Proposal:H.013820.6
Parish:Winn
Routes:LA 501
Description:LA 501: IRON BRANCH BRIDGE
Type Construction:CLEARING AND GRUBBING, GRADING, DRAINAGE STRUCTURES, MILLING ASPHALT PAVEMENT, PAVEMENT PATCHING, PAVEMENT WIDENING, ASPHALT CONCRETE OVERLAY, AND RELATED WORK.
Estimated Construction Cost:$775,655.66
| Rank | License | Bidder | Construction Bid |
| 1 | 15099 | Amethyst Construction, Inc. | $905,492.61 |
| 2 | 54928 | Womack And Sons Constr. Group LLC | $929,267.69 |
| 3 | 59705 | David Temple dba Northern State Construction, LLC | $963,664.50 |
| 4 | 49239 | WL Bass Construction Inc. | $1,057,089.00 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Amethyst Construction, Inc. | - 2 - Womack And Sons Constr. Group LLC | - 3 - David Temple dba Northern State Construction, LLC | - 4 - WL Bass Construction Inc. | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 201-01-00100 | Clearing and Grubbing | 0.72 | LUMP | 15,000.00 | 15,000.00 | 17,000.00 | 17,000.00 | 20,000.00 | 20,000.00 | 21,000.00 | 21,000.00 | | 0002 | 202-02-03000 | Removal of Base – Soil Cement, Asphalt, or BCS | 442.5 | SQYD | 16.00 | 7,080.00 | 12.00 | 5,310.00 | 5.00 | 2,212.50 | 5.00 | 2,212.50 | | 0003 | 202-02-32100 | Removal of Pipe (Cross Drain) 24" X 86' CMP | 86 | LNFT | 25.00 | 2,150.00 | 125.00 | 10,750.00 | 10.00 | 860.00 | 12.00 | 1,032.00 | | 0004 | 202-02-32100 | Removal of Pipe (Cross Drain) 3 - 96" X 120' CMP | 360 | LNFT | 25.00 | 9,000.00 | 165.00 | 59,400.00 | 10.00 | 3,600.00 | 18.00 | 6,480.00 | | 0005 | 202-02-32120 | Removal of Pipe (Side Drain) 24" X 28' RMP | 28 | LNFT | 25.00 | 700.00 | 105.00 | 2,940.00 | 10.00 | 280.00 | 23.00 | 644.00 | | 0006 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 55,000.00 | 55,000.00 | 25,000.00 | 25,000.00 | 20,000.00 | 20,000.00 | 38,000.00 | 38,000.00 | | 0007 | 203-10-00100 | Cleaning Existing Ditches | 462 | LNFT | 24.00 | 11,088.00 | 11.00 | 5,082.00 | 20.00 | 9,240.00 | 9.00 | 4,158.00 | | 0008 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 10 | EACH | 220.00 | 2,200.00 | 150.00 | 1,500.00 | 150.00 | 1,500.00 | 150.00 | 1,500.00 | | 0009 | 204-06-00100 | Temporary Silt Fencing | 840 | LNFT | 3.30 | 2,772.00 | 6.00 | 5,040.00 | 2.00 | 1,680.00 | 3.00 | 2,520.00 | | 0010 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 19 | CUYD | 205.00 | 3,895.00 | 400.00 | 7,600.00 | 100.00 | 1,900.00 | 120.00 | 2,280.00 | | 0011 | 402-03-00100 | Non-Mainline Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) | 30 | CUYD | 98.00 | 2,940.00 | 90.00 | 2,700.00 | 100.00 | 3,000.00 | 95.00 | 2,850.00 | | 0012 | 502-01-00100 | Asphalt Concrete | 100 | TON | 235.00 | 23,500.00 | 360.00 | 36,000.00 | 200.00 | 20,000.00 | 255.00 | 25,500.00 | | 0013 | 509-01-00100 | Milling Asphalt Pavement | 980 | SQYD | 9.00 | 8,820.00 | 26.00 | 25,480.00 | 5.00 | 4,900.00 | 15.00 | 14,700.00 | | 0014 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -41 | CUYD | 0.01 | -0.41 | 0.01 | -0.41 | 1.00 | -41.00 | 1.00 | -41.00 | | 0015 | 510-01-00250 | Pavement Patching (14 inch Minimum Thickness) | 523 | SQYD | 135.00 | 70,605.00 | 150.00 | 78,450.00 | 200.00 | 104,600.00 | 205.00 | 107,215.00 | | 0016 | 510-02-00100 | Pavement Widening 14" Minimum Thickness | 159.4 | SQYD | 145.00 | 23,113.00 | 210.00 | 33,474.00 | 200.00 | 31,880.00 | 240.00 | 38,256.00 | | 0017 | 701-01-01001 | Cross Drain Pipe (24" RCP) | 72 | LNFT | 235.00 | 16,920.00 | 400.00 | 28,800.00 | 75.00 | 5,400.00 | 110.00 | 7,920.00 | | 0018 | 701-06-00060 | Side Drain Pipe Arch (30" Equiv. RCPA) | 104 | LNFT | 160.00 | 16,640.00 | 220.00 | 22,880.00 | 100.00 | 10,400.00 | 170.00 | 17,680.00 | | 0019 | 701-17-00100 | Trench Excavation Safety Protection (Depth >5 feet) | 152 | LNFT | 0.01 | 1.52 | 1.00 | 152.00 | 5.00 | 760.00 | 70.00 | 10,640.00 | | 0020 | 711-01-04000 | Riprap (55 lb, 18" Thick) | 678 | SQYD | 70.00 | 47,460.00 | 62.00 | 42,036.00 | 95.00 | 64,410.00 | 110.00 | 74,580.00 | | 0021 | 711-04-00100 | Geotextile Fabric | 678 | SQYD | 3.00 | 2,034.00 | 2.50 | 1,695.00 | 5.00 | 3,390.00 | 3.00 | 2,034.00 | | 0022 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 25,000.00 | 25,000.00 | 12,000.00 | 12,000.00 | 7,500.00 | 7,500.00 | 37,000.00 | 37,000.00 | | 0023 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 0.08 | MILE | 2,000.00 | 160.00 | 2,400.00 | 192.00 | 5,000.00 | 400.00 | 2,000.00 | 160.00 | | 0024 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 0.189 | MILE | 2,000.00 | 378.00 | 2,400.00 | 453.60 | 5,000.00 | 945.00 | 2,000.00 | 378.00 | | 0025 | 716-01-00100 | Mulch (Vegetative) | 1.7 | TON | 1,500.00 | 2,550.00 | 1,000.00 | 1,700.00 | 800.00 | 1,360.00 | 800.00 | 1,360.00 | | 0026 | 717-01-00100 | Seeding | 68 | LB | 32.00 | 2,176.00 | 20.00 | 1,360.00 | 15.00 | 1,020.00 | 15.00 | 1,020.00 | | 0027 | 718-01-00100 | Fertilizer | 840 | LB | 1.50 | 1,260.00 | 2.50 | 2,100.00 | 0.65 | 546.00 | 0.70 | 588.00 | | 0028 | 720-01-01000 | Erosion Control System (Slope Protection) (Type A) | 200 | SQYD | 7.50 | 1,500.00 | 2.50 | 500.00 | 5.00 | 1,000.00 | 5.00 | 1,000.00 | | 0029 | 722-02-00100 | Project Site Laboratory (Equipped) | 1 | EACH | 18,000.00 | 18,000.00 | 30,000.00 | 30,000.00 | 18,500.00 | 18,500.00 | 13,000.00 | 13,000.00 | | 0030 | 726-01-00100 | Bedding Material | 156 | CUYD | 130.00 | 20,280.00 | 120.00 | 18,720.00 | 100.00 | 15,600.00 | 198.00 | 30,888.00 | | 0031 | 727-01-00100 | Mobilization | 1 | LUMP | 50,000.00 | 50,000.00 | 39,150.00 | 39,150.00 | 45,000.00 | 45,000.00 | 105,000.00 | 105,000.00 | | 0032 | 729-16-00200 | Object Marker Assembly (Type 2) | 6 | EACH | 400.00 | 2,400.00 | 150.00 | 900.00 | 100.00 | 600.00 | 80.00 | 480.00 | | 0033 | 731-02-00100 | Reflectorized Raised Pavement Markers | 11 | EACH | 25.00 | 275.00 | 30.00 | 330.00 | 7.00 | 77.00 | 25.00 | 275.00 | | 0034 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 0.189 | MILE | 9,500.00 | 1,795.50 | 11,500.00 | 2,173.50 | 5,000.00 | 945.00 | 9,500.00 | 1,795.50 | | 0035 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.08 | MILE | 5,000.00 | 400.00 | 6,000.00 | 480.00 | 5,000.00 | 400.00 | 5,000.00 | 400.00 | | 0036 | 740-01-00100 | Construction Layout | 1 | LUMP | 12,000.00 | 12,000.00 | 5,200.00 | 5,200.00 | 12,000.00 | 12,000.00 | 25,000.00 | 25,000.00 | | 0037 | 805-15-01700 | Reinforced Concrete Box Culverts (Precast) (7' x 7') | 352 | LNFT | 825.00 | 290,400.00 | 860.00 | 302,720.00 | 1,150.00 | 404,800.00 | 942.00 | 331,584.00 | | 0038 | 805-17-00100 | Reinforced Concrete Box Culvert Headwall (Including Wingwalls)(46 cu. yd. concrete & 7076 lbs. deformed reinforcing steel) | 2 | EACH | 78,000.00 | 156,000.00 | 50,000.00 | 100,000.00 | 71,500.00 | 143,000.00 | 63,000.00 | 126,000.00 | | | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 905,492.61 | | 929,267.69 | | 963,664.50 | | 1,057,089.00 |
|