000.00 | 5.50 | 2,750.00 | | 0124 | 736-12-06014 | Conductor (6c, #14 awg) | 3,640 | LNFT | 5.00 | 18,200.00 | 3.00 | 10,920.00 | 2.80 | 10,192.00 | | 0125 | 736-12-10014 | Conductor (10c, #14 awg) | 2,589 | LNFT | 5.00 | 12,945.00 | 4.00 | 10,356.00 | 2.41 | 6,239.49 | | 0126 | 736-12-10014 | Conductor (10c, #14 awg) | 342 | LNFT | 5.00 | 1,710.00 | 4.00 | 1,368.00 | 2.41 | 824.22 | | 0127 | 736-21-00000 | LED Pedestrian Countdown Signal Head | 26 | EACH | 500.00 | 13,000.00 | 900.00 | 23,400.00 | 1,380.00 | 35,880.00 | | 0128 | 737-04-00001 | Painted Curbs and Islands | 130 | LNFT | 30.00 | 3,900.00 | 50.00 | 6,500.00 | 70.00 | 9,100.00 | | 0129 | 739-01-00100 | Hydro-Seeding | 2.8 | ACRE | 5,000.00 | 14,000.00 | 2,500.00 | 7,000.00 | 2,950.00 | 8,260.00 | | 0130 | 740-01-00100 | Construction Layout | 1 | LUMP | 250,000.00 | 250,000.00 | 130,000.00 | 130,000.00 | 250,000.00 | 250,000.00 | | 0131 | 804-01-00200 | Precast Concrete Piles (14") | 390 | LNFT | 125.00 | 48,750.00 | 140.00 | 54,600.00 | 115.00 | 44,850.00 | | 0132 | 804-05-00200 | Precast Concrete Test Piles (14") | 1 | EACH | 10,000.00 | 10,000.00 | 90,000.00 | 90,000.00 | 5,000.00 | 5,000.00 | | 0133 | 804-14-00100 | Dynamic Monitoring Assistance | 3 | EACH | 1,500.00 | 4,500.00 | 2,500.00 | 7,500.00 | 2,500.00 | 7,500.00 | | 0134 | 804-18-00100 | Vibration Monitoring | 10 | DAY | 1,250.00 | 12,500.00 | 800.00 | 8,000.00 | 1,150.00 | 11,500.00 | | 0135 | 805-01-00100 | Class A1 Concrete (Slab Span) | 50.37 | CUYD | 500.00 | 25,185.00 | 2,000.00 | 100,740.00 | 3,400.00 | 171,258.00 | | 0136 | 805-01-00300 | Class A1 Concrete (Bent Cap) | 14 | CUYD | 1,500.00 | 21,000.00 | 2,500.00 | 35,000.00 | 4,500.00 | 63,000.00 | | 0137 | 805-18-00100 | Concrete Finish (Class 2 Rubbed Finish) | 192 | SQFT | 1.00 | 192.00 | 1.00 | 192.00 | 4.50 | 864.00 | | 0138 | 805-18-00200 | Concrete Finish (Class 3 Special Finish) | 1,052 | SQFT | 2.00 | 2,104.00 | 1.30 | 1,367.60 | 6.50 | 6,838.00 | | 0139 | 806-01-00100 | Deformed Reinforcing Steel | 14,140 | LB | 2.00 | 28,280.00 | 2.00 | 28,280.00 | 2.25 | 31,815.00 | | 0140 | 806-03-00100 | Deformed Reinforcing Steel Mechanical Splice splice | 33 | EACH | 100.00 | 3,300.00 | 200.00 | 6,600.00 | 90.00 | 2,970.00 | | 0141 | 810-03-00100 | Concrete and Metal Bridge Railing | 50 | LNFT | 500.00 | 25,000.00 | 600.00 | 30,000.00 | 825.00 | 41,250.00 | | 0142 | 813-01-00100 | Concrete Approach Slabs (Cast-in-Place) | 460 | SQFT | 50.00 | 23,000.00 | 80.00 | 36,800.00 | 185.00 | 85,100.00 | | 0143 | 814-01-00100 | Elastomeric Bearing Pads (Non-Reinforced) | 69 | SFIN | 150.00 | 10,350.00 | 110.00 | 7,590.00 | 100.00 | 6,900.00 | | 0144 | 815-03-00300 | Joint Seal (Poured) | 73 | LNFT | 5.00 | 365.00 | 26.00 | 1,898.00 | 50.00 | 3,650.00 | | 0145 | 822-01-00100 | Trenching and Backfilling | 1,510 | LNFT | 8.00 | 12,080.00 | 7.00 | 10,570.00 | 8.80 | 13,288.00 | | 0146 | 822-02-00200 | Conduit w Conductors (PVC/HDPE) (1") (2#10,1#10 BARE STRANDED GROUND) (H) | 1,670 | LNFT | 25.00 | 41,750.00 | 22.00 | 36,740.00 | 11.75 | 19,622.50 | | 0147 | 822-02-00200 | Conduit w Conductors (PVC/HDPE) (1") (4#10,1#10 BARE STRANDED GROUND) (E ) | 30 | LNFT | 8.00 | 240.00 | 8.00 | 240.00 | 13.00 | 390.00 | | 0148 | 822-02-00500 | Conduit w Conductors (PVC/HDPE) (2") (2#2, 1#2 WHITE NEUTRAL, 1#2 BARE STRANDED GROUND) (C ) | 20 | LNFT | 25.00 | 500.00 | 21.00 | 420.00 | 35.00 | 700.00 | | 0149 | 822-02-02200 | Conduit w Conductors (Rigid Galv Steel) (1") (4#10, 1#10 GREEN INSULATED GROUND) (I) | 30 | LNFT | 25.00 | 750.00 | 13.00 | 390.00 | 18.00 | 540.00 | | 0150 | 822-02-02500 | Conduit w Conductors (Rigid Galv Steel) (2") (3#2) (A) | 30 | LNFT | 45.00 | 1,350.00 | 28.00 | 840.00 | 65.00 | 1,950.00 | | 0151 | 822-02-04200 | Conduit w Conductors (Fiberglass) (1") (4#10,1#10 BARE STRANDED GROUND) (D) | 30 | LNFT | 30.00 | 900.00 | 25.00 | 750.00 | 52.00 | 1,560.00 | | 0152 | 822-02-04500 | Conduit w Conductors (Fiberglass) (2") (2#2, 1#2 WHITE NEUTRAL, 1#2 BARE STRANDED GROUND) (B) | 20 | LNFT | 50.00 | 1,000.00 | 42.00 | 840.00 | 75.00 | 1,500.00 | | 0153 | 822-03-00100 | Conductors (4#10, 1#10 GREEN INSULATED GROUND) | 30 | LNFT | 6.00 | 180.00 | 4.00 | 120.00 | 40.00 | 1,200.00 | | 0154 | 822-03-00100 | Conductors (IN EXISTING CONDUIT) (2#10, 1#10 GREEN INSULATED GROUND) (G) | 30 | LNFT | 5.00 | 150.00 | 3.00 | 90.00 | 40.00 | 1,200.00 | | 0155 | 822-04-00100 | Jacked or Bored Casing (4" Dia) (PVC/HDPE) | 160 | LNFT | 30.00 | 4,800.00 | 22.00 | 3,520.00 | 53.00 | 8,480.00 | | 0156 | 822-05-02100 | Light Pole (30') (ALUM) (SINGLE ARM) (7' ARM) (GROUND MOUNT, BREAKAWAY) | 8 | EACH | 7,000.00 | 56,000.00 | 9,000.00 | 72,000.00 | 9,000.00 | 72,000.00 | | 0157 | 822-07-02800 | Luminaire (LOWMAST) (LED) (4K) | 8 | EACH | 750.00 | 6,000.00 | 1,400.00 | 11,200.00 | 1,800.00 | 14,400.00 | | 0158 | 822-08-00200 | Electrical Service Point (Structure) | 1 | EACH | 30,000.00 | 30,000.00 | 19,000.00 | 19,000.00 | 40,000.00 | 40,000.00 | | 0159 | 822-11-00100 | Removal and Disposal of Electrical Equipment | 1 | LUMP | 5,000.00 | 5,000.00 | 1,100.00 | 1,100.00 | 11,300.00 | 11,300.00 | | 0160 | 822-12-00300 | Removal and Storage of Light Pole remove and store | 8 | EACH | 500.00 | 4,000.00 | 600.00 | 4,800.00 | 600.00 | 4,800.00 | | 0161 | 822-13-00100 | Removal and Disposal of Light Pole Foundation remove and dispose | 8 | EACH | 500.00 | 4,000.00 | 1,500.00 | 12,000.00 | 1,300.00 | 10,400.00 | | 0162 | 822-14-00100 | Removal and Disposal of Luminaire | 8 | EACH | 100.00 | 800.00 | 57.00 | 456.00 | 140.00 | 1,120.00 | | 0163 | 822-16-00200 | Underground Junction Box (11" x 18") | 13 | EACH | 1,000.00 | 13,000.00 | 800.00 | 10,400.00 | 1,550.00 | 20,150.00 | | 0164 | 822-19-00100 | Modular Breakaway Cable System | 8 | EACH | 3,000.00 | 24,000.00 | 2,000.00 | 16,000.00 | 2,650.00 | 21,200.00 | | 0165 | 822-20-00100 | Disconnect (Service) | 3 | EACH | 4,500.00 | 13,500.00 | 3,800.00 | 11,400.00 | 6,200.00 | 18,600.00 | | 0166 | 822-21-00100 | Duct Marker (Concrete) | 4 | EACH | 300.00 | 1,200.00 | 700.00 | 2,800.00 | 725.00 | 2,900.00 | | 0167 | 822-22-00300 | Underground Marker Tape (6")(Detectable) | 1,510 | LNFT | 1.00 | 1,510.00 | 0.60 | 906.00 | 2.31 | 3,488.10 | | 0168 | 830-07-00100 | Structural Concrete Patching | 35 | SQFT | 500.00 | 17,500.00 | 900.00 | 31,500.00 | 400.00 | 14,000.00 | | 0169 | 830-10-00100 | Epoxy Injection | 80 | LNFT | 100.00 | 8,000.00 | 500.00 | 40,000.00 | 300.00 | 24,000.00 | | 0170 | NS-201-00004 | Arborist Services | 18 | EACH | 250.00 | 4,500.00 | 2,250.00 | 40,500.00 | 4,000.00 | 72,000.00 | | 0171 | NS-201-00005 | Arborist Services | 1 | LUMP | 50,000.00 | 50,000.00 | 5,400.00 | 5,400.00 | 100,000.00 | 100,000.00 | | 0172 | NS-500-00220 | Sawing and Sealing Longitudinal Joints in Asphalt Concrete Overlay | 52,749 | LNFT | 2.50 | 131,872.50 | 1.65 | 87,035.85 | 3.00 | 158,247.00 | | 0173 | NS-500-00240 | Sawing and Sealing Transverse Joints in Asphalt Concrete Overlay | 19,924 | LNFT | 2.50 | 49,810.00 | 1.80 | 35,863.20 | 3.00 | 59,772.00 | | 0174 | NS-500-00260 | Sawcuts in Asphalt Concrete Lifts | 72,673 | LNFT | 1.00 | 72,673.00 | 1.30 | 94,474.90 | 1.80 | 130,811.40 | | 0175 | NS-500-00360 | Saw Cutting Asphalt Concrete Pavement Over Portland Cement Concrete Composite Pavement | 746,339 | INLF | 2.00 | 1,492,678.00 | 0.45 | 335,852.55 | 1.80 | 1,343,410.20 | | 0176 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 14,360 | INLF | 2.00 | 28,720.00 | 0.60 | 8,616.00 | 3.00 | 43,080.00 | | 0177 | NS-702-00001 | Cleaning Existing Catch Basin | 2 | EACH | 350.00 | 700.00 | 4,000.00 | 8,000.00 | 1,500.00 | 3,000.00 | | 0178 | NS-719-00004 | Hand Formed and Poured In-Place Concrete Curb Within the Limits of the Tree Dripline | 2,599 | LNFT | 15.00 | 38,985.00 | 70.00 | 181,930.00 | 90.00 | 233,910.00 | | 0179 | NS-719-00005 | Gravel Bed and Filter Cloth over Tree Roots | 1,420.1 | SQYD | 25.00 | 35,502.50 | 30.00 | 42,603.00 | 100.00 | 142,010.00 | | 0180 | NS-736-00001 | GPS | 4 | EACH | 500.00 | 2,000.00 | 500.00 | 2,000.00 | 1,050.00 | 4,200.00 | | 0181 | NS-736-00003 | Managed Ethernet Switch | 4 | EACH | 4,000.00 | 16,000.00 | 2,500.00 | 10,000.00 | 6,250.00 | 25,000.00 | | 0182 | NS-736-00020 | Wireless Magnetometer Vehicle Detection System (Cabinet Components) | 4 | EACH | 9,000.00 | 36,000.00 | 7,500.00 | 30,000.00 | 15,200.00 | 60,800.00 | | 0183 | NS-736-00021 | Wireless Magnetometer Vehicle Detection System (Antennas) | 4 | EACH | 15,000.00 | 60,000.00 | 11,000.00 | 44,000.00 | 20,240.00 | 80,960.00 | | 0184 | NS-736-00022 | Wireless Magnetometer Vehicle Detection System (Magnetometers) | 131 | EACH | 1,000.00 | 131,000.00 | 900.00 | 117,900.00 | 6,250.00 | 818,750.00 | | 0185 | NS-736-00130 | TS-2 Traffic Signal Cabinet (Ground Mounted) | 4 | EACH | 19,000.00 | 76,000.00 | 21,000.00 | 84,000.00 | 28,100.00 | 112,400.00 | | 0186 | NS-736-00135 | 2-Wire Accessible Pedestrian Pushbutton Detectors | 26 | EACH | 1,000.00 | 26,000.00 | 1,000.00 | 26,000.00 | 3,775.00 | 98,150.00 | | 0187 | NS-736-00136 | 2-Wire Accessible Pedestrian Pushbutton Cabinet Control | 4 | EACH | 4,500.00 | 18,000.00 | 3,300.00 | 13,200.00 | 7,400.00 | 29,600.00 | | 0188 | NS-744-00600 | Lane Separator System (Furnish and Install) | 408 | LNFT | 200.00 | 81,600.00 | 73.00 | 29,784.00 | 90.00 | 36,720.00 | | 0189 | NS-830-00800 | Latex Modified Concrete Overlay | 8,454 | SFIN | 100.00 | 845,400.00 | 15.00 | 126,810.00 | 18.80 | 158,935.20 | | 0190 | NS-ITS-04035 | Fiber Optic Fan Out Kits, SM, 12 Strand, Furnish & Install | 4 | EACH | 450.00 | 1,800.00 | 51.00 | 204.00 | 305.00 | 1,220.00 | | 0191 | NS-ITS-04180 | Fiber Optic Connection, Install, Splice | 76 | EACH | 100.00 | 7,600.00 | 15.00 | 1,140.00 | 195.00 | 14,820.00 | | 0192 | NS-ITS-04200 | Fiber Optic Connection, Termination, Furnish & Install | 48 | EACH | 130.00 | 6,240.00 | 800.00 | 38,400.00 | 210.00 | 10,080.00 | | 0193 | NS-ITS-04250 | Fiber Optic Drop Cable, SM, 12 Strand, Furnish & Install | 153 | LNFT | 50.00 | 7,650.00 | 4.00 | 612.00 | 4.50 | 688.50 | | 0194 | NS-ITS-04290 | Fiber Optic Patch Cord, SM, 2 Strand, Furnish & Install | 8 | EACH | 175.00 | 1,400.00 | 32.00 | 256.00 | 150.00 | 1,200.00 | | 0195 | NS-ITS-04425 | Fiber Optic Connection Patch Panel, Outdoor, Furnish & Install | 4 | EACH | 2,200.00 | 8,800.00 | 900.00 | 3,600.00 | 1,500.00 | 6,000.00 | | 0196 | NS-ITS-12000 | Communications System Integration | 1 | LUMP | 10,000.00 | 10,000.00 | 2,400.00 | 2,400.00 | 3,360.00 | 3,360.00 | | 0197 | NS-MSC-00080 | Detectable Warning Surface Retrofit for Curb Ramps | 3 | EACH | 300.00 | 900.00 | 4,000.00 | 12,000.00 | 1,700.00 | 5,100.00 | | 0198 | TS-736-10250 | Signal Support (Mast Arm Standard w/ 25 ft arm) | 1 | EACH | 25,000.00 | 25,000.00 | 18,000.00 | 18,000.00 | 30,000.00 | 30,000.00 | | 0199 | TS-736-10300 | Signal Support (Mast Arm Standard w/ 30 ft arm) | 1 | EACH | 27,000.00 | 27,000.00 | 23,000.00 | 23,000.00 | 31,150.00 | 31,150.00 | | 0200 | TS-736-10350 | Signal Support (Mast Arm Standard w/ 35 ft arm) | 1 | EACH | 30,000.00 | 30,000.00 | 26,000.00 | 26,000.00 | 34,150.00 | 34,150.00 | | 0201 | TS-736-10400 | Signal Support (Mast Arm Standard w/ 40 ft arm) | 2 | EACH | 35,000.00 | 70,000.00 | 30,000.00 | 60,000.00 | 37,500.00 | 75,000.00 | | 0202 | TS-736-10450 | Signal Support (Mast Arm Standard w/ 45 ft arm) | 6 | EACH | 37,000.00 | 222,000.00 | 35,000.00 | 210,000.00 | 40,250.00 | 241,500.00 | | 0203 | TS-736-10550 | Signal Support (Mast Arm Standard w/ 55 ft arm) | 1 | EACH | 45,000.00 | 45,000.00 | 65,000.00 | 65,000.00 | 105,000.00 | 105,000.00 | | 0204 | TS-736-10600 | Signal Support (Mast Arm Standard w/ 60 ft arm) | 1 | EACH | 60,000.00 | 60,000.00 | 67,000.00 | 67,000.00 | 115,000.00 | 115,000.00 | | 0205 | TS-736-11350 | Additional Mast Arm (35 ft. arm) | 3 | EACH | 10,000.00 | 30,000.00 | 9,000.00 | 27,000.00 | 15,500.00 | 46,500.00 | | 0206 | TS-736-11450 | Additional Mast Arm (45 ft. arm) | 3 | EACH | 13,000.00 | 39,000.00 | 10,000.00 | 30,000.00 | 15,000.00 | 45,000.00 | | 0207 | TS-736-12008 | Luminaire Arm w/LED Luminaire (8 ft. arm) | 6 | EACH | 2,500.00 | 15,000.00 | 2,400.00 | 14,400.00 | 3,400.00 | 20,400.00 | | 0208 | TS-736-15002 | GPS Based Traffic Signal Preemption System (With Existing Fiber Communication) | 4 | EACH | 12,000.00 | 48,000.00 | 8,000.00 | 32,000.00 | 12,000.00 | 48,000.00 | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 18,246,387.55 | | 21,225,617.75 | | 26,983,545.26 |
|