Bid Tabulations for the Letting of 11/10/2021 LA DOTD Headquarters

Proposal:H.012966.6
Parish:Sabine
Routes:US 171
Description:US 171: CONVERSE TO DESOTO P/L
Type Construction:MILLING ASPHALT CONCRETE, PAVEMENT PATCHING, ASPHALT CONCRETE PAVEMENT, AND RELATED WORK.
Estimated Construction Cost:$3,008,274.39
Rank License BidderConstruction Bid
108584Madden Contracting Co., LLC$2,931,845.97
267822Earnest Contracting LLC$3,590,152.25
312312GILCHRIST CONSTRUCTION COMPANY, LLC$3,955,692.70


Line
Number
Item NumberItem DescriptionQuantityUnit of
Measure
- 1 -
Madden Contracting Co., LLC
- 2 -
Earnest Contracting LLC
- 3 -
GILCHRIST CONSTRUCTION COMPANY, LLC
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001202-02-02020Removal of Asphalt Pavement 2,398.4   SQYD1.002,398.4015.0035,976.0010.0023,984.00
0002202-02-06100Removal of Concrete Walks and Drives 86     SQYD25.002,150.0020.001,720.0060.005,160.00
0003202-02-14500Removal of Guard Rail 2,795.5   LNFT13.0036,341.508.0022,364.0010.0027,955.00
0004202-02-32500Removal of Portland Cement Concrete Pavement 1,109     SQYD1.001,109.0015.0016,635.0013.0014,417.00
0005401-02-00100Aggregate Surface Course (Adjusted Vehicular Measurement) 2,399     CUYD27.5065,972.50120.00287,880.0050.00119,950.00
0006502-01-00100Asphalt Concrete 15,640.7   TON110.001,720,477.00120.501,884,704.35135.002,111,494.50
0007502-01-00200Asphalt Concrete, Drives, Turnouts and Miscellaneous 2,204.4   TON70.00154,308.00114.15251,632.26135.00297,594.00
0008509-01-00100Milling Asphalt Pavement 151,270     SQYD1.30196,651.003.00453,810.002.00302,540.00
0009509-02-00100Contractor Retained Reclaimed Asphalt Pavement -3,262     CUYD0.01-32.620.10-326.201.00-3,262.00
0010510-01-00100Pavement Patching (6" Minimum Thickness) 78     SQYD43.503,393.0081.556,360.90184.0014,352.00
0011510-01-00400Pavement Patching (24" Minimum Thickness) 918     SQYD175.00160,650.00181.00166,158.00205.00188,190.00
0012704-01-01020Guard Rail (Single Thrie Beam) (6'-3" post spacing) 600     LNFT80.0048,000.0052.0031,200.0060.0036,000.00
0013704-03-00200Blocked Out Guard Rail - 31", (6'-3" Post Spacing) 1,562.5   LNFT28.0043,750.0038.0059,375.0040.0062,500.00
0014704-05-00300Guard Rail Anchor Sections - 31", (Trailing End) 19.8   LNFT130.002,574.00200.003,960.00215.004,257.00
0015704-07-00200Guard Rail Transitions (Double Thrie Beam) 200     LNFT95.0019,000.00110.0022,000.00120.0024,000.00
0016704-10-00310Guard Rail End Treatment, NCHRP 350 - 31" (TL-3 Flared) 10     EACH3,650.0036,500.003,800.0038,000.003,200.0032,000.00
0017713-01-00100Temporary Signs and Barricades 1     LUMP119,250.00119,250.0035,000.0035,000.00125,000.00125,000.00
0018713-03-01000Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) 15.424 MILE425.006,555.20500.007,712.00200.003,084.80
0019713-03-02000Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) 15.424 MILE600.009,254.40600.009,254.40650.0010,025.60
0020713-04-01000Temporary Pavement Markings (Solid Line) (4" Width) 30.848 MILE900.0027,763.20900.0027,763.201,000.0030,848.00
0021724-02-00100Rumble Strips (Shoulder/Edge) 15.424 MILE1,177.0018,154.051,500.0023,136.001,200.0018,508.80
0022727-01-00100Mobilization 1     LUMP119,250.00119,250.0050,000.0050,000.00355,000.00355,000.00
0023729-16-00300Object Marker Assembly (Type 3) 12     EACH105.001,260.00110.001,320.00125.001,500.00
0024731-01-00100Nonreflectorized Raised Pavement Markers 2,067     EACH11.0022,737.0011.0022,737.0012.0024,804.00
0025731-02-00100Reflectorized Raised Pavement Markers 1,018     EACH6.506,617.006.506,617.007.007,126.00
0026732-01-01040Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) 455     LNFT3.501,592.503.501,592.504.001,820.00
0027732-02-02000Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) 15.424 MILE4,400.0067,865.604,400.0067,865.605,000.0077,120.00
0028732-03-02000Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) 7.712 MILE1,895.0014,614.241,895.0014,614.242,000.0015,424.00
0029732-04-01080Plastic Pavement Legends and Symbols (Arrow - Left Turn) 3     EACH325.00975.00325.00975.00350.001,050.00
0030732-04-15020Plastic Pavement Legends and Symbols (ONLY) 3     EACH325.00975.00325.00975.00350.001,050.00
0031732-05-00100Removal of Existing Markings 0.114 MILE6,500.00741.006,500.00741.0010,000.001,140.00
0032735-01-00100Mailboxes 4     EACH5.0020.00100.00400.0040.00160.00
0033735-02-00100Mailbox Supports (Single) 4     EACH245.00980.00750.003,000.00225.00900.00
0034740-01-00100Construction Layout 1     LUMP20,000.0020,000.0035,000.0035,000.0020,000.0020,000.00
           
  CONTRACTOR TOTAL   2,931,845.97 3,590,152.25 3,955,692.70