Proposal:H.006528.6
Parish:Jefferson Davis
Description:FENTON ELEMENTARY SIDEWALKS
Type Construction:CLEARING AND GRUBBING, GRADING, DRAINAGE STRUCTURES, PORTLAND CEMENT CONCRETE SIDEWALK, AND RELATED WORK.
Estimated Construction Cost:$393,756.50
| Rank | License | Bidder | Construction Bid |
| 1 | 65305 | McCoy Group, LLC | $380,008.32 |
| 2 | 54928 | Womack And Sons Constr. Group LLC | $382,040.05 |
| 3 | 36384 | JOHN BAILEY, INC. | $491,769.00 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - McCoy Group, LLC | - 2 - Womack And Sons Constr. Group LLC | - 3 - JOHN BAILEY, INC. | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 201-01-00100 | Clearing and Grubbing | 2.5 | LUMP | 11,058.54 | 11,058.54 | 3,800.00 | 3,800.00 | 25,000.00 | 25,000.00 | | 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 8,256.02 | 8,256.02 | 5,000.00 | 5,000.00 | 10,000.00 | 10,000.00 | | 0003 | 202-02-02020 | Removal of Asphalt Pavement | 14.1 | SQYD | 36.94 | 520.85 | 38.00 | 535.80 | 75.00 | 1,057.50 | | 0004 | 202-02-06100 | Removal of Concrete Walks and Drives | 673 | SQYD | 30.97 | 20,842.81 | 16.50 | 11,104.50 | 35.00 | 23,555.00 | | 0005 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 804.78 | 804.78 | 9,750.00 | 9,750.00 | 25,000.00 | 25,000.00 | | 0006 | 203-10-00100 | Cleaning Existing Ditches | 50 | LNFT | 60.81 | 3,040.50 | 46.00 | 2,300.00 | 25.00 | 1,250.00 | | 0007 | 204-02-00100 | Temporary Hay Bales | 40 | EACH | 42.71 | 1,708.40 | 14.00 | 560.00 | 20.00 | 800.00 | | 0008 | 204-06-00100 | Temporary Silt Fencing | 3,899 | LNFT | 1.97 | 7,681.03 | 2.25 | 8,772.75 | 3.00 | 11,697.00 | | 0009 | 402-03-00100 | Non-Mainline Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) | 30 | CUYD | 100.00 | 3,000.00 | 108.00 | 3,240.00 | 150.00 | 4,500.00 | | 0010 | 701-04-01000 | Storm Drain Pipe Arch (15" Equiv. RCPA) | 108 | LNFT | 72.79 | 7,861.32 | 78.00 | 8,424.00 | 110.00 | 11,880.00 | | 0011 | 701-04-01020 | Storm Drain Pipe Arch (18" Equiv. RCPA) | 134 | LNFT | 82.43 | 11,045.62 | 94.00 | 12,596.00 | 115.00 | 15,410.00 | | 0012 | 701-04-01040 | Storm Drain Pipe Arch (24" Equiv. RCPA) | 20 | LNFT | 154.38 | 3,087.60 | 190.00 | 3,800.00 | 125.00 | 2,500.00 | | 0013 | 701-06-00020 | Side Drain Pipe Arch (18" Equiv. RCPA) | 128 | LNFT | 84.43 | 10,807.04 | 76.00 | 9,728.00 | 85.00 | 10,880.00 | | 0014 | 701-06-00040 | Side Drain Pipe Arch (24" Equiv. RCPA) | 68 | LNFT | 121.32 | 8,249.76 | 105.00 | 7,140.00 | 95.00 | 6,460.00 | | 0015 | 701-06-00060 | Side Drain Pipe Arch (30" Equiv. RCPA) | 32 | LNFT | 176.55 | 5,649.60 | 141.00 | 4,512.00 | 100.00 | 3,200.00 | | 0016 | 701-07-00300 | Yard Drain Pipe (8") | 96 | LNFT | 88.15 | 8,462.40 | 86.00 | 8,256.00 | 70.00 | 6,720.00 | | 0017 | 701-07-00500 | Yard Drain Pipe (12") | 27 | LNFT | 63.04 | 1,702.08 | 108.00 | 2,916.00 | 65.00 | 1,755.00 | | 0018 | 701-10-01020 | Reinforced Concrete Pipe (Extension) (15") | 7 | LNFT | 126.36 | 884.52 | 390.00 | 2,730.00 | 100.00 | 700.00 | | 0019 | 701-15-00100 | Concrete Collar | 1 | EACH | 1,447.44 | 1,447.44 | 3,000.00 | 3,000.00 | 500.00 | 500.00 | | 0020 | 702-03-00100 | Catch Basins (CB-01) | 5 | EACH | 3,636.82 | 18,184.10 | 3,380.00 | 16,900.00 | 4,500.00 | 22,500.00 | | 0021 | 706-01-00100 | Concrete Walk (4" Thick) | 1,333.1 | SQYD | 54.89 | 73,173.86 | 76.00 | 101,315.60 | 85.00 | 113,313.50 | | 0022 | 706-02-00200 | Concrete Drive (6" Thick) | 988.6 | SQYD | 61.25 | 60,551.75 | 79.00 | 78,099.40 | 95.00 | 93,917.00 | | 0023 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 20,258.03 | 20,258.03 | 6,000.00 | 6,000.00 | 15,000.00 | 15,000.00 | | 0024 | 714-01-00600 | Slab Sodding (St. Augustine) | 1,028 | SQYD | 7.90 | 8,121.20 | 12.00 | 12,336.00 | 12.00 | 12,336.00 | | 0025 | 726-01-00100 | Bedding Material | 48 | CUYD | 75.92 | 3,644.16 | 190.00 | 9,120.00 | 150.00 | 7,200.00 | | 0026 | 727-01-00100 | Mobilization | 1 | LUMP | 36,895.03 | 36,895.03 | 14,150.00 | 14,150.00 | 25,000.00 | 25,000.00 | | 0027 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 156 | LNFT | 35.75 | 5,577.00 | 48.00 | 7,488.00 | 35.00 | 5,460.00 | | 0028 | 739-01-00100 | Hydro-Seeding | 1.5 | ACRE | 1,191.74 | 1,787.61 | 2,500.00 | 3,750.00 | 2,500.00 | 3,750.00 | | 0029 | 740-01-00100 | Construction Layout | 1 | LUMP | 15,000.00 | 15,000.00 | 4,400.00 | 4,400.00 | 2,500.00 | 2,500.00 | | 0030 | 741-11-00200 | Adjusting Water Valve and Meter Box | 2 | EACH | 1,191.74 | 2,383.48 | 1,000.00 | 2,000.00 | 1,200.00 | 2,400.00 | | 0031 | NS-500-00340 | Saw Cutting Asphalt Concrete Pavement | 208 | INLF | 1.36 | 282.88 | 5.75 | 1,196.00 | 4.00 | 832.00 | | 0032 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 424 | INLF | 1.90 | 805.60 | 5.00 | 2,120.00 | 4.00 | 1,696.00 | | 0033 | NS-700-00100 | Trench Drains | 12 | EACH | 939.55 | 11,274.60 | 1,100.00 | 13,200.00 | 1,500.00 | 18,000.00 | | 0034 | NS-719-00002 | Tree Trimming | 1 | LUMP | 5,958.71 | 5,958.71 | 1,800.00 | 1,800.00 | 5,000.00 | 5,000.00 | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 380,008.32 | | 382,040.05 | | 491,769.00 |
|