Proposal:H.014572.6
Parish:St. Martin
Routes:LA 352
Description:LA 352 SLIDE REPAIR
Type Construction:CLEARING AND GRUBBING, GRADING, DRAINAGE STRUCTURES, PAVEMENT PATCHING, CLASS II BASE COURSE, LIME TREATMENT, IN-PLACE CEMENT STABILIZED BASE COURSE, ASPHALT CONCRETE PAVEMENT, AND RELATED WORK.
Estimated Construction Cost:$3,569,306.55
| Rank | License | Bidder | Construction Bid |
| 1 | 54928 | Womack And Sons Constr. Group LLC | $2,729,757.10 |
| 2 | 12312 | GILCHRIST CONSTRUCTION COMPANY, LLC | $3,684,013.30 |
| 3 | 52306 | SIEMA CONSTRUCTION, LLC | $4,898,627.75 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Womack And Sons Constr. Group LLC | - 2 - GILCHRIST CONSTRUCTION COMPANY, LLC | - 3 - SIEMA CONSTRUCTION, LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 201-01-00100 | Clearing and Grubbing | 10 | LUMP | 33,500.00 | 33,500.00 | 50,000.00 | 50,000.00 | 95,300.00 | 95,300.00 | | 0002 | 202-02-02020 | Removal of Asphalt Pavement | 5,225 | SQYD | 2.80 | 14,630.00 | 5.00 | 26,125.00 | 8.00 | 41,800.00 | | 0003 | 202-02-03000 | Removal of Base – Soil Cement, Asphalt, or BCS | 1,830.5 | SQYD | 7.00 | 12,813.50 | 15.00 | 27,457.50 | 15.50 | 28,372.75 | | 0004 | 202-02-03010 | Removal of Base – Recycled PCC or Stone | 5,225 | SQYD | 3.00 | 15,675.00 | 4.00 | 20,900.00 | 13.50 | 70,537.50 | | 0005 | 202-02-32100 | Removal of Pipe (Cross Drain) 24" RCPA | 24 | LNFT | 52.00 | 1,248.00 | 60.00 | 1,440.00 | 15.00 | 360.00 | | 0006 | 202-02-38220 | Removal of Sign Supports | 7 | EACH | 12.00 | 84.00 | 150.00 | 1,050.00 | 10.50 | 73.50 | | 0007 | 202-02-38360 | Removal of Sign Faces | 11 | EACH | 12.00 | 132.00 | 100.00 | 1,100.00 | 10.50 | 115.50 | | 0008 | 203-01-00100 | General Excavation | 25,474 | CUYD | 8.50 | 216,529.00 | 16.00 | 407,584.00 | 24.50 | 624,113.00 | | 0009 | 203-03-00100 | Embankment | 68,367 | CUYD | 18.00 | 1,230,606.00 | 31.00 | 2,119,377.00 | 40.50 | 2,768,863.50 | | 0010 | 203-04-00300 | Nonplastic Embankment (Stone) | 43 | CUYD | 530.00 | 22,790.00 | 450.00 | 19,350.00 | 190.00 | 8,170.00 | | 0011 | 203-08-00100 | Geotextile Fabric | 482 | SQYD | 2.75 | 1,325.50 | 2.00 | 964.00 | 3.50 | 1,687.00 | | 0012 | 204-06-00100 | Temporary Silt Fencing | 9,700 | LNFT | 2.00 | 19,400.00 | 2.00 | 19,400.00 | 2.50 | 24,250.00 | | 0013 | 204-07-00100 | Temporary Stone Construction Entrance | 4 | EACH | 9,000.00 | 36,000.00 | 1,000.00 | 4,000.00 | 2,800.00 | 11,200.00 | | 0014 | 302-02-04070 | Class II Base Course (4" Thick) (Crushed Stone or Recycled Portland Cement Concrete) | 5,700.1 | SQYD | 22.00 | 125,402.20 | 16.00 | 91,201.60 | 23.00 | 131,102.30 | | 0015 | 303-01-00200 | In-Place Cement Stabilized Base Course (8-1/2" Thick) | 5,701 | SQYD | 12.00 | 68,412.00 | 14.00 | 79,814.00 | 17.00 | 96,917.00 | | 0016 | 304-01-00100 | Lime | 15.58 | TON | 300.00 | 4,674.00 | 350.00 | 5,453.00 | 350.00 | 5,453.00 | | 0017 | 304-05-00100 | Lime Treatment (Type E) | 1,099 | SQYD | 20.00 | 21,980.00 | 13.00 | 14,287.00 | 10.50 | 11,539.50 | | 0018 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 887 | CUYD | 130.00 | 115,310.00 | 50.00 | 44,350.00 | 133.00 | 117,971.00 | | 0019 | 502-01-00100 | Asphalt Concrete | 1,174.5 | TON | 200.00 | 234,900.00 | 140.00 | 164,430.00 | 134.00 | 157,383.00 | | 0020 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 55.5 | TON | 300.00 | 16,650.00 | 140.00 | 7,770.00 | 181.00 | 10,045.50 | | 0021 | 510-01-00260 | Pavement Patching (16 inch Minimum Thickness) | 125 | SQYD | 225.00 | 28,125.00 | 200.00 | 25,000.00 | 320.00 | 40,000.00 | | 0022 | 701-11-01040 | Reinforced Concrete Pipe Arch (Extension) (24" Equiv.) | 166 | LNFT | 130.00 | 21,580.00 | 300.00 | 49,800.00 | 112.00 | 18,592.00 | | 0023 | 701-15-00100 | Concrete Collar | 5 | EACH | 2,500.00 | 12,500.00 | 3,500.00 | 17,500.00 | 700.00 | 3,500.00 | | 0024 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 39,500.00 | 39,500.00 | 65,000.00 | 65,000.00 | 62,000.00 | 62,000.00 | | 0025 | 713-02-00100 | Temporary Pavement Markings (4" Width) | 25,650 | LNFT | 0.25 | 6,412.50 | 1.00 | 25,650.00 | 0.55 | 14,107.50 | | 0026 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 22 | LNFT | 1.25 | 27.50 | 6.00 | 132.00 | 5.20 | 114.40 | | 0027 | 713-11-00100 | Portable Changeable Message Signs | 2 | EACH | 7,500.00 | 15,000.00 | 10,000.00 | 20,000.00 | 14,655.00 | 29,310.00 | | 0028 | 722-02-00100 | Project Site Laboratory (Equipped) | 1 | EACH | 65,000.00 | 65,000.00 | 20,000.00 | 20,000.00 | 39,500.00 | 39,500.00 | | 0029 | 726-01-00100 | Bedding Material | 17.2 | CUYD | 225.00 | 3,870.00 | 100.00 | 1,720.00 | 140.00 | 2,408.00 | | 0030 | 727-01-00100 | Mobilization | 1 | LUMP | 123,500.00 | 123,500.00 | 105,000.00 | 105,000.00 | 210,000.00 | 210,000.00 | | 0031 | 729-01-00100 | Sign (Type A) | 30.8 | SQFT | 35.00 | 1,078.00 | 34.00 | 1,047.20 | 17.50 | 539.00 | | 0032 | 729-16-00300 | Object Marker Assembly (Type 3) | 5 | EACH | 125.00 | 625.00 | 110.00 | 550.00 | 201.00 | 1,005.00 | | 0033 | 729-22-00200 | Square Tubing Post with 2-1/4" Omni-Directional Anchor | 4 | EACH | 220.00 | 880.00 | 180.00 | 720.00 | 310.00 | 1,240.00 | | 0034 | 731-02-00100 | Reflectorized Raised Pavement Markers | 107 | EACH | 12.50 | 1,337.50 | 16.00 | 1,712.00 | 15.50 | 1,658.50 | | 0035 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 1.619 | MILE | 10,000.00 | 16,190.00 | 9,000.00 | 14,571.00 | 8,800.00 | 14,247.20 | | 0036 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.81 | MILE | 3,100.00 | 2,511.00 | 6,000.00 | 4,860.00 | 5,150.00 | 4,171.50 | | 0037 | 732-05-00100 | Removal of Existing Markings | 0.81 | MILE | 9,500.00 | 7,695.00 | 14,000.00 | 11,340.00 | 13,400.00 | 10,854.00 | | 0038 | 735-01-00100 | Mailboxes | 2 | EACH | 25.00 | 50.00 | 25.00 | 50.00 | 75.00 | 150.00 | | 0039 | 735-02-00100 | Mailbox Supports (Single) | 2 | EACH | 250.00 | 500.00 | 200.00 | 400.00 | 325.00 | 650.00 | | 0040 | 739-01-00100 | Hydro-Seeding | 10.18 | ACRE | 2,500.00 | 25,450.00 | 2,000.00 | 20,360.00 | 2,050.00 | 20,869.00 | | 0041 | 740-01-00100 | Construction Layout | 1 | LUMP | 30,000.00 | 30,000.00 | 13,000.00 | 13,000.00 | 25,000.00 | 25,000.00 | | 0042 | NS-500-00340 | Saw Cutting Asphalt Concrete Pavement | 119,548 | INLF | 0.30 | 35,864.40 | 1.00 | 119,548.00 | 1.20 | 143,457.60 | | 0043 | NS-736-00300 | Portable Flagger System | 1 | LUMP | 100,000.00 | 100,000.00 | 60,000.00 | 60,000.00 | 50,000.00 | 50,000.00 | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 2,729,757.10 | | 3,684,013.30 | | 4,898,627.75 |
|