Bid Tabulations for the Letting of 11/10/2021 LA DOTD Headquarters

Proposal:H.013515.6
Parish:Vermilion
Routes:LA 92
Description:LA 92: PAVEMENT PRESERVATION
Type Construction:DRAINAGE STRUCTURES, MILLING ASPHALT CONCRETE, PAVEMENT PATCHING, IN-PLACE CEMENT TREATED SUBGRADE, LIME TREATMENT, IN-PLACE CEMENT STABILIZED BASE COURSE, ASPHALT SURFACE TREATMENT, ASPHALT CONCRETE OVERLAY, AND RELATED WORK.
Estimated Construction Cost:$3,486,536.92
Rank License BidderConstruction Bid
133663Glenn Lege Construction LLC$3,986,916.37
234356Prairie Contractors LLC$4,253,839.34
351821Elliott Construction, LLC$4,358,416.34


Line
Number
Item NumberItem DescriptionQuantityUnit of
Measure
- 1 -
Glenn Lege Construction LLC
- 2 -
Prairie Contractors LLC
- 3 -
Elliott Construction, LLC
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001202-02-02000Removal of Asphalt Drives 1,632     SQYD9.6115,683.5210.0016,320.0015.0024,480.00
0002202-02-06040Removal of Concrete Box Headwall 2 Barrel 6'x6' Box Culvert1     EACH14,820.7414,820.74325.00325.0020,000.0020,000.00
0003202-02-06100Removal of Concrete Walks and Drives 450     SQYD23.2610,467.0010.004,500.0025.0011,250.00
0004202-02-14500Removal of Guard Rail 382.5   LNFT9.003,442.5016.006,120.0010.003,825.00
0005202-02-32100Removal of Pipe (Cross Drain) 30" RCP8     LNFT74.00592.00275.002,200.0060.00480.00
0006202-02-32120Removal of Pipe (Side Drain) 36" CMP20     LNFT74.001,480.00175.003,500.0060.001,200.00
0007203-07-00100Borrow (Vehicular Measurement) 923     CUYD25.0023,075.0055.0050,765.0025.0023,075.00
0008204-05-00100Temporary Sediment Check Dams (Hay) 34     EACH256.298,713.86150.005,100.00160.005,440.00
0009303-01-00200In-Place Cement Stabilized Base Course (8-1/2" Thick) 45,594     SQYD10.00455,940.009.25421,744.5010.00455,940.00
0010303-02-00100Removal of Existing Patches 4,092     SQYD30.03122,882.761.004,092.005.0020,460.00
0011304-01-00100Lime 224.53  TON260.0058,377.80280.0062,868.40255.0057,255.15
0012304-03-00400Lime Treatment (Type C) (12" Thick) 23,760     SQYD5.30125,928.002.7565,340.005.25124,740.00
0013309-01-12000In-Place Cement Treated Subgrade (12" Thick) 45,594     SQYD9.20419,464.8010.90496,974.608.50387,549.00
0014401-02-00100Aggregate Surface Course (Adjusted Vehicular Measurement) 2,260     CUYD66.37149,996.2031.0070,060.0035.0079,100.00
0015402-03-00100Non-Mainline Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) 100     CUYD110.0011,000.00100.0010,000.0050.005,000.00
0016502-01-00100Asphalt Concrete 14,886.6   TON90.001,339,794.00102.001,518,433.20105.001,563,093.00
0017502-01-00200Asphalt Concrete, Drives, Turnouts and Miscellaneous 1,717     TON102.50175,992.50137.00235,229.00135.00231,795.00
0018507-01-00100Asphalt Material (CRS-2P Emulsion) 29,855     GAL3.1794,640.353.0089,565.003.50104,492.50
0019507-02-00200Aggregate (S2) 43,905     SQYD1.0847,417.401.3057,076.501.5065,857.50
0020507-02-00300Aggregate (S3) 43,905     SQYD0.9340,831.651.1048,295.501.2554,881.25
0021509-01-00100Milling Asphalt Pavement 41,018     SQYD3.40139,461.205.40221,497.204.25174,326.50
0022509-02-00100Contractor Retained Reclaimed Asphalt Pavement -5,508     CUYD0.10-550.800.01-55.080.01-55.08
0023510-01-00200Pavement Patching (12" Minimum Thickness) 291     SQYD125.0036,375.00200.0058,200.00125.0036,375.00
0024701-03-01062Storm Drain Pipe (30" RCP/RPVCP) 8     LNFT210.001,680.00350.002,800.00250.002,000.00
0025701-05-02102Side Drain Pipe (Erosion) (36" RPVCP/CMP) 88     LNFT260.0022,880.00225.0019,800.00175.0015,400.00
0026701-08-00100Relaying Pipe 24" - 48"26     LNFT175.004,550.00375.009,750.00100.002,600.00
0027701-10-01080Reinforced Concrete Pipe (Extension) (30") 8     LNFT210.001,680.00400.003,200.00250.002,000.00
0028701-15-00100Concrete Collar 7     EACH585.004,095.002,000.0014,000.002,500.0017,500.00
0029701-17-00100Trench Excavation Safety Protection (Depth >5 feet) 111     LNFT33.683,738.4830.003,330.0025.002,775.00
0030702-03-00100Catch Basins (CB-01) 2     EACH3,600.007,200.006,500.0013,000.004,600.009,200.00
0031702-08-00200Side Drain Safety End (Type 2) 1     EACH7,200.007,200.008,500.008,500.0012,000.0012,000.00
0032704-01-01020Guard Rail (Single Thrie Beam) (6'-3" post spacing) 200     LNFT64.3512,870.0070.0014,000.0065.0013,000.00
0033704-03-00200Blocked Out Guard Rail - 31", (6'-3" Post Spacing) 112.5   LNFT40.654,573.1335.003,937.5040.004,500.00
0034704-07-00200Guard Rail Transitions (Double Thrie Beam) 100     LNFT130.0913,009.00100.0010,000.00130.0013,000.00
0035704-10-00205Guard Rail End Treatment, MASH, (TL-3 Tangent) 4     EACH4,355.6317,422.524,000.0016,000.004,325.0017,300.00
0036706-02-00200Concrete Drive (6" Thick) 420     SQYD100.0042,000.00130.0054,600.0085.0035,700.00
0037707-04-00100Asphalt Curb 54     LNFT219.6811,862.72200.0010,800.00150.008,100.00
0038711-01-05000Riprap (130 lb, 24" Thick) 53     SQYD100.005,300.00250.0013,250.00150.007,950.00
0039711-04-00100Geotextile Fabric 53     SQYD10.00530.006.00318.0010.00530.00
0040713-01-00100Temporary Signs and Barricades 1     LUMP142,276.80142,276.8075,000.0075,000.00125,000.00125,000.00
0041713-02-00500Temporary Pavement Markings (24" Width) 44     LNFT1.1651.045.00220.001.0044.00
0042713-03-01000Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) 11.624 MILE850.009,880.40700.008,136.80650.007,555.60
0043713-03-02000Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) 11.624 MILE987.2811,476.141.0011.6260.00697.44
0044713-04-01000Temporary Pavement Markings (Solid Line) (4" Width) 23.712 MILE1,451.8834,426.981,500.0035,568.00115.002,726.88
0045713-06-00200Temporary Reflectorized Raised Pavement Markers (Tabs) 1,537     EACH0.62952.942.203,381.402.503,842.50
0046722-02-00100Project Site Laboratory (Equipped) 1     EACH11,716.0011,716.0012,000.0012,000.0020,000.0020,000.00
0047724-01-00100Rumble Strips (Centerline) 2.718 MILE1,742.254,735.441,200.003,261.601,500.004,077.00
0048724-02-00100Rumble Strips (Shoulder/Edge) 5.437 MILE1,742.259,472.611,200.006,524.401,500.008,155.50
0049724-03-00100Rumble Strips (Intersection) 1     EACH2,903.752,903.752,750.002,750.003,000.003,000.00
0050726-01-00100Bedding Material 18.4   CUYD81.281,495.55200.003,680.00100.001,840.00
0051727-01-00100Mobilization 1     LUMP161,125.75161,125.75265,000.00265,000.00400,000.00400,000.00
0052729-16-00200Object Marker Assembly (Type 2) 14     EACH63.88894.3265.00910.0065.00910.00
0053729-16-00300Object Marker Assembly (Type 3) 18     EACH116.152,090.70110.001,980.00115.002,070.00
0054731-01-00100Nonreflectorized Raised Pavement Markers 384     EACH17.426,689.2818.006,912.0030.0011,520.00
0055731-02-00100Reflectorized Raised Pavement Markers 388     EACH10.454,054.6010.003,880.0025.009,700.00
0056732-01-02080Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) 11     LNFT23.23255.5325.00275.0090.00990.00
0057732-02-02000Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) 5.928 MILE5,807.5034,426.865,500.0032,604.007,500.0044,460.00
0058732-03-02000Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) 2.906 MILE2,323.006,750.642,200.006,393.204,600.0013,367.60
0059732-04-19100Plastic Pavement Legends and Symbols (STOP AHEAD) 1     EACH1,742.251,742.251,700.001,700.001,150.001,150.00
0060732-05-00100Removal of Existing Markings 0.028 MILE11,615.00325.2215,000.00420.0025,000.00700.00
0061735-01-00100Mailboxes 68     EACH17.421,184.5615.001,020.0025.001,700.00
0062735-02-00100Mailbox Supports (Single) 77     EACH226.4917,439.73175.0013,475.00225.0017,325.00
0063739-01-00100Hydro-Seeding 0.22  ACRE17,422.503,832.9515,000.003,300.0013,500.002,970.00
0064740-01-00100Construction Layout 1     LUMP22,000.0022,000.0025,000.0025,000.0025,000.0025,000.00
0065805-17-00100Reinforced Concrete Box Culvert Headwall Quantity of Steel = 822 LBS Quantity of Concrete = 11.36 CUYD1     EACH38,300.0038,300.0095,000.0095,000.0035,500.0035,500.00
           
  CONTRACTOR TOTAL   3,986,916.37 4,253,839.34 4,358,416.34