Proposal:H.011937.6
Parish:Assumption, St. Mary
Routes:US 90
Description:US 90: CABLE BARRIER IN ASSUMP & ST MARY
Type Construction:CABLE BARRIER SYSTEM, AND RELATED WORK.
Estimated Construction Cost:$1,108,326.04
| Rank | License | Bidder | Construction Bid |
| 1 | 58815 | Simmons Erosion Control, Inc. | $807,469.00 |
| 2 | 59016 | MASSANA CONSTRUCTION INC. | $823,019.00 |
| 3 | 67594 | Traffic Commander, LLC | $897,134.10 |
| 4 | 69714 | Roadwrxx, LLC | $1,022,880.00 |
| 5 | 64826 | Highway Safety Systems LLC | $1,028,135.25 |
| 6 | 54928 | Womack And Sons Constr. Group LLC | $1,152,957.75 |
| 7 | 63313 | BRIGGS BROTHERS ENTERPRISES CORPORATION | $1,254,701.47 |
| 8 | 69570 | Bridging The Gap, L.L.C. | $1,926,374.81 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Simmons Erosion Control, Inc. | - 2 - MASSANA CONSTRUCTION INC. | - 3 - Traffic Commander, LLC | - 4 - Roadwrxx, LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 203-07-00100 | Borrow (Vehicular Measurement) | 47 | CUYD | 50.00 | 2,350.00 | 55.00 | 2,585.00 | 125.00 | 5,875.00 | 100.00 | 4,700.00 | | 0002 | 204-06-00100 | Temporary Silt Fencing | 2,460 | LNFT | 1.00 | 2,460.00 | 3.00 | 7,380.00 | 0.01 | 24.60 | 1.00 | 2,460.00 | | 0003 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 19,000.00 | 19,000.00 | 64,321.00 | 64,321.00 | 50,000.00 | 50,000.00 | 100,000.00 | 100,000.00 | | 0004 | 727-01-00100 | Mobilization | 1 | LUMP | 57,710.00 | 57,710.00 | 42,508.00 | 42,508.00 | 85,000.00 | 85,000.00 | 100,000.00 | 100,000.00 | | 0005 | 739-01-00100 | Hydro-Seeding | 18.2 | ACRE | 500.00 | 9,100.00 | 2,600.00 | 47,320.00 | 1,000.00 | 18,200.00 | 100.00 | 1,820.00 | | 0006 | 740-01-00100 | Construction Layout | 1 | LUMP | 18,500.00 | 18,500.00 | 2,500.00 | 2,500.00 | 50,000.00 | 50,000.00 | 5,000.00 | 5,000.00 | | 0007 | NS-704-00001 | High Tension Cable Barrier | 12,335 | LNFT | 23.00 | 283,705.00 | 24.00 | 296,040.00 | 21.50 | 265,202.50 | 30.00 | 370,050.00 | | 0008 | NS-704-00002 | Cable Barrier Gated End Terminal | 8 | EACH | 5,000.00 | 40,000.00 | 5,000.00 | 40,000.00 | 4,075.00 | 32,600.00 | 10,000.00 | 80,000.00 | | 0009 | NS-704-00003 | Concrete Strip | 6,897 | SQYD | 52.00 | 358,644.00 | 45.00 | 310,365.00 | 56.00 | 386,232.00 | 50.00 | 344,850.00 | | 0010 | NS-713-00009 | Portable Changeable Message Sign (with communications) | 4 | EACH | 4,000.00 | 16,000.00 | 2,500.00 | 10,000.00 | 1,000.00 | 4,000.00 | 3,500.00 | 14,000.00 | | | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 807,469.00 | | 823,019.00 | | 897,134.10 | | 1,022,880.00 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 5 - Highway Safety Systems LLC | - 6 - Womack And Sons Constr. Group LLC | - 7 - BRIGGS BROTHERS ENTERPRISES CORPORATION | - 8 - Bridging The Gap, L.L.C. | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 203-07-00100 | Borrow (Vehicular Measurement) | 47 | CUYD | 100.00 | 4,700.00 | 100.00 | 4,700.00 | 25.00 | 1,175.00 | 1,367.18 | 64,257.46 | | 0002 | 204-06-00100 | Temporary Silt Fencing | 2,460 | LNFT | 3.00 | 7,380.00 | 6.10 | 15,006.00 | 2.08 | 5,116.80 | 16.50 | 40,590.00 | | 0003 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 74,000.00 | 74,000.00 | 88,000.00 | 88,000.00 | 15,000.00 | 15,000.00 | 205,753.43 | 205,753.43 | | 0004 | 727-01-00100 | Mobilization | 1 | LUMP | 110,000.00 | 110,000.00 | 24,580.00 | 24,580.00 | 100,000.00 | 100,000.00 | 68,584.48 | 68,584.48 | | 0005 | 739-01-00100 | Hydro-Seeding | 18.2 | ACRE | 2,575.00 | 46,865.00 | 5,150.00 | 93,730.00 | 2,940.00 | 53,508.00 | 7,809.89 | 142,140.00 | | 0006 | 740-01-00100 | Construction Layout | 1 | LUMP | 30,000.00 | 30,000.00 | 3,725.00 | 3,725.00 | 10,000.00 | 10,000.00 | 102,876.71 | 102,876.71 | | 0007 | NS-704-00001 | High Tension Cable Barrier | 12,335 | LNFT | 21.15 | 260,885.25 | 30.05 | 370,666.75 | 38.43 | 474,034.05 | 37.29 | 459,972.15 | | 0008 | NS-704-00002 | Cable Barrier Gated End Terminal | 8 | EACH | 4,750.00 | 38,000.00 | 6,720.00 | 53,760.00 | 7,691.25 | 61,530.00 | 11,635.12 | 93,080.96 | | 0009 | NS-704-00003 | Concrete Strip | 6,897 | SQYD | 65.00 | 448,305.00 | 70.00 | 482,790.00 | 69.46 | 479,065.62 | 100.66 | 694,252.02 | | 0010 | NS-713-00009 | Portable Changeable Message Sign (with communications) | 4 | EACH | 2,000.00 | 8,000.00 | 4,000.00 | 16,000.00 | 13,818.00 | 55,272.00 | 13,716.90 | 54,867.60 | | | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 1,028,135.25 | | 1,152,957.75 | | 1,254,701.47 | | 1,926,374.81 |
|