Proposal:H.001234.6
Parish:West Baton Rouge
Routes:LA 1
Description:LA 1: PORT ALLEN CANAL BR REPL (PH1)(HBI)
Type Construction:CLEARING AND GRUBBING, GRADING, DRAINAGE STRUCTURES, MILLING ASPHALT CONCRETE, SUBGRADE TREATMENT, CLASS II BASE COURSE, ASPHALT CONCRETE PAVEMENT, PORTLAND CEMENT CONCRETE PAVEMENT, PRECAST CONCRETE PILES, TREATED TIMBER PILES, TEMPORARY SHEETING (STEEL), TEMPORARY MECHANICALLY STABILIZED EARTH WALL, MSEW STRUCTURAL EXCAVATION AND BACKFILL, COMPOSITE STEEL AND CONCRETE GIRDER BRIDGES, TRAFFIC SIGNALIZATION, INTELLIGENT TRANSPORTATION SYSTEM, ALTERNATE AA1: TEMPORARY SHEETING (STEEL)(WALL 2); ALTERNATE AA2: MSE WALL, STRUCTURAL EXCAVATION AND BACKFILL (WALL 3); AND RELATED WORK.
Estimated Construction Cost:$62,453,939.07
Maximum Number of Days Allowed for Construction:9999
Calculated Daily User Cost:$20,000.00
| Rank | License | Bidder | Construction Bid | Bidder's Proposed Contract Time | Total Bid |
| 1 | 47347 | Kiewit Louisiana Co. | $57,666,023.33 | 300.00 | $63,666,023.33 |
| 2 | 02179 | Boh Bros. Construction Co., LLC. | $55,407,384.08 | 550.00 | $66,407,384.08 |
| 3 | 55950 | Brown Industrial Construction, LLC | $54,658,711.41 | 600.00 | $66,658,711.41 |
| 4 | 34567 | James Construction Group LLC | $53,241,006.50 | 690.00 | $67,041,006.50 |
| 5 | 39462 | JB JAMES CONSTRUCTION LLC | $58,194,675.58 | 840.00 | $74,994,675.58 |
| 6 | 12312 | GILCHRIST CONSTRUCTION COMPANY, LLC | $64,961,663.58 | 800.00 | $80,961,663.58 |
| 7 | 11170 | W.G. Yates & Sons Construction Co. | $68,256,273.10 | 824.00 | $84,736,273.10 |
| 8 | 54452 | ORION CONSTRUCTION LIMITED PARTNERSHIP | $66,031,140.24 | 1260.00 | $91,231,140.24 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Kiewit Louisiana Co. | - 2 - Boh Bros. Construction Co., LLC. | - 3 - Brown Industrial Construction, LLC | - 4 - James Construction Group LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 1,937,160.00 | 1,937,160.00 | 120,000.00 | 120,000.00 | 900,000.00 | 900,000.00 | 250,000.00 | 250,000.00 | | 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 200,000.00 | 200,000.00 | 60,000.00 | 60,000.00 | 70,000.00 | 70,000.00 | 18,500.00 | 18,500.00 | | 0003 | 202-02-02020 | Removal of Asphalt Pavement | 15,017.1 | SQYD | 8.00 | 120,136.80 | 10.00 | 150,171.00 | 2.30 | 34,539.33 | 7.00 | 105,119.70 | | 0004 | 202-02-03010 | Removal of Base – Recycled PCC or Stone | 20,128.3 | SQYD | 1.00 | 20,128.30 | 5.00 | 100,641.50 | 5.20 | 104,667.16 | 2.00 | 40,256.60 | | 0005 | 202-02-06020 | Removal of Concrete Box Culverts (5'X3'X40' STA 33+20 - LEFT LA 1 SB) | 1 | EACH | 2,800.00 | 2,800.00 | 6,000.00 | 6,000.00 | 4,050.00 | 4,050.00 | 5,000.00 | 5,000.00 | | 0006 | 202-02-06040 | Removal of Concrete Box Headwall (4'X3' STA 16+55 - LEFT LA 1 SB) | 1 | EACH | 900.00 | 900.00 | 3,000.00 | 3,000.00 | 500.00 | 500.00 | 4,000.00 | 4,000.00 | | 0007 | 202-02-06040 | Removal of Concrete Box Headwall (4'X3' STA 26+14- LEFT LA 1 SB) | 1 | EACH | 900.00 | 900.00 | 3,000.00 | 3,000.00 | 500.00 | 500.00 | 4,000.00 | 4,000.00 | | 0008 | 202-02-06040 | Removal of Concrete Box Headwall (4'X3' STA 26+14- LEFT W FRONTAGE RD.) | 1 | EACH | 1,750.00 | 1,750.00 | 3,000.00 | 3,000.00 | 500.00 | 500.00 | 4,000.00 | 4,000.00 | | 0009 | 202-02-06040 | Removal of Concrete Box Headwall (4'X3' STA 33+20 - LEFT LA 1 SB) | 2 | EACH | 500.00 | 1,000.00 | 3,000.00 | 6,000.00 | 500.00 | 1,000.00 | 4,000.00 | 8,000.00 | | 0010 | 202-02-06060 | Removal of Concrete Catch Basin | 1 | EACH | 1,600.00 | 1,600.00 | 1,000.00 | 1,000.00 | 500.00 | 500.00 | 1,200.00 | 1,200.00 | | 0011 | 202-02-06100 | Removal of Concrete Walks and Drives | 610 | SQYD | 5.00 | 3,050.00 | 25.00 | 15,250.00 | 11.00 | 6,710.00 | 6.00 | 3,660.00 | | 0012 | 202-02-06140 | Removal of Curbs (Concrete) | 469.6 | LNFT | 7.00 | 3,287.20 | 15.00 | 7,044.00 | 6.00 | 2,817.60 | 13.00 | 6,104.80 | | 0013 | 202-02-14500 | Removal of Guard Rail | 818.8 | LNFT | 5.00 | 4,094.00 | 10.00 | 8,188.00 | 7.50 | 6,141.00 | 7.50 | 6,141.00 | | 0014 | 202-02-32100 | Removal of Pipe (Cross Drain) () | 323 | LNFT | 20.00 | 6,460.00 | 20.00 | 6,460.00 | 23.00 | 7,429.00 | 20.00 | 6,460.00 | | 0015 | 202-02-32120 | Removal of Pipe (Side Drain) () | 61 | LNFT | 43.00 | 2,623.00 | 20.00 | 1,220.00 | 16.00 | 976.00 | 55.00 | 3,355.00 | | 0016 | 202-02-32180 | Removal of Pipe Headwalls | 5 | EACH | 6.00 | 30.00 | 500.00 | 2,500.00 | 600.00 | 3,000.00 | 1,600.00 | 8,000.00 | | 0017 | 202-02-32500 | Removal of Portland Cement Concrete Pavement | 4,365 | SQYD | 5.00 | 21,825.00 | 5.00 | 21,825.00 | 9.50 | 41,467.50 | 6.00 | 26,190.00 | | 0018 | 202-02-38220 | Removal of Sign Supports | 17 | EACH | 64.00 | 1,088.00 | 50.00 | 850.00 | 50.00 | 850.00 | 50.00 | 850.00 | | 0019 | 202-02-38300 | Removal of Sign and U-Channel Post | 31 | EACH | 135.00 | 4,185.00 | 10.00 | 310.00 | 10.00 | 310.00 | 10.00 | 310.00 | | 0020 | 202-02-38360 | Removal of Sign Faces | 16 | EACH | 72.00 | 1,152.00 | 10.00 | 160.00 | 10.00 | 160.00 | 10.00 | 160.00 | | 0021 | 203-01-00100 | General Excavation | 5,242 | CUYD | 17.00 | 89,114.00 | 30.00 | 157,260.00 | 16.00 | 83,872.00 | 12.00 | 62,904.00 | | 0022 | 203-02-00100 | Drainage Excavation | 2,396 | CUYD | 9.00 | 21,564.00 | 20.00 | 47,920.00 | 14.00 | 33,544.00 | 12.00 | 28,752.00 | | 0023 | 203-03-00100 | Embankment | 20,586 | CUYD | 47.00 | 967,542.00 | 35.00 | 720,510.00 | 28.00 | 576,408.00 | 60.00 | 1,235,160.00 | | 0024 | 203-04-00300 | Nonplastic Embankment (Stone) | 32 | CUYD | 300.00 | 9,600.00 | 200.00 | 6,400.00 | 150.00 | 4,800.00 | 570.00 | 18,240.00 | | 0025 | 203-08-00100 | Geotextile Fabric | 654 | SQYD | 13.00 | 8,502.00 | 10.00 | 6,540.00 | 2.25 | 1,471.50 | 7.00 | 4,578.00 | | 0026 | 203-11-00100 | Settlement Plate Installation and Monitoring | 6 | EACH | 1,100.00 | 6,600.00 | 3,000.00 | 18,000.00 | 3,000.00 | 18,000.00 | 2,000.00 | 12,000.00 | | 0027 | 204-02-00100 | Temporary Hay Bales | 140 | EACH | 27.39 | 3,834.60 | 3.00 | 420.00 | 15.00 | 2,100.00 | 33.00 | 4,620.00 | | 0028 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 6 | EACH | 164.34 | 986.04 | 175.00 | 1,050.00 | 175.00 | 1,050.00 | 172.00 | 1,032.00 | | 0029 | 204-06-00100 | Temporary Silt Fencing | 4,049 | LNFT | 2.14 | 8,664.86 | 3.00 | 12,147.00 | 1.75 | 7,085.75 | 3.00 | 12,147.00 | | 0030 | 204-07-00100 | Temporary Stone Construction Entrance | 2 | EACH | 7,121.53 | 14,243.06 | 12,000.00 | 24,000.00 | 5,500.00 | 11,000.00 | 3,000.00 | 6,000.00 | | 0031 | 302-02-10060 | Class II Base Course (10" Thick) (Crushed Stone, Recycled Portland Cement Concrete, Blended Calcium Sulfate) | 19,074.7 | SQYD | 33.00 | 629,465.10 | 30.00 | 572,241.00 | 15.40 | 293,750.38 | 20.00 | 381,494.00 | | 0032 | 302-02-12060 | Class II Base Course (12" Thick) (Crushed Stone, Recycled Portland Cement Concrete, Blended Calcium Sulfate) | 1,934.6 | SQYD | 43.00 | 83,187.80 | 50.00 | 96,730.00 | 19.70 | 38,111.62 | 30.00 | 58,038.00 | | 0033 | 305-01-04020 | Subgrade Layer (12" Thick) (Treated) | 21,010 | SQYD | 25.00 | 525,250.00 | 20.00 | 420,200.00 | 12.00 | 252,120.00 | 14.00 | 294,140.00 | | 0034 | 401-01-00100 | Aggregate Surface Course (Net Section) | 67.9 | CUYD | 280.00 | 19,012.00 | 100.00 | 6,790.00 | 130.00 | 8,827.00 | 100.00 | 6,790.00 | | 0035 | 402-01-00100 | Mainline Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) | 300 | CUYD | 148.60 | 44,580.00 | 100.00 | 30,000.00 | 100.00 | 30,000.00 | 100.00 | 30,000.00 | | 0036 | 502-01-00100 | Asphalt Concrete | 1,039.1 | TON | 170.30 | 176,958.73 | 150.00 | 155,865.00 | 186.00 | 193,272.60 | 186.00 | 193,272.60 | | 0037 | 502-03-00300 | Asphalt Concrete (6" Thick) | 70 | SQYD | 217.58 | 15,230.60 | 115.00 | 8,050.00 | 350.00 | 24,500.00 | 350.00 | 24,500.00 | | 0038 | 509-01-00100 | Milling Asphalt Pavement | 1,600.3 | SQYD | 20.75 | 33,206.23 | 7.00 | 11,202.10 | 8.50 | 13,602.55 | 8.50 | 13,602.55 | | 0039 | 601-01-00700 | Portland Cement Concrete Pavement (11" Thick) | 13,594.7 | SQYD | 111.00 | 1,509,011.70 | 100.00 | 1,359,470.00 | 88.00 | 1,196,333.60 | 105.00 | 1,427,443.50 | | 0040 | 601-03-01300 | Portland Cement Concrete Shoulder (11" Thick) | 4,414.7 | SQYD | 100.00 | 441,470.00 | 110.00 | 485,617.00 | 90.00 | 397,323.00 | 105.00 | 463,543.50 | | 0041 | 601-04-00100 | Portland Cement Concrete Pavement Coring | 15 | EACH | 1,055.00 | 15,825.00 | 300.00 | 4,500.00 | 120.00 | 1,800.00 | 120.00 | 1,800.00 | | 0042 | 701-01-01001 | Cross Drain Pipe (24" RCP) | 122 | LNFT | 114.00 | 13,908.00 | 200.00 | 24,400.00 | 115.00 | 14,030.00 | 170.00 | 20,740.00 | | 0043 | 701-02-01080 | Cross Drain Pipe Arch (48" Equiv. RCPA) | 75 | LNFT | 140.00 | 10,500.00 | 300.00 | 22,500.00 | 260.00 | 19,500.00 | 250.00 | 18,750.00 | | 0044 | 701-02-01100 | Cross Drain Pipe Arch (54" Equiv. RCPA) | 54 | LNFT | 600.00 | 32,400.00 | 350.00 | 18,900.00 | 300.00 | 16,200.00 | 325.00 | 17,550.00 | | 0045 | 701-03-01022 | Storm Drain Pipe (18" RCP/RPVCP) | 919 | LNFT | 62.00 | 56,978.00 | 100.00 | 91,900.00 | 75.00 | 68,925.00 | 110.00 | 101,090.00 | | 0046 | 701-03-01062 | Storm Drain Pipe (30" RCP/RPVCP) | 190 | LNFT | 92.00 | 17,480.00 | 150.00 | 28,500.00 | 120.00 | 22,800.00 | 145.00 | 27,550.00 | | 0047 | 701-03-02022 | Storm Drain Pipe (Outfall) (18" RPVCP or 24" CMP) | 32 | LNFT | 210.00 | 6,720.00 | 200.00 | 6,400.00 | 78.00 | 2,496.00 | 230.00 | 7,360.00 | | 0048 | 701-04-01020 | Storm Drain Pipe Arch (18" Equiv. RCPA) | 258 | LNFT | 70.00 | 18,060.00 | 115.00 | 29,670.00 | 80.00 | 20,640.00 | 130.00 | 33,540.00 | | 0049 | 701-04-01120 | Storm Drain Pipe Arch (48" Equiv. RCPA) | 652 | LNFT | 195.00 | 127,140.00 | 230.00 | 149,960.00 | 210.00 | 136,920.00 | 250.00 | 163,000.00 | | 0050 | 701-04-02040 | Storm Drain Pipe Arch (Outfall) (24" Equiv. CMPA) | 76 | LNFT | 124.00 | 9,424.00 | 200.00 | 15,200.00 | 130.00 | 9,880.00 | 200.00 | 15,200.00 | | 0051 | 701-04-02120 | Storm Drain Pipe Arch (Outfall) (48" Equiv. CMPA) | 15 | LNFT | 316.00 | 4,740.00 | 550.00 | 8,250.00 | 350.00 | 5,250.00 | 650.00 | 9,750.00 | | 0052 | 701-05-01046 | Side Drain Pipe (18" RCP/RPVCP) | 610 | LNFT | 65.00 | 39,650.00 | 100.00 | 61,000.00 | 67.00 | 40,870.00 | 105.00 | 64,050.00 | | 0053 | 701-05-01082 | Side Drain Pipe (30" RCP/RPVCP/CMP) | 249 | LNFT | 131.00 | 32,619.00 | 150.00 | 37,350.00 | 128.00 | 31,872.00 | 160.00 | 39,840.00 | | 0054 | 701-05-01142 | Side Drain Pipe (48" RCP/RPVCP/CMP) | 63 | LNFT | 422.00 | 26,586.00 | 200.00 | 12,600.00 | 188.00 | 11,844.00 | 230.00 | 14,490.00 | | 0055 | 701-10-01080 | Reinforced Concrete Pipe (Extension) (30") | 12 | LNFT | 500.00 | 6,000.00 | 300.00 | 3,600.00 | 230.00 | 2,760.00 | 500.00 | 6,000.00 | | 0056 | 701-14-00100 | Cleaning Existing Pipes | 60 | LNFT | 56.00 | 3,360.00 | 10.00 | 600.00 | 22.00 | 1,320.00 | 40.00 | 2,400.00 | | 0057 | 701-15-00100 | Concrete Collar | 1 | EACH | 1,550.00 | 1,550.00 | 3,000.00 | 3,000.00 | 2,000.00 | 2,000.00 | 4,000.00 | 4,000.00 | | 0058 | 702-02-00200 | Manholes (R-CB-11) | 3 | EACH | 5,000.00 | 15,000.00 | 12,000.00 | 36,000.00 | 3,500.00 | 10,500.00 | 10,000.00 | 30,000.00 | | 0059 | 702-02-00300 | Manholes (R-CB-11 MOD) | 3 | EACH | 5,300.00 | 15,900.00 | 12,000.00 | 36,000.00 | 4,200.00 | 12,600.00 | 9,000.00 | 27,000.00 | | 0060 | 702-03-00100 | Catch Basins (CB-01) | 18 | EACH | 4,300.00 | 77,400.00 | 5,500.00 | 99,000.00 | 2,800.00 | 50,400.00 | 7,500.00 | 135,000.00 | | 0061 | 704-03-00200 | Blocked Out Guard Rail - 31", (6'-3" Post Spacing) | 1,034.2 | LNFT | 30.00 | 31,026.00 | 40.00 | 41,368.00 | 28.00 | 28,957.60 | 28.00 | 28,957.60 | | 0062 | 704-05-00300 | Guard Rail Anchor Sections - 31", (Trailing End) | 9.9 | LNFT | 136.95 | 1,355.81 | 130.00 | 1,287.00 | 150.00 | 1,485.00 | 95.00 | 940.50 | | 0063 | 704-07-00200 | Guard Rail Transitions (Double Thrie Beam) | 50 | LNFT | 120.52 | 6,026.00 | 100.00 | 5,000.00 | 95.00 | 4,750.00 | 135.00 | 6,750.00 | | 0064 | 704-10-00120 | Guard Rail End Treatment, MASH, (TL-3 Flared) | 1 | EACH | 2,739.05 | 2,739.05 | 2,800.00 | 2,800.00 | 2,800.00 | 2,800.00 | 2,800.00 | 2,800.00 | | 0065 | 704-10-00205 | Guard Rail End Treatment, MASH, (TL-3 Tangent) | 8 | EACH | 2,958.17 | 23,665.36 | 3,000.00 | 24,000.00 | 2,950.00 | 23,600.00 | 2,950.00 | 23,600.00 | | 0066 | 705-06-00400 | Chain Link Fence (7 Foot Height) | 143 | LNFT | 235.56 | 33,685.08 | 215.00 | 30,745.00 | 50.00 | 7,150.00 | 215.00 | 30,745.00 | | 0067 | 706-03-00100 | Incidental Concrete Paving (4" Thick) | 229.2 | SQYD | 60.00 | 13,752.00 | 65.00 | 14,898.00 | 65.00 | 14,898.00 | 60.00 | 13,752.00 | | 0068 | 711-01-03040 | Riprap (30 lb, 24" Thick) | 28.9 | SQYD | 150.00 | 4,335.00 | 160.00 | 4,624.00 | 130.00 | 3,757.00 | 250.00 | 7,225.00 | | 0069 | 711-02-00600 | Riprap (250 lb) | 777 | CUYD | 140.00 | 108,780.00 | 210.00 | 163,170.00 | 125.00 | 97,125.00 | 150.00 | 116,550.00 | | 0070 | 711-04-00100 | Geotextile Fabric | 1,194.9 | SQYD | 3.00 | 3,584.70 | 4.00 | 4,779.60 | 2.30 | 2,748.27 | 4.50 | 5,377.05 | | 0071 | 712-01-00100 | Concrete Cast-in-Place Revetment (4" Thick) | 461 | SQYD | 115.00 | 53,015.00 | 70.00 | 32,270.00 | 93.00 | 42,873.00 | 85.00 | 39,185.00 | | 0072 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 1,525,898.00 | 1,525,898.00 | 450,000.00 | 450,000.00 | 600,000.00 | 600,000.00 | 200,000.00 | 200,000.00 | | 0073 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 480 | LNFT | 1.64 | 787.20 | 1.65 | 792.00 | 1.50 | 720.00 | 1.50 | 720.00 | | 0074 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 2.423 | MILE | 43.82 | 106.18 | 1,000.00 | 2,423.00 | 1,100.00 | 2,665.30 | 1,500.00 | 3,634.50 | | 0075 | 713-03-02020 | Temporary Pavement Markings (Broken Line) (4" W) (10' L) (Type 1 Removable) | 0.596 | MILE | 8,217.15 | 4,897.42 | 8,000.00 | 4,768.00 | 7,550.00 | 4,499.80 | 7,550.00 | 4,499.80 | | 0076 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 6.182 | MILE | 2,739.05 | 16,932.81 | 2,700.00 | 16,691.40 | 2,500.00 | 15,455.00 | 2,500.00 | 15,455.00 | | 0077 | 713-04-01020 | Temporary Pavement Markings (Solid Line) (4"Width) (Type 1 Removable) | 2.118 | MILE | 19,020.75 | 40,285.95 | 16,500.00 | 34,947.00 | 15,000.00 | 31,770.00 | 15,000.00 | 31,770.00 | | 0078 | 713-05-00400 | Temporary Pavement Legends & Symbols (RR Crossing) | 2 | EACH | 273.90 | 547.80 | 270.00 | 540.00 | 250.00 | 500.00 | 250.00 | 500.00 | | 0079 | 713-06-00100 | Temporary Reflectorized Raised Pavement Markers | 71 | EACH | 16.43 | 1,166.53 | 17.00 | 1,207.00 | 15.00 | 1,065.00 | 15.00 | 1,065.00 | | 0080 | 713-07-00100 | Temporary Precast Concrete Barrier (Contractor Furnished) | 354 | EACH | 1,200.00 | 424,800.00 | 1,200.00 | 424,800.00 | 950.00 | 336,300.00 | 435.00 | 153,990.00 | | 0081 | 713-10-00100 | Temporary Precast Concrete Barrier Movement | 95 | EACH | 120.00 | 11,400.00 | 175.00 | 16,625.00 | 85.00 | 8,075.00 | 150.00 | 14,250.00 | | 0082 | 713-11-00100 | Portable Changeable Message Signs | 5 | EACH | 12,000.00 | 60,000.00 | 20,000.00 | 100,000.00 | 5,000.00 | 25,000.00 | 18,000.00 | 90,000.00 | | 0083 | 716-01-00100 | Mulch (Vegetative) | 10.3 | TON | 712.15 | 7,335.15 | 800.00 | 8,240.00 | 435.00 | 4,480.50 | 650.00 | 6,695.00 | | 0084 | 717-01-00100 | Seeding | 199 | LB | 13.15 | 2,616.85 | 14.00 | 2,786.00 | 14.20 | 2,825.80 | 12.00 | 2,388.00 | | 0085 | 718-01-00100 | Fertilizer | 5,080 | LB | 0.50 | 2,540.00 | 0.50 | 2,540.00 | 0.75 | 3,810.00 | 0.46 | 2,336.80 | | 0086 | 718-02-00100 | Agricultural Lime | 9.8 | TON | 219.12 | 2,147.38 | 225.00 | 2,205.00 | 200.00 | 1,960.00 | 200.00 | 1,960.00 | | 0087 | 722-02-00100 | Project Site Laboratory (Equipped) | 1 | EACH | 43,824.80 | 43,824.80 | 55,000.00 | 55,000.00 | 60,000.00 | 60,000.00 | 52,861.86 | 52,861.86 | | 0088 | 725-01-00100 | Temporary Detour Roads | 11,074.2 | SQYD | 110.00 | 1,218,162.00 | 100.00 | 1,107,420.00 | 135.00 | 1,495,017.00 | 120.00 | 1,328,904.00 | | 0089 | 726-01-00100 | Bedding Material | 417 | CUYD | 90.00 | 37,530.00 | 55.00 | 22,935.00 | 96.00 | 40,032.00 | 65.00 | 27,105.00 | | 0090 | 727-01-00100 | Mobilization | 1 | LUMP | 5,690,000.00 | 5,690,000.00 | 4,275,000.00 | 4,275,000.00 | 5,500,000.00 | 5,500,000.00 | 5,324,000.00 | 5,324,000.00 | | 0091 | 728-01-01200 | Jacked or Bored Pipe (36") () | 134 | LNFT | 618.13 | 82,829.42 | 325.00 | 43,550.00 | 800.00 | 107,200.00 | 525.00 | 70,350.00 | | 0092 | 729-01-00100 | Sign (Type A) | 137.5 | SQFT | 38.35 | 5,273.13 | 30.00 | 4,125.00 | 30.00 | 4,125.00 | 30.00 | 4,125.00 | | 0093 | 729-04-00100 | Sign (Type D) | 562 | SQFT | 38.35 | 21,552.70 | 38.00 | 21,356.00 | 38.00 | 21,356.00 | 38.00 | 21,356.00 | | 0094 | 729-06-00100 | Sign (Overhead Mounted) | 155 | SQFT | 38.35 | 5,944.25 | 50.00 | 7,750.00 | 45.00 | 6,975.00 | 45.00 | 6,975.00 | | 0095 | 729-08-00100 | Mounting (2 1/2" Size Post) | 1 | EACH | 1,095.62 | 1,095.62 | 1,250.00 | 1,250.00 | 1,250.00 | 1,250.00 | 1,250.00 | 1,250.00 | | 0096 | 729-08-00200 | Mounting (3 1/2" Size Post) | 2 | EACH | 1,314.74 | 2,629.48 | 1,450.00 | 2,900.00 | 1,450.00 | 2,900.00 | 1,450.00 | 2,900.00 | | 0097 | 729-08-00600 | Mounting (W6 x 12 Size Post) | 8 | EACH | 1,972.12 | 15,776.96 | 1,700.00 | 13,600.00 | 1,700.00 | 13,600.00 | 1,700.00 | 13,600.00 | | 0098 | 729-08-00700 | Mounting (W8 x 18 Size Post) | 8 | EACH | 1,917.34 | 15,338.72 | 2,450.00 | 19,600.00 | 2,450.00 | 19,600.00 | 2,450.00 | 19,600.00 | | 0099 | 729-22-00200 | Square Tubing Post with 2-1/4" Omni-Directional Anchor | 13 | EACH | 115.04 | 1,495.52 | 170.00 | 2,210.00 | 170.00 | 2,210.00 | 170.00 | 2,210.00 | | 0100 | 731-02-00100 | Reflectorized Raised Pavement Markers | 331 | EACH | 16.43 | 5,438.33 | 16.00 | 5,296.00 | 15.00 | 4,965.00 | 15.00 | 4,965.00 | | 0101 | 732-01-01080 | Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) | 340 | LNFT | 27.39 | 9,312.60 | 27.00 | 9,180.00 | 25.00 | 8,500.00 | 25.00 | 8,500.00 | | 0102 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 7.171 | MILE | 7,337.64 | 52,618.22 | 6,500.00 | 46,611.50 | 6,000.00 | 43,026.00 | 6,000.00 | 43,026.00 | | 0103 | 732-02-02040 | Plastic Pavement Striping (Solid Line) (8" Width) (Thermoplastic 90 mil) | 0.073 | MILE | 32,868.60 | 2,399.41 | 30,000.00 | 2,190.00 | 29,000.00 | 2,117.00 | 28,700.00 | 2,095.10 | | 0104 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 2.147 | MILE | 2,739.05 | 5,880.74 | 2,700.00 | 5,796.90 | 2,500.00 | 5,367.50 | 2,500.00 | 5,367.50 | | 0105 | 732-03-02010 | Plastic Pavement Striping (Dotted Line)(4" W)(2' L)(Thermo 90 mil) | 0.027 | MILE | 11,504.01 | 310.61 | 8,500.00 | 229.50 | 12,000.00 | 324.00 | 11,000.00 | 297.00 | | 0106 | 732-04-18000 | Plastic Pavement Legends and Symbols (RR Crossing) | 2 | EACH | 1,643.43 | 3,286.86 | 1,600.00 | 3,200.00 | 1,500.00 | 3,000.00 | 1,500.00 | 3,000.00 | | 0107 | 736-01-00100 | Trenching and Backfilling | 1,466 | LNFT | 6.00 | 8,796.00 | 5.50 | 8,063.00 | 3.90 | 5,717.40 | 5.00 | 7,330.00 | | 0108 | 736-03-00100 | Jacking or Boring | 8,432 | LNFT | 13.43 | 113,241.76 | 8.00 | 67,456.00 | 9.40 | 79,260.80 | 11.50 | 96,968.00 | | 0109 | 736-11-00200 | Conduit (2" HDPE, Schedule 80) | 23,401 | LNFT | 3.43 | 80,265.43 | 1.75 | 40,951.75 | 1.75 | 40,951.75 | 1.75 | 40,951.75 | | 0110 | 736-12-01004 | Conductor (1c, #4 awg) | 2,596 | LNFT | 3.41 | 8,852.36 | 3.25 | 8,437.00 | 2.90 | 7,528.40 | 2.90 | 7,528.40 | | 0111 | 736-12-01006 | Conductor (1c, #6 awg) | 814 | LNFT | 2.34 | 1,904.76 | 2.77 | 2,254.78 | 2.15 | 1,750.10 | 2.00 | 1,628.00 | | 0112 | 736-12-01008 | Conductor (1c, #8 awg) | 2,244 | LNFT | 1.60 | 3,590.40 | 2.55 | 5,722.20 | 1.45 | 3,253.80 | 1.44 | 3,231.36 | | 0113 | 740-01-00100 | Construction Layout | 1 | LUMP | 297,989.00 | 297,989.00 | 200,000.00 | 200,000.00 | 450,000.00 | 450,000.00 | 500,000.00 | 500,000.00 | | 0114 | 802-01-00100 | Structural Excavation (Bents) | 6,211 | CUYD | 65.00 | 403,715.00 | 50.00 | 310,550.00 | 48.00 | 298,128.00 | 30.00 | 186,330.00 | | 0115 | 802-03-00100 | Temporary Sheeting (Steel) (WALL 1) | 15,275 | SQFT | 30.00 | 458,250.00 | 90.00 | 1,374,750.00 | 46.00 | 702,650.00 | 60.00 | 916,500.00 | | 0116 | 802-04-00100 | Mechanically Stabilized Earth Wall (LA 1 SB MSE WALL) | 5,249 | SQFT | 40.00 | 209,960.00 | 125.00 | 656,125.00 | 44.00 | 230,956.00 | 45.00 | 236,205.00 | | 0117 | 802-04-00100 | Mechanically Stabilized Earth Wall (TEMPORARY MSE WALL 1 & 2) | 2,576 | SQFT | 40.00 | 103,040.00 | 105.00 | 270,480.00 | 40.00 | 103,040.00 | 25.00 | 64,400.00 | | 0118 | 802-05-00100 | MSEW Structural Excavation and Backfill | 1 | LUMP | 50,000.00 | 50,000.00 | 150,000.00 | 150,000.00 | 500,000.00 | 500,000.00 | 30,000.00 | 30,000.00 | | 0119 | 804-01-00200 | Precast Concrete Piles (14") | 127 | LNFT | 119.00 | 15,113.00 | 155.00 | 19,685.00 | 120.00 | 15,240.00 | 400.00 | 50,800.00 | | 0120 | 804-01-00400 | Precast Concrete Piles (18") | 33,750 | LNFT | 80.00 | 2,700,000.00 | 69.00 | 2,328,750.00 | 70.00 | 2,362,500.00 | 70.00 | 2,362,500.00 | | 0121 | 804-01-00600 | Precast Concrete Piles (24") | 17,480 | LNFT | 125.00 | 2,185,000.00 | 115.00 | 2,010,200.00 | 110.00 | 1,922,800.00 | 119.00 | 2,080,120.00 | | 0122 | 804-01-00700 | Precast Concrete Piles (30") | 1,344 | LNFT | 320.00 | 430,080.00 | 185.00 | 248,640.00 | 200.00 | 268,800.00 | 178.00 | 239,232.00 | | 0123 | 804-01-00800 | Precast Concrete Piles (36") | 903 | LNFT | 290.00 | 261,870.00 | 248.00 | 223,944.00 | 260.00 | 234,780.00 | 223.00 | 201,369.00 | | 0124 | 804-02-00100 | Treated Timber Piles (Noncoastal Treatment) | 30,555 | LNFT | 25.00 | 763,875.00 | 11.00 | 336,105.00 | 20.00 | 611,100.00 | 12.00 | 366,660.00 | | 0125 | 804-05-00400 | Precast Concrete Test Piles (18") | 2 | EACH | 50,000.00 | 100,000.00 | 39,000.00 | 78,000.00 | 150,000.00 | 300,000.00 | 50,000.00 | 100,000.00 | | 0126 | 804-05-00600 | Precast Concrete Test Piles (24") | 2 | EACH | 50,000.00 | 100,000.00 | 49,700.00 | 99,400.00 | 150,000.00 | 300,000.00 | 58,000.00 | 116,000.00 | | 0127 | 804-14-00100 | Dynamic Monitoring Assistance | 80 | EACH | 245.30 | 19,624.00 | 2,160.00 | 172,800.00 | 2,200.00 | 176,000.00 | 2,000.00 | 160,000.00 | | 0129 | 804-17-00100 | Construction Site Survey | 1 | LUMP | 200,000.00 | 200,000.00 | 40,000.00 | 40,000.00 | 5,000.00 | 5,000.00 | 38,000.00 | 38,000.00 | | 0130 | 804-18-00100 | Vibration Monitoring | 75 | DAY | 602.59 | 45,194.25 | 650.00 | 48,750.00 | 1,500.00 | 112,500.00 | 750.00 | 56,250.00 | | 0131 | 805-01-00200 | Class A1 Concrete (Deck) | 5,159.03 | CUYD | 683.00 | 3,523,617.49 | 1,000.00 | 5,159,030.00 | 820.00 | 4,230,404.60 | 650.00 | 3,353,369.50 | | 0132 | 805-04-00100 | Class MASS(A1) Concrete (Bent Cap) | 1,520.09 | CUYD | 1,250.00 | 1,900,112.50 | 850.00 | 1,292,076.50 | 950.00 | 1,444,085.50 | 1,150.00 | 1,748,103.50 | | 0133 | 805-04-00200 | Class MASS(A1) Concrete (Column) | 1,353.21 | CUYD | 1,100.00 | 1,488,531.00 | 850.00 | 1,150,228.50 | 640.00 | 866,054.40 | 750.00 | 1,014,907.50 | | 0134 | 805-04-00300 | Class MASS(A1) Concrete (Footing) | 4,497.7 | CUYD | 600.00 | 2,698,620.00 | 300.00 | 1,349,310.00 | 350.00 | 1,574,195.00 | 490.00 | 2,203,873.00 | | 0135 | 805-08-01600 | Precast-Prestressed Concrete Girders (Type LG-72) | 5,326 | LNFT | 305.00 | 1,624,430.00 | 400.00 | 2,130,400.00 | 330.00 | 1,757,580.00 | 350.00 | 1,864,100.00 | | 0136 | 805-08-01700 | Precast-Prestressed Concrete Girder (Type LG-78) | 7,668 | LNFT | 420.00 | 3,220,560.00 | 500.00 | 3,834,000.00 | 440.00 | 3,373,920.00 | 450.00 | 3,450,600.00 | | 0137 | 805-16-02700 | Reinforced Concrete Box Culverts (Extension) (4'X3')(EXTENSION) | 100.5 | LNFT | 740.00 | 74,370.00 | 675.00 | 67,837.50 | 640.00 | 64,320.00 | 1,100.00 | 110,550.00 | | 0138 | 805-18-00100 | Concrete Finish (Class 2 Rubbed Finish) | 38,922 | SQFT | 2.50 | 97,305.00 | 1.00 | 38,922.00 | 1.00 | 38,922.00 | 1.00 | 38,922.00 | | 0139 | 805-18-00200 | Concrete Finish (Class 3 Special Finish) | 133,800 | SQFT | 1.00 | 133,800.00 | 0.50 | 66,900.00 | 1.50 | 200,700.00 | 0.50 | 66,900.00 | | 0140 | 806-01-00100 | Deformed Reinforcing Steel | 2,589,893 | LB | 1.16 | 3,004,275.88 | 1.10 | 2,848,882.30 | 1.40 | 3,625,850.20 | 1.00 | 2,589,893.00 | | 0141 | 806-02-00100 | Deformed Reinforcing Steel (Corrosion Resistant) (Stainless Steel) | 13,502 | LB | 5.40 | 72,910.80 | 3.50 | 47,257.00 | 4.00 | 54,008.00 | 4.00 | 54,008.00 | | 0142 | 807-01-00100 | Structural Metalwork (Grade 36) | 1,241 | LUMP | 2,600.00 | 2,600.00 | 3,000.00 | 3,000.00 | 27,700.00 | 27,700.00 | 10,000.00 | 10,000.00 | | 0143 | 807-01-00400 | Structural Metalwork (Grade 50W) | 4,476,017 | LUMP | 9,700,000.00 | 9,700,000.00 | 12,000,000.00 | 12,000,000.00 | 10,760,000.00 | 10,760,000.00 | 11,000,000.00 | 11,000,000.00 | | 0144 | 807-02-00100 | Structural Metalwork (Anchor Bolts) | 4,093 | LUMP | 95,000.00 | 95,000.00 | 85,000.00 | 85,000.00 | 80,000.00 | 80,000.00 | 60,000.00 | 60,000.00 | | 0145 | 807-03-00100 | Structural Metalwork (Access System) | 14,448 | LUMP | 141,000.00 | 141,000.00 | 150,000.00 | 150,000.00 | 120,000.00 | 120,000.00 | 200,000.00 | 200,000.00 | | 0146 | 810-01-00120 | Concrete Bridge Railing (36 inch Height) | 5,432 | LNFT | 87.00 | 472,584.00 | 80.00 | 434,560.00 | 100.00 | 543,200.00 | 70.00 | 380,240.00 | | 0147 | 810-05-00120 | Concrete Roadway Barrier (36 inch Height) | 285 | LNFT | 100.00 | 28,500.00 | 180.00 | 51,300.00 | 220.00 | 62,700.00 | 460.00 | 131,100.00 | | 0148 | 813-01-00100 | Concrete Approach Slabs (Cast-in-Place) | 4,530 | SQFT | 62.00 | 280,860.00 | 60.00 | 271,800.00 | 70.00 | 317,100.00 | 80.00 | 362,400.00 | | 0149 | 814-02-00100 | Elastomeric Bearing Pads (Reinforced) | 1,156 | SFIN | 73.00 | 84,388.00 | 65.00 | 75,140.00 | 78.00 | 90,168.00 | 85.00 | 98,260.00 | | 0150 | 814-03-00100 | Bearing Assembly (Disc) | 24 | EACH | 13,000.00 | 312,000.00 | 11,000.00 | 264,000.00 | 11,000.00 | 264,000.00 | 10,500.00 | 252,000.00 | | 0151 | 815-02-00100 | Sealed Expansion Joint (End Dams and Preformed Neoprene Seal) | 280 | LNFT | 500.00 | 140,000.00 | 320.00 | 89,600.00 | 220.00 | 61,600.00 | 650.00 | 182,000.00 | | 0152 | 815-02-00300 | Sealed Expansion Joint (Modular) | 112 | LNFT | 2,600.00 | 291,200.00 | 2,700.00 | 302,400.00 | 2,400.00 | 268,800.00 | 3,500.00 | 392,000.00 | | 0153 | 816-01-00100 | Bridge Deck Drainage System (Collection) | 1 | LUMP | 50,000.00 | 50,000.00 | 36,000.00 | 36,000.00 | 50,000.00 | 50,000.00 | 30,000.00 | 30,000.00 | | 0154 | 822-01-00100 | Trenching and Backfilling | 250 | LNFT | 10.00 | 2,500.00 | 5.50 | 1,375.00 | 3.85 | 962.50 | 3.86 | 965.00 | | 0155 | 822-02-00100 | Conduit w Conductors (PVC/HDPE) (3/4") (3/4") (1#2 BARE STRANDED GROUND) (G) | 20 | LNFT | 9.94 | 198.80 | 14.50 | 290.00 | 12.00 | 240.00 | 12.00 | 240.00 | | 0157 | 822-02-00300 | Conduit w Conductors (PVC/HDPE) (1-1/4") (WITH PULLTAPE) (SCH40) | 7,656 | LNFT | 20.12 | 154,038.72 | 3.50 | 26,796.00 | 4.00 | 30,624.00 | 3.98 | 30,470.88 | | 0159 | 822-02-01500 | Conduit w Conductors (Rigid Alum) (2") , 1#2 GREEN INSUL. GROUND) | 50 | LNFT | 35.50 | 1,775.00 | 50.00 | 2,500.00 | 14.00 | 700.00 | 14.00 | 700.00 | | 0161 | 822-04-00100 | Jacked or Bored Casing (4" Dia) (PVC/HDPE) | 759 | LNFT | 19.58 | 14,861.22 | 20.00 | 15,180.00 | 25.30 | 19,202.70 | 25.28 | 19,187.52 | | 0162 | 822-04-00200 | Jacked or Bored Casing (6" Dia) (PVC/HDPE) | 1,575 | LNFT | 30.29 | 47,706.75 | 29.00 | 45,675.00 | 44.20 | 69,615.00 | 44.20 | 69,615.00 | | 0163 | 822-08-00200 | Electrical Service Point (Structure) | 1 | EACH | 7,330.26 | 7,330.26 | 16,000.00 | 16,000.00 | 7,200.00 | 7,200.00 | 7,189.00 | 7,189.00 | | 0164 | 822-09-00100 | Electrical System | 1 | LUMP | 136,973.39 | 136,973.39 | 90,000.00 | 90,000.00 | 72,135.00 | 72,135.00 | 72,135.00 | 72,135.00 | | 0165 | 822-11-00100 | Removal and Disposal of Electrical Equipment | 1 | LUMP | 25,765.33 | 25,765.33 | 1,500.00 | 1,500.00 | 5,770.00 | 5,770.00 | 5,769.00 | 5,769.00 | | 0166 | 822-11-00100 | Removal and Disposal of Electrical Equipment (STORAGE OF ELECTRICAL EQUIPMENT) | 1 | LUMP | 4,733.01 | 4,733.01 | 1,500.00 | 1,500.00 | 5,770.00 | 5,770.00 | 5,769.00 | 5,769.00 | | 0167 | 822-12-00100 | Removal and Storage of Light Pole (Ground Mount) (GROUND MOUNT) | 1 | EACH | 8,726.49 | 8,726.49 | 7,500.00 | 7,500.00 | 577.00 | 577.00 | 577.00 | 577.00 | | 0168 | 822-13-00100 | Removal and Disposal of Light Pole Foundation (GROUND MOUNT) | 1 | EACH | 657.37 | 657.37 | 3,650.00 | 3,650.00 | 770.00 | 770.00 | 769.00 | 769.00 | | 0169 | 822-14-00100 | Removal and Disposal of Luminaire | 6 | EACH | 307.65 | 1,845.90 | 70.00 | 420.00 | 38.00 | 228.00 | 38.00 | 228.00 | | 0170 | 822-16-00200 | Underground Junction Box (11" x 18") | 2 | EACH | 1,419.90 | 2,839.80 | 890.00 | 1,780.00 | 713.00 | 1,426.00 | 713.00 | 1,426.00 | | 0171 | 822-17-00400 | Structure Junction Box (Stainless Steel) | 2 | EACH | 1,443.57 | 2,887.14 | 3,200.00 | 6,400.00 | 636.00 | 1,272.00 | 636.00 | 1,272.00 | | 0172 | 822-20-00100 | Disconnect (Service) | 1 | EACH | 2,934.46 | 2,934.46 | 2,000.00 | 2,000.00 | 1,466.00 | 1,466.00 | 1,466.00 | 1,466.00 | | 0173 | 822-21-00100 | Duct Marker (Concrete) | 1 | EACH | 650.79 | 650.79 | 350.00 | 350.00 | 1,028.00 | 1,028.00 | 1,028.00 | 1,028.00 | | 0174 | 822-22-00100 | Underground Marker Tape (3")(Detectable) | 250 | LNFT | 0.77 | 192.50 | 1.40 | 350.00 | 0.35 | 87.50 | 0.35 | 87.50 | | 0175 | NS-203-00100 | Geosynthetic Load Transfer Platform | 13,007 | SQFT | 25.00 | 325,175.00 | 20.00 | 260,140.00 | 25.50 | 331,678.50 | 25.00 | 325,175.00 | | 0176 | NS-500-00300 | Traffic Maintenance Asphalt Concrete | 300 | TON | 219.12 | 65,736.00 | 100.00 | 30,000.00 | 140.00 | 42,000.00 | 95.00 | 28,500.00 | | 0177 | NS-500-00340 | Saw Cutting Asphalt Concrete Pavement | 7,989 | INLF | 1.08 | 8,628.12 | 1.25 | 9,986.25 | 1.40 | 11,184.60 | 0.85 | 6,790.65 | | 0178 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 3,776 | INLF | 1.28 | 4,833.28 | 1.50 | 5,664.00 | 1.80 | 6,796.80 | 1.00 | 3,776.00 | | 0179 | NS-700-00810 | Impact Attenuator (Construction Zone)(Test Level 3) | 5 | EACH | 9,203.21 | 46,016.05 | 17,000.00 | 85,000.00 | 8,500.00 | 42,500.00 | 8,500.00 | 42,500.00 | | 0180 | NS-700-00820 | Impact Attenuator Relocation (Construction Zone) | 4 | EACH | 986.06 | 3,944.24 | 3,000.00 | 12,000.00 | 1,500.00 | 6,000.00 | 2,000.00 | 8,000.00 | | 0181 | NS-729-00029 | Breakaway Square Tubing Sign Support w/ Mowing Pad | 3 | EACH | 1,040.84 | 3,122.52 | 800.00 | 2,400.00 | 750.00 | 2,250.00 | 750.00 | 2,250.00 | | 0182 | NS-ITS-01121 | CCTV Camera Assembly, Furnish and Install with PTZ, Digital | 6 | EACH | 10,507.29 | 63,043.74 | 7,200.00 | 43,200.00 | 6,820.00 | 40,920.00 | 6,820.00 | 40,920.00 | | 0183 | NS-ITS-02120 | Dynamic Message Sign, Furnish & Install, LED Full Matrix, Front Access, Pole Mount | 1 | EACH | 154,296.22 | 154,296.22 | 165,000.00 | 165,000.00 | 140,000.00 | 140,000.00 | 139,998.00 | 139,998.00 | | 0184 | NS-ITS-03255 | Bluetooth Data Collection Unit Ethernet POE, Furnish & Install | 4 | EACH | 8,572.67 | 34,290.68 | 10,000.00 | 40,000.00 | 9,733.00 | 38,932.00 | 9,733.00 | 38,932.00 | | 0185 | NS-ITS-03340 | Vehicle Detector, Radar Right Angle, Furnish & Install | 3 | EACH | 8,046.12 | 24,138.36 | 11,000.00 | 33,000.00 | 6,260.00 | 18,780.00 | 6,260.00 | 18,780.00 | | 0186 | NS-ITS-03501 | CCTV Camera Site, Remove | 1 | EACH | 8,446.06 | 8,446.06 | 10,000.00 | 10,000.00 | 192.00 | 192.00 | 7,839.36 | 7,839.36 | | 0187 | NS-ITS-03521 | DMS Site, Remove | 1 | EACH | 7,081.77 | 7,081.77 | 7,500.00 | 7,500.00 | 3,846.00 | 3,846.00 | 11,493.36 | 11,493.36 | | 0188 | NS-ITS-04000 | Fiber Optic Marker | 10 | EACH | 354.98 | 3,549.80 | 150.00 | 1,500.00 | 204.00 | 2,040.00 | 204.00 | 2,040.00 | | 0189 | NS-ITS-04020 | Fiber Optic Cable, SM, Furnish & Install, 13-48 Fibers | 14,554 | LNFT | 4.61 | 67,093.94 | 2.60 | 37,840.40 | 3.55 | 51,666.70 | 3.53 | 51,375.62 | | 0190 | NS-ITS-04035 | Fiber Optic Fan Out Kits, SM, 12 Strand, Furnish & Install | 16 | EACH | 115.96 | 1,855.36 | 135.00 | 2,160.00 | 100.00 | 1,600.00 | 100.00 | 1,600.00 | | 0191 | NS-ITS-04180 | Fiber Optic Connection, Install, Splice | 64 | EACH | 108.86 | 6,967.04 | 50.00 | 3,200.00 | 95.00 | 6,080.00 | 95.00 | 6,080.00 | | 0192 | NS-ITS-04200 | Fiber Optic Connection, Termination, Furnish & Install | 192 | EACH | 80.46 | 15,448.32 | 60.00 | 11,520.00 | 70.00 | 13,440.00 | 69.61 | 13,365.12 | | 0193 | NS-ITS-04250 | Fiber Optic Drop Cable, SM, 12 Strand, Furnish & Install | 492 | LNFT | 4.73 | 2,327.16 | 2.45 | 1,205.40 | 3.65 | 1,795.80 | 3.64 | 1,790.88 | | 0194 | NS-ITS-04290 | Fiber Optic Patch Cord, SM, 2 Strand, Furnish & Install | 26 | EACH | 66.26 | 1,722.76 | 42.00 | 1,092.00 | 57.00 | 1,482.00 | 57.00 | 1,482.00 | | 0195 | NS-ITS-04360 | Fiber Optic Connection Splice Tray, Furnish & Install | 20 | EACH | 71.00 | 1,420.00 | 80.00 | 1,600.00 | 61.00 | 1,220.00 | 61.00 | 1,220.00 | | 0196 | NS-ITS-04425 | Fiber Optic Connection Patch Panel, Outdoor, Furnish & Install | 5 | EACH | 695.75 | 3,478.75 | 600.00 | 3,000.00 | 598.00 | 2,990.00 | 598.00 | 2,990.00 | | 0197 | NS-ITS-05025 | Splice Closure, Outdoor, Furnish & Install | 5 | EACH | 1,402.15 | 7,010.75 | 1,200.00 | 6,000.00 | 1,205.00 | 6,025.00 | 1,205.00 | 6,025.00 | | 0198 | NS-ITS-06020 | Pullbox, In-ground, Furnish & Install (TYPE F) | 14 | EACH | 1,508.65 | 21,121.10 | 1,700.00 | 23,800.00 | 1,144.00 | 16,016.00 | 1,144.00 | 16,016.00 | | 0199 | NS-ITS-06020 | Pullbox, In-ground, Furnish & Install (TYPE K) | 20 | EACH | 3,632.58 | 72,651.60 | 4,000.00 | 80,000.00 | 2,315.00 | 46,300.00 | 2,315.00 | 46,300.00 | | 0200 | NS-ITS-06120 | Pullbox, Structure Mount, Furnish & Install - New | 4 | EACH | 2,502.58 | 10,010.32 | 3,400.00 | 13,600.00 | 655.00 | 2,620.00 | 655.00 | 2,620.00 | | 0201 | NS-ITS-07020 | ITS Controller Cabinet, Pole Mount, Furnish & Install | 4 | EACH | 17,032.92 | 68,131.68 | 17,000.00 | 68,000.00 | 13,938.00 | 55,752.00 | 13,938.00 | 55,752.00 | | 0202 | NS-ITS-07220 | ITS Controller Cabinet, Pad Mount, Furnish & Install | 1 | EACH | 20,470.28 | 20,470.28 | 20,000.00 | 20,000.00 | 12,986.00 | 12,986.00 | 12,986.00 | 12,986.00 | | 0203 | NS-ITS-08061 | Pole, Foundation & Lowering Device, >= 60', Furnish & Install | 1 | EACH | 93,477.01 | 93,477.01 | 100,000.00 | 100,000.00 | 74,430.00 | 74,430.00 | 74,430.00 | 74,430.00 | | 0204 | NS-ITS-08101 | Pole, Foundation & Lowering Device, >= 100', Furnish & Install | 2 | EACH | 144,356.90 | 288,713.80 | 110,000.00 | 220,000.00 | 87,136.00 | 174,272.00 | 87,136.00 | 174,272.00 | | 0205 | NS-ITS-08180 | Lowering Tool, Electric Hoist Assembly & Clutch Adapter, Furnish | 2 | EACH | 4,614.69 | 9,229.38 | 3,500.00 | 7,000.00 | 3,963.00 | 7,926.00 | 3,963.00 | 7,926.00 | | 0206 | NS-ITS-09080 | Local Ethernet Switch, Furnish & Install | 5 | EACH | 2,100.27 | 10,501.35 | 2,000.00 | 10,000.00 | 1,645.00 | 8,225.00 | 1,645.00 | 8,225.00 | | 0207 | NS-ITS-09140 | Gigabit Ethernet Aggregation Switch, Furnish & Install | 1 | EACH | 8,756.07 | 8,756.07 | 12,000.00 | 12,000.00 | 10,200.00 | 10,200.00 | 10,200.00 | 10,200.00 | | 0208 | NS-ITS-09380 | Point-to-Point Microwave Ethernet Data Radio, Install | 1 | EACH | 1,774.88 | 1,774.88 | 840.00 | 840.00 | 4,115.00 | 4,115.00 | 4,115.00 | 4,115.00 | | 0209 | NS-ITS-09440 | Point-to-Point Microwave Ethernet Data Radio Antenna, Install | 1 | EACH | 1,301.57 | 1,301.57 | 200.00 | 200.00 | 3,292.00 | 3,292.00 | 3,292.00 | 3,292.00 | | 0210 | NS-ITS-10060 | Electrical Service | 5 | EACH | 7,992.88 | 39,964.40 | 7,000.00 | 35,000.00 | 5,459.00 | 27,295.00 | 5,459.00 | 27,295.00 | | 0211 | NS-ITS-10220 | Power Surge Suppressor, Furnish & Install | 15 | EACH | 381.01 | 5,715.15 | 250.00 | 3,750.00 | 224.00 | 3,360.00 | 224.00 | 3,360.00 | | 0212 | NS-ITS-10340 | Data Surge Suppressor, Furnish & Install | 19 | EACH | 345.51 | 6,564.69 | 235.00 | 4,465.00 | 105.00 | 1,995.00 | 105.00 | 1,995.00 | | 0213 | NS-ITS-10362 | Power Surge Suppressor (ITS Cabinet), Furnish & Install | 5 | EACH | 975.00 | 4,875.00 | 1,000.00 | 5,000.00 | 3,849.00 | 19,245.00 | 3,849.00 | 19,245.00 | | 0214 | NS-ITS-12000 | Communications System Integration | 1 | LUMP | 12,867.88 | 12,867.88 | 9,000.00 | 9,000.00 | 49,385.00 | 49,385.00 | 49,385.00 | 49,385.00 | | 0215 | NS-ITS-12020 | TMC Integration | 1 | LUMP | 10,649.28 | 10,649.28 | 8,000.00 | 8,000.00 | 21,165.00 | 21,165.00 | 21,165.00 | 21,165.00 | | 0216 | NS-ITS-13200 | As-Builts | 1 | LUMP | 3,017.29 | 3,017.29 | 5,500.00 | 5,500.00 | 1,930.00 | 1,930.00 | 1,930.00 | 1,930.00 | | 0217 | NS-ITS-15320 | 2" Rigid Galvanized Steel Conduit | 160 | LNFT | 64.78 | 10,364.80 | 50.00 | 8,000.00 | 22.95 | 3,672.00 | 55.00 | 8,800.00 | | 0218 | NS-ITS-15640 | 4" FRE Conduit | 2,552 | LNFT | 128.38 | 327,625.76 | 120.00 | 306,240.00 | 140.00 | 357,280.00 | 139.57 | 356,182.64 | | 0222 | 804-09-00400 | Static Load Test (Precast Concrete Piles (18")) | 2 | EACH | 50,006.49 | 100,012.98 | 84,000.00 | 168,000.00 | 120,000.00 | 240,000.00 | 75,500.00 | 151,000.00 | | 0223 | 804-09-00600 | Static Load Test (Precast Concrete Piles (24")) | 2 | EACH | 33,572.19 | 67,144.38 | 106,600.00 | 213,200.00 | 120,000.00 | 240,000.00 | 77,000.00 | 154,000.00 | | 0224 | 808-01-00300 | Steel Grid Flooring TYPE W-19-4 (2*3/16) STEEL | 598 | SQFT | 60.23 | 36,017.54 | 70.00 | 41,860.00 | 79.00 | 47,242.00 | 100.00 | 59,800.00 | | | | SUBTOTAL GENERAL | | | | 57,581,783 | | 55,197,504 | | 54,495,191 | | 52,973,647 | | | | | | | | | | | | | | | | | Alternate AA2 | ALTERNATE AA2 (TEMPORARY MSE WALL) | | | | | | | | | | | | | | | | | | | | | | | | | | 0220 | 802-04-00100 | Mechanically Stabilized Earth Wall (TEMPORARY MSE WALL 3) | 1,856 | SQFT | 40.00 | 74,240.00 | 105.00 | 194,880.00 | 45.00 | 83,520.00 | 140.00 | 259,840.00 | | 0221 | 802-05-00100 | MSEW Structural Excavation and Backfill (TEMPORARY MSE WALL 3) | 1 | LUMP | 10,000.00 | 10,000.00 | 15,000.00 | 15,000.00 | 80,000.00 | 80,000.00 | 7,520.00 | 7,520.00 | | | | SUBTOTAL ALT AA2 | | | | 84,240.00 | | 209,880.00 | | 163,520.00 | | 267,360.00 | | | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 57,666,023.33 | | 55,407,384.08 | | 54,658,711.41 | | 53,241,006.50 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 5 - JB JAMES CONSTRUCTION LLC | - 6 - GILCHRIST CONSTRUCTION COMPANY, LLC | - 7 - W.G. Yates & Sons Construction Co. | - 8 - ORION CONSTRUCTION LIMITED PARTNERSHIP | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 1,500,000.00 | 1,500,000.00 | 500,000.00 | 500,000.00 | 250,000.00 | 250,000.00 | 130,000.00 | 130,000.00 | | 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 67,000.00 | 67,000.00 | 250,000.00 | 250,000.00 | 50,000.00 | 50,000.00 | 33,000.00 | 33,000.00 | | 0003 | 202-02-02020 | Removal of Asphalt Pavement | 15,017.1 | SQYD | 14.00 | 210,239.40 | 9.00 | 135,153.90 | 8.00 | 120,136.80 | 7.00 | 105,119.70 | | 0004 | 202-02-03010 | Removal of Base – Recycled PCC or Stone | 20,128.3 | SQYD | 5.00 | 100,641.50 | 8.00 | 161,026.40 | 6.00 | 120,769.80 | 9.00 | 181,154.70 | | 0005 | 202-02-06020 | Removal of Concrete Box Culverts (5'X3'X40' STA 33+20 - LEFT LA 1 SB) | 1 | EACH | 2,500.00 | 2,500.00 | 8,000.00 | 8,000.00 | 8,500.00 | 8,500.00 | 6,100.00 | 6,100.00 | | 0006 | 202-02-06040 | Removal of Concrete Box Headwall (4'X3' STA 16+55 - LEFT LA 1 SB) | 1 | EACH | 650.00 | 650.00 | 1,100.00 | 1,100.00 | 1,750.00 | 1,750.00 | 3,100.00 | 3,100.00 | | 0007 | 202-02-06040 | Removal of Concrete Box Headwall (4'X3' STA 26+14- LEFT LA 1 SB) | 1 | EACH | 650.00 | 650.00 | 1,100.00 | 1,100.00 | 1,750.00 | 1,750.00 | 3,100.00 | 3,100.00 | | 0008 | 202-02-06040 | Removal of Concrete Box Headwall (4'X3' STA 26+14- LEFT W FRONTAGE RD.) | 1 | EACH | 650.00 | 650.00 | 1,100.00 | 1,100.00 | 1,750.00 | 1,750.00 | 3,100.00 | 3,100.00 | | 0009 | 202-02-06040 | Removal of Concrete Box Headwall (4'X3' STA 33+20 - LEFT LA 1 SB) | 2 | EACH | 650.00 | 1,300.00 | 1,100.00 | 2,200.00 | 1,750.00 | 3,500.00 | 3,100.00 | 6,200.00 | | 0010 | 202-02-06060 | Removal of Concrete Catch Basin | 1 | EACH | 400.00 | 400.00 | 1,100.00 | 1,100.00 | 1,300.00 | 1,300.00 | 1,600.00 | 1,600.00 | | 0011 | 202-02-06100 | Removal of Concrete Walks and Drives | 610 | SQYD | 10.00 | 6,100.00 | 15.00 | 9,150.00 | 14.00 | 8,540.00 | 26.00 | 15,860.00 | | 0012 | 202-02-06140 | Removal of Curbs (Concrete) | 469.6 | LNFT | 10.00 | 4,696.00 | 7.00 | 3,287.20 | 10.00 | 4,696.00 | 15.50 | 7,278.80 | | 0013 | 202-02-14500 | Removal of Guard Rail | 818.8 | LNFT | 7.50 | 6,141.00 | 8.00 | 6,550.40 | 12.50 | 10,235.00 | 8.00 | 6,550.40 | | 0014 | 202-02-32100 | Removal of Pipe (Cross Drain) () | 323 | LNFT | 35.00 | 11,305.00 | 32.00 | 10,336.00 | 20.00 | 6,460.00 | 40.00 | 12,920.00 | | 0015 | 202-02-32120 | Removal of Pipe (Side Drain) () | 61 | LNFT | 30.00 | 1,830.00 | 30.00 | 1,830.00 | 25.00 | 1,525.00 | 31.00 | 1,891.00 | | 0016 | 202-02-32180 | Removal of Pipe Headwalls | 5 | EACH | 500.00 | 2,500.00 | 1,500.00 | 7,500.00 | 400.00 | 2,000.00 | 2,100.00 | 10,500.00 | | 0017 | 202-02-32500 | Removal of Portland Cement Concrete Pavement | 4,365 | SQYD | 10.00 | 43,650.00 | 10.50 | 45,832.50 | 15.00 | 65,475.00 | 17.00 | 74,205.00 | | 0018 | 202-02-38220 | Removal of Sign Supports | 17 | EACH | 50.00 | 850.00 | 55.00 | 935.00 | 675.00 | 11,475.00 | 410.00 | 6,970.00 | | 0019 | 202-02-38300 | Removal of Sign and U-Channel Post | 31 | EACH | 10.00 | 310.00 | 11.00 | 341.00 | 25.00 | 775.00 | 17.40 | 539.40 | | 0020 | 202-02-38360 | Removal of Sign Faces | 16 | EACH | 10.00 | 160.00 | 11.00 | 176.00 | 310.00 | 4,960.00 | 116.25 | 1,860.00 | | 0021 | 203-01-00100 | General Excavation | 5,242 | CUYD | 25.00 | 131,050.00 | 10.00 | 52,420.00 | 10.00 | 52,420.00 | 7.00 | 36,694.00 | | 0022 | 203-02-00100 | Drainage Excavation | 2,396 | CUYD | 20.00 | 47,920.00 | 20.00 | 47,920.00 | 20.00 | 47,920.00 | 26.00 | 62,296.00 | | 0023 | 203-03-00100 | Embankment | 20,586 | CUYD | 35.00 | 720,510.00 | 38.00 | 782,268.00 | 30.00 | 617,580.00 | 15.00 | 308,790.00 | | 0024 | 203-04-00300 | Nonplastic Embankment (Stone) | 32 | CUYD | 175.00 | 5,600.00 | 200.00 | 6,400.00 | 180.00 | 5,760.00 | 110.00 | 3,520.00 | | 0025 | 203-08-00100 | Geotextile Fabric | 654 | SQYD | 5.00 | 3,270.00 | 5.00 | 3,270.00 | 7.00 | 4,578.00 | 5.00 | 3,270.00 | | 0026 | 203-11-00100 | Settlement Plate Installation and Monitoring | 6 | EACH | 1,700.00 | 10,200.00 | 1,800.00 | 10,800.00 | 3,500.00 | 21,000.00 | 3,000.00 | 18,000.00 | | 0027 | 204-02-00100 | Temporary Hay Bales | 140 | EACH | 25.00 | 3,500.00 | 27.00 | 3,780.00 | 16.00 | 2,240.00 | 20.00 | 2,800.00 | | 0028 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 6 | EACH | 150.00 | 900.00 | 160.00 | 960.00 | 160.00 | 960.00 | 210.00 | 1,260.00 | | 0029 | 204-06-00100 | Temporary Silt Fencing | 4,049 | LNFT | 3.00 | 12,147.00 | 2.25 | 9,110.25 | 3.00 | 12,147.00 | 3.00 | 12,147.00 | | 0030 | 204-07-00100 | Temporary Stone Construction Entrance | 2 | EACH | 5,000.00 | 10,000.00 | 6,000.00 | 12,000.00 | 15,000.00 | 30,000.00 | 6,000.00 | 12,000.00 | | 0031 | 302-02-10060 | Class II Base Course (10" Thick) (Crushed Stone, Recycled Portland Cement Concrete, Blended Calcium Sulfate) | 19,074.7 | SQYD | 32.00 | 610,390.40 | 28.00 | 534,091.60 | 30.00 | 572,241.00 | 30.00 | 572,241.00 | | 0032 | 302-02-12060 | Class II Base Course (12" Thick) (Crushed Stone, Recycled Portland Cement Concrete, Blended Calcium Sulfate) | 1,934.6 | SQYD | 35.00 | 67,711.00 | 38.00 | 73,514.80 | 48.00 | 92,860.80 | 40.00 | 77,384.00 | | 0033 | 305-01-04020 | Subgrade Layer (12" Thick) (Treated) | 21,010 | SQYD | 19.00 | 399,190.00 | 18.00 | 378,180.00 | 21.00 | 441,210.00 | 21.00 | 441,210.00 | | 0034 | 401-01-00100 | Aggregate Surface Course (Net Section) | 67.9 | CUYD | 120.00 | 8,148.00 | 100.00 | 6,790.00 | 175.00 | 11,882.50 | 110.00 | 7,469.00 | | 0035 | 402-01-00100 | Mainline Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) | 300 | CUYD | 200.00 | 60,000.00 | 65.00 | 19,500.00 | 150.00 | 45,000.00 | 100.00 | 30,000.00 | | 0036 | 502-01-00100 | Asphalt Concrete | 1,039.1 | TON | 138.00 | 143,395.80 | 225.00 | 233,797.50 | 142.00 | 147,552.20 | 89.86 | 93,373.53 | | 0037 | 502-03-00300 | Asphalt Concrete (6" Thick) | 70 | SQYD | 100.00 | 7,000.00 | 100.00 | 7,000.00 | 103.00 | 7,210.00 | 35.00 | 2,450.00 | | 0038 | 509-01-00100 | Milling Asphalt Pavement | 1,600.3 | SQYD | 6.00 | 9,601.80 | 8.50 | 13,602.55 | 6.50 | 10,401.95 | 2.23 | 3,568.67 | | 0039 | 601-01-00700 | Portland Cement Concrete Pavement (11" Thick) | 13,594.7 | SQYD | 80.00 | 1,087,576.00 | 115.00 | 1,563,390.50 | 110.00 | 1,495,417.00 | 109.00 | 1,481,822.30 | | 0040 | 601-03-01300 | Portland Cement Concrete Shoulder (11" Thick) | 4,414.7 | SQYD | 80.00 | 353,176.00 | 115.00 | 507,690.50 | 125.00 | 551,837.50 | 109.00 | 481,202.30 | | 0041 | 601-04-00100 | Portland Cement Concrete Pavement Coring | 15 | EACH | 200.00 | 3,000.00 | 500.00 | 7,500.00 | 255.00 | 3,825.00 | 256.00 | 3,840.00 | | 0042 | 701-01-01001 | Cross Drain Pipe (24" RCP) | 122 | LNFT | 160.00 | 19,520.00 | 130.00 | 15,860.00 | 210.00 | 25,620.00 | 210.00 | 25,620.00 | | 0043 | 701-02-01080 | Cross Drain Pipe Arch (48" Equiv. RCPA) | 75 | LNFT | 300.00 | 22,500.00 | 265.00 | 19,875.00 | 585.00 | 43,875.00 | 360.00 | 27,000.00 | | 0044 | 701-02-01100 | Cross Drain Pipe Arch (54" Equiv. RCPA) | 54 | LNFT | 400.00 | 21,600.00 | 375.00 | 20,250.00 | 490.00 | 26,460.00 | 500.00 | 27,000.00 | | 0045 | 701-03-01022 | Storm Drain Pipe (18" RCP/RPVCP) | 919 | LNFT | 100.00 | 91,900.00 | 115.00 | 105,685.00 | 85.00 | 78,115.00 | 105.00 | 96,495.00 | | 0046 | 701-03-01062 | Storm Drain Pipe (30" RCP/RPVCP) | 190 | LNFT | 130.00 | 24,700.00 | 185.00 | 35,150.00 | 125.00 | 23,750.00 | 160.00 | 30,400.00 | | 0047 | 701-03-02022 | Storm Drain Pipe (Outfall) (18" RPVCP or 24" CMP) | 32 | LNFT | 90.00 | 2,880.00 | 135.00 | 4,320.00 | 150.00 | 4,800.00 | 185.00 | 5,920.00 | | 0048 | 701-04-01020 | Storm Drain Pipe Arch (18" Equiv. RCPA) | 258 | LNFT | 90.00 | 23,220.00 | 125.00 | 32,250.00 | 105.00 | 27,090.00 | 130.00 | 33,540.00 | | 0049 | 701-04-01120 | Storm Drain Pipe Arch (48" Equiv. RCPA) | 652 | LNFT | 220.00 | 143,440.00 | 290.00 | 189,080.00 | 240.00 | 156,480.00 | 305.00 | 198,860.00 | | 0050 | 701-04-02040 | Storm Drain Pipe Arch (Outfall) (24" Equiv. CMPA) | 76 | LNFT | 130.00 | 9,880.00 | 165.00 | 12,540.00 | 140.00 | 10,640.00 | 170.00 | 12,920.00 | | 0051 | 701-04-02120 | Storm Drain Pipe Arch (Outfall) (48" Equiv. CMPA) | 15 | LNFT | 280.00 | 4,200.00 | 480.00 | 7,200.00 | 565.00 | 8,475.00 | 450.00 | 6,750.00 | | 0052 | 701-05-01046 | Side Drain Pipe (18" RCP/RPVCP) | 610 | LNFT | 80.00 | 48,800.00 | 102.00 | 62,220.00 | 85.00 | 51,850.00 | 115.00 | 70,150.00 | | 0053 | 701-05-01082 | Side Drain Pipe (30" RCP/RPVCP/CMP) | 249 | LNFT | 130.00 | 32,370.00 | 170.00 | 42,330.00 | 130.00 | 32,370.00 | 210.00 | 52,290.00 | | 0054 | 701-05-01142 | Side Drain Pipe (48" RCP/RPVCP/CMP) | 63 | LNFT | 250.00 | 15,750.00 | 275.00 | 17,325.00 | 240.00 | 15,120.00 | 310.00 | 19,530.00 | | 0055 | 701-10-01080 | Reinforced Concrete Pipe (Extension) (30") | 12 | LNFT | 80.00 | 960.00 | 320.00 | 3,840.00 | 400.00 | 4,800.00 | 210.00 | 2,520.00 | | 0056 | 701-14-00100 | Cleaning Existing Pipes | 60 | LNFT | 60.00 | 3,600.00 | 50.00 | 3,000.00 | 200.00 | 12,000.00 | 26.00 | 1,560.00 | | 0057 | 701-15-00100 | Concrete Collar | 1 | EACH | 600.00 | 600.00 | 3,000.00 | 3,000.00 | 2,500.00 | 2,500.00 | 2,000.00 | 2,000.00 | | 0058 | 702-02-00200 | Manholes (R-CB-11) | 3 | EACH | 6,900.00 | 20,700.00 | 6,000.00 | 18,000.00 | 8,500.00 | 25,500.00 | 6,800.00 | 20,400.00 | | 0059 | 702-02-00300 | Manholes (R-CB-11 MOD) | 3 | EACH | 8,600.00 | 25,800.00 | 6,500.00 | 19,500.00 | 8,500.00 | 25,500.00 | 7,100.00 | 21,300.00 | | 0060 | 702-03-00100 | Catch Basins (CB-01) | 18 | EACH | 3,250.00 | 58,500.00 | 5,200.00 | 93,600.00 | 7,775.00 | 139,950.00 | 4,700.00 | 84,600.00 | | 0061 | 704-03-00200 | Blocked Out Guard Rail - 31", (6'-3" Post Spacing) | 1,034.2 | LNFT | 28.00 | 28,957.60 | 30.00 | 31,026.00 | 24.00 | 24,820.80 | 20.00 | 20,684.00 | | 0062 | 704-05-00300 | Guard Rail Anchor Sections - 31", (Trailing End) | 9.9 | LNFT | 95.00 | 940.50 | 100.00 | 990.00 | 130.00 | 1,287.00 | 125.00 | 1,237.50 | | 0063 | 704-07-00200 | Guard Rail Transitions (Double Thrie Beam) | 50 | LNFT | 135.00 | 6,750.00 | 140.00 | 7,000.00 | 115.00 | 5,750.00 | 125.00 | 6,250.00 | | 0064 | 704-10-00120 | Guard Rail End Treatment, MASH, (TL-3 Flared) | 1 | EACH | 2,800.00 | 2,800.00 | 2,900.00 | 2,900.00 | 2,550.00 | 2,550.00 | 2,750.00 | 2,750.00 | | 0065 | 704-10-00205 | Guard Rail End Treatment, MASH, (TL-3 Tangent) | 8 | EACH | 2,950.00 | 23,600.00 | 3,100.00 | 24,800.00 | 2,800.00 | 22,400.00 | 3,000.00 | 24,000.00 | | 0066 | 705-06-00400 | Chain Link Fence (7 Foot Height) | 143 | LNFT | 215.00 | 30,745.00 | 225.00 | 32,175.00 | 65.00 | 9,295.00 | 70.00 | 10,010.00 | | 0067 | 706-03-00100 | Incidental Concrete Paving (4" Thick) | 229.2 | SQYD | 70.00 | 16,044.00 | 110.00 | 25,212.00 | 100.00 | 22,920.00 | 71.00 | 16,273.20 | | 0068 | 711-01-03040 | Riprap (30 lb, 24" Thick) | 28.9 | SQYD | 120.00 | 3,468.00 | 175.00 | 5,057.50 | 90.00 | 2,601.00 | 152.00 | 4,392.80 | | 0069 | 711-02-00600 | Riprap (250 lb) | 777 | CUYD | 230.00 | 178,710.00 | 90.00 | 69,930.00 | 110.00 | 85,470.00 | 205.00 | 159,285.00 | | 0070 | 711-04-00100 | Geotextile Fabric | 1,194.9 | SQYD | 3.00 | 3,584.70 | 4.00 | 4,779.60 | 7.00 | 8,364.30 | 5.00 | 5,974.50 | | 0071 | 712-01-00100 | Concrete Cast-in-Place Revetment (4" Thick) | 461 | SQYD | 155.00 | 71,455.00 | 250.00 | 115,250.00 | 85.00 | 39,185.00 | 67.00 | 30,887.00 | | 0072 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 500,000.00 | 500,000.00 | 2,000,000.00 | 2,000,000.00 | 350,000.00 | 350,000.00 | 415,000.00 | 415,000.00 | | 0073 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 480 | LNFT | 2.00 | 960.00 | 2.10 | 1,008.00 | 1.55 | 744.00 | 2.00 | 960.00 | | 0074 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 2.423 | MILE | 1,100.00 | 2,665.30 | 1,725.00 | 4,179.68 | 8,000.00 | 19,384.00 | 1,100.00 | 2,665.30 | | 0075 | 713-03-02020 | Temporary Pavement Markings (Broken Line) (4" W) (10' L) (Type 1 Removable) | 0.596 | MILE | 9,000.00 | 5,364.00 | 12,200.00 | 7,271.20 | 8,000.00 | 4,768.00 | 9,000.00 | 5,364.00 | | 0076 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 6.182 | MILE | 2,200.00 | 13,600.40 | 1,950.00 | 12,054.90 | 2,600.00 | 16,073.20 | 2,200.00 | 13,600.40 | | 0077 | 713-04-01020 | Temporary Pavement Markings (Solid Line) (4"Width) (Type 1 Removable) | 2.118 | MILE | 18,000.00 | 38,124.00 | 17,000.00 | 36,006.00 | 15,500.00 | 32,829.00 | 18,000.00 | 38,124.00 | | 0078 | 713-05-00400 | Temporary Pavement Legends & Symbols (RR Crossing) | 2 | EACH | 500.00 | 1,000.00 | 325.00 | 650.00 | 275.00 | 550.00 | 500.00 | 1,000.00 | | 0079 | 713-06-00100 | Temporary Reflectorized Raised Pavement Markers | 71 | EACH | 12.00 | 852.00 | 7.00 | 497.00 | 16.00 | 1,136.00 | 12.00 | 852.00 | | 0080 | 713-07-00100 | Temporary Precast Concrete Barrier (Contractor Furnished) | 354 | EACH | 1,100.00 | 389,400.00 | 1,200.00 | 424,800.00 | 1,550.00 | 548,700.00 | 1,250.00 | 442,500.00 | | 0081 | 713-10-00100 | Temporary Precast Concrete Barrier Movement | 95 | EACH | 70.00 | 6,650.00 | 160.00 | 15,200.00 | 450.00 | 42,750.00 | 85.00 | 8,075.00 | | 0082 | 713-11-00100 | Portable Changeable Message Signs | 5 | EACH | 18,000.00 | 90,000.00 | 21,000.00 | 105,000.00 | 7,500.00 | 37,500.00 | 40,000.00 | 200,000.00 | | 0083 | 716-01-00100 | Mulch (Vegetative) | 10.3 | TON | 650.00 | 6,695.00 | 700.00 | 7,210.00 | 450.00 | 4,635.00 | 440.00 | 4,532.00 | | 0084 | 717-01-00100 | Seeding | 199 | LB | 12.00 | 2,388.00 | 13.00 | 2,587.00 | 32.00 | 6,368.00 | 14.50 | 2,885.50 | | 0085 | 718-01-00100 | Fertilizer | 5,080 | LB | 0.50 | 2,540.00 | 0.50 | 2,540.00 | 1.00 | 5,080.00 | 0.75 | 3,810.00 | | 0086 | 718-02-00100 | Agricultural Lime | 9.8 | TON | 200.00 | 1,960.00 | 210.00 | 2,058.00 | 350.00 | 3,430.00 | 648.83 | 6,358.53 | | 0087 | 722-02-00100 | Project Site Laboratory (Equipped) | 1 | EACH | 90,000.00 | 90,000.00 | 175,000.00 | 175,000.00 | 125,000.00 | 125,000.00 | 80,000.00 | 80,000.00 | | 0088 | 725-01-00100 | Temporary Detour Roads | 11,074.2 | SQYD | 150.00 | 1,661,130.00 | 50.00 | 553,710.00 | 120.00 | 1,328,904.00 | 105.00 | 1,162,791.00 | | 0089 | 726-01-00100 | Bedding Material | 417 | CUYD | 85.00 | 35,445.00 | 80.00 | 33,360.00 | 135.00 | 56,295.00 | 110.00 | 45,870.00 | | 0090 | 727-01-00100 | Mobilization | 1 | LUMP | 5,000,000.00 | 5,000,000.00 | 6,300,000.00 | 6,300,000.00 | 6,500,000.00 | 6,500,000.00 | 5,600,000.00 | 5,600,000.00 | | 0091 | 728-01-01200 | Jacked or Bored Pipe (36") () | 134 | LNFT | 800.00 | 107,200.00 | 900.00 | 120,600.00 | 800.00 | 107,200.00 | 300.00 | 40,200.00 | | 0092 | 729-01-00100 | Sign (Type A) | 137.5 | SQFT | 30.00 | 4,125.00 | 32.00 | 4,400.00 | 26.00 | 3,575.00 | 40.60 | 5,582.50 | | 0093 | 729-04-00100 | Sign (Type D) | 562 | SQFT | 38.00 | 21,356.00 | 40.00 | 22,480.00 | 36.00 | 20,232.00 | 40.60 | 22,817.20 | | 0094 | 729-06-00100 | Sign (Overhead Mounted) | 155 | SQFT | 45.00 | 6,975.00 | 47.00 | 7,285.00 | 155.00 | 24,025.00 | 75.40 | 11,687.00 | | 0095 | 729-08-00100 | Mounting (2 1/2" Size Post) | 1 | EACH | 1,250.00 | 1,250.00 | 1,300.00 | 1,300.00 | 1,800.00 | 1,800.00 | 2,320.09 | 2,320.09 | | 0096 | 729-08-00200 | Mounting (3 1/2" Size Post) | 2 | EACH | 1,450.00 | 2,900.00 | 1,600.00 | 3,200.00 | 2,000.00 | 4,000.00 | 2,320.10 | 4,640.20 | | 0097 | 729-08-00600 | Mounting (W6 x 12 Size Post) | 8 | EACH | 1,700.00 | 13,600.00 | 1,800.00 | 14,400.00 | 2,200.00 | 17,600.00 | 2,320.09 | 18,560.72 | | 0098 | 729-08-00700 | Mounting (W8 x 18 Size Post) | 8 | EACH | 2,450.00 | 19,600.00 | 2,600.00 | 20,800.00 | 2,300.00 | 18,400.00 | 3,480.14 | 27,841.12 | | 0099 | 729-22-00200 | Square Tubing Post with 2-1/4" Omni-Directional Anchor | 13 | EACH | 170.00 | 2,210.00 | 180.00 | 2,340.00 | 130.00 | 1,690.00 | 232.01 | 3,016.13 | | 0100 | 731-02-00100 | Reflectorized Raised Pavement Markers | 331 | EACH | 14.00 | 4,634.00 | 7.00 | 2,317.00 | 16.00 | 5,296.00 | 14.00 | 4,634.00 | | 0101 | 732-01-01080 | Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) | 340 | LNFT | 20.00 | 6,800.00 | 19.00 | 6,460.00 | 26.00 | 8,840.00 | 20.00 | 6,800.00 | | 0102 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 7.171 | MILE | 5,200.00 | 37,289.20 | 4,500.00 | 32,269.50 | 6,500.00 | 46,611.50 | 5,200.00 | 37,289.20 | | 0103 | 732-02-02040 | Plastic Pavement Striping (Solid Line) (8" Width) (Thermoplastic 90 mil) | 0.073 | MILE | 15,000.00 | 1,095.00 | 18,000.00 | 1,314.00 | 30,000.00 | 2,190.00 | 15,000.00 | 1,095.00 | | 0104 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 2.147 | MILE | 2,900.00 | 6,226.30 | 2,500.00 | 5,367.50 | 2,600.00 | 5,582.20 | 2,900.00 | 6,226.30 | | 0105 | 732-03-02010 | Plastic Pavement Striping (Dotted Line)(4" W)(2' L)(Thermo 90 mil) | 0.027 | MILE | 6,700.00 | 180.90 | 12,000.00 | 324.00 | 12,000.00 | 324.00 | 6,000.00 | 162.00 | | 0106 | 732-04-18000 | Plastic Pavement Legends and Symbols (RR Crossing) | 2 | EACH | 1,300.00 | 2,600.00 | 1,600.00 | 3,200.00 | 1,750.00 | 3,500.00 | 1,300.00 | 2,600.00 | | 0107 | 736-01-00100 | Trenching and Backfilling | 1,466 | LNFT | 4.00 | 5,864.00 | 4.00 | 5,864.00 | 4.00 | 5,864.00 | 4.90 | 7,183.40 | | 0108 | 736-03-00100 | Jacking or Boring | 8,432 | LNFT | 9.40 | 79,260.80 | 9.50 | 80,104.00 | 10.00 | 84,320.00 | 11.35 | 95,703.20 | | 0109 | 736-11-00200 | Conduit (2" HDPE, Schedule 80) | 23,401 | LNFT | 2.00 | 46,802.00 | 2.00 | 46,802.00 | 1.80 | 42,121.80 | 2.90 | 67,862.90 | | 0110 | 736-12-01004 | Conductor (1c, #4 awg) | 2,596 | LNFT | 3.00 | 7,788.00 | 3.00 | 7,788.00 | 3.00 | 7,788.00 | 2.88 | 7,476.48 | | 0111 | 736-12-01006 | Conductor (1c, #6 awg) | 814 | LNFT | 2.00 | 1,628.00 | 2.25 | 1,831.50 | 2.20 | 1,790.80 | 1.98 | 1,611.72 | | 0112 | 736-12-01008 | Conductor (1c, #8 awg) | 2,244 | LNFT | 2.00 | 4,488.00 | 1.50 | 3,366.00 | 1.50 | 3,366.00 | 1.35 | 3,029.40 | | 0113 | 740-01-00100 | Construction Layout | 1 | LUMP | 450,000.00 | 450,000.00 | 750,000.00 | 750,000.00 | 750,000.00 | 750,000.00 | 1,000,000.00 | 1,000,000.00 | | 0114 | 802-01-00100 | Structural Excavation (Bents) | 6,211 | CUYD | 50.00 | 310,550.00 | 46.00 | 285,706.00 | 50.00 | 310,550.00 | 25.00 | 155,275.00 | | 0115 | 802-03-00100 | Temporary Sheeting (Steel) (WALL 1) | 15,275 | SQFT | 60.00 | 916,500.00 | 60.00 | 916,500.00 | 75.00 | 1,145,625.00 | 98.00 | 1,496,950.00 | | 0116 | 802-04-00100 | Mechanically Stabilized Earth Wall (LA 1 SB MSE WALL) | 5,249 | SQFT | 70.00 | 367,430.00 | 100.00 | 524,900.00 | 45.00 | 236,205.00 | 76.00 | 398,924.00 | | 0117 | 802-04-00100 | Mechanically Stabilized Earth Wall (TEMPORARY MSE WALL 1 & 2) | 2,576 | SQFT | 10.00 | 25,760.00 | 18.00 | 46,368.00 | 26.00 | 66,976.00 | 27.00 | 69,552.00 | | 0118 | 802-05-00100 | MSEW Structural Excavation and Backfill | 1 | LUMP | 500,000.00 | 500,000.00 | 1,250,000.00 | 1,250,000.00 | 1,250,000.00 | 1,250,000.00 | 260,000.00 | 260,000.00 | | 0119 | 804-01-00200 | Precast Concrete Piles (14") | 127 | LNFT | 100.00 | 12,700.00 | 125.00 | 15,875.00 | 120.00 | 15,240.00 | 190.00 | 24,130.00 | | 0120 | 804-01-00400 | Precast Concrete Piles (18") | 33,750 | LNFT | 70.00 | 2,362,500.00 | 79.00 | 2,666,250.00 | 90.00 | 3,037,500.00 | 104.00 | 3,510,000.00 | | 0121 | 804-01-00600 | Precast Concrete Piles (24") | 17,480 | LNFT | 110.00 | 1,922,800.00 | 115.00 | 2,010,200.00 | 130.00 | 2,272,400.00 | 166.00 | 2,901,680.00 | | 0122 | 804-01-00700 | Precast Concrete Piles (30") | 1,344 | LNFT | 220.00 | 295,680.00 | 185.00 | 248,640.00 | 200.00 | 268,800.00 | 310.00 | 416,640.00 | | 0123 | 804-01-00800 | Precast Concrete Piles (36") | 903 | LNFT | 300.00 | 270,900.00 | 255.00 | 230,265.00 | 275.00 | 248,325.00 | 370.00 | 334,110.00 | | 0124 | 804-02-00100 | Treated Timber Piles (Noncoastal Treatment) | 30,555 | LNFT | 14.00 | 427,770.00 | 19.00 | 580,545.00 | 25.00 | 763,875.00 | 29.00 | 886,095.00 | | 0125 | 804-05-00400 | Precast Concrete Test Piles (18") | 2 | EACH | 110,000.00 | 220,000.00 | 100,000.00 | 200,000.00 | 25,000.00 | 50,000.00 | 55,000.00 | 110,000.00 | | 0126 | 804-05-00600 | Precast Concrete Test Piles (24") | 2 | EACH | 140,000.00 | 280,000.00 | 100,000.00 | 200,000.00 | 25,000.00 | 50,000.00 | 65,000.00 | 130,000.00 | | 0127 | 804-14-00100 | Dynamic Monitoring Assistance | 80 | EACH | 1,800.00 | 144,000.00 | 2,500.00 | 200,000.00 | 1,000.00 | 80,000.00 | 2,300.00 | 184,000.00 | | 0129 | 804-17-00100 | Construction Site Survey | 1 | LUMP | 32,000.00 | 32,000.00 | 500,000.00 | 500,000.00 | 25,000.00 | 25,000.00 | 50,000.00 | 50,000.00 | | 0130 | 804-18-00100 | Vibration Monitoring | 75 | DAY | 700.00 | 52,500.00 | 500.00 | 37,500.00 | 1,250.00 | 93,750.00 | 750.00 | 56,250.00 | | 0131 | 805-01-00200 | Class A1 Concrete (Deck) | 5,159.03 | CUYD | 700.00 | 3,611,321.00 | 1,100.00 | 5,674,933.00 | 850.00 | 4,385,175.50 | 926.00 | 4,777,261.78 | | 0132 | 805-04-00100 | Class MASS(A1) Concrete (Bent Cap) | 1,520.09 | CUYD | 1,000.00 | 1,520,090.00 | 1,500.00 | 2,280,135.00 | 1,500.00 | 2,280,135.00 | 1,000.00 | 1,520,090.00 | | 0133 | 805-04-00200 | Class MASS(A1) Concrete (Column) | 1,353.21 | CUYD | 1,100.00 | 1,488,531.00 | 950.00 | 1,285,549.50 | 1,750.00 | 2,368,117.50 | 1,510.00 | 2,043,347.10 | | 0134 | 805-04-00300 | Class MASS(A1) Concrete (Footing) | 4,497.7 | CUYD | 700.00 | 3,148,390.00 | 500.00 | 2,248,850.00 | 1,150.00 | 5,172,355.00 | 590.00 | 2,653,643.00 | | 0135 | 805-08-01600 | Precast-Prestressed Concrete Girders (Type LG-72) | 5,326 | LNFT | 360.00 | 1,917,360.00 | 360.00 | 1,917,360.00 | 400.00 | 2,130,400.00 | 405.00 | 2,157,030.00 | | 0136 | 805-08-01700 | Precast-Prestressed Concrete Girder (Type LG-78) | 7,668 | LNFT | 500.00 | 3,834,000.00 | 490.00 | 3,757,320.00 | 550.00 | 4,217,400.00 | 540.00 | 4,140,720.00 | | 0137 | 805-16-02700 | Reinforced Concrete Box Culverts (Extension) (4'X3')(EXTENSION) | 100.5 | LNFT | 400.00 | 40,200.00 | 450.00 | 45,225.00 | 950.00 | 95,475.00 | 600.00 | 60,300.00 | | 0138 | 805-18-00100 | Concrete Finish (Class 2 Rubbed Finish) | 38,922 | SQFT | 1.00 | 38,922.00 | 2.10 | 81,736.20 | 2.50 | 97,305.00 | 3.50 | 136,227.00 | | 0139 | 805-18-00200 | Concrete Finish (Class 3 Special Finish) | 133,800 | SQFT | 0.50 | 66,900.00 | 2.60 | 347,880.00 | 0.60 | 80,280.00 | 4.00 | 535,200.00 | | 0140 | 806-01-00100 | Deformed Reinforcing Steel | 2,589,893 | LB | 1.31 | 3,392,759.83 | 1.30 | 3,366,860.90 | 1.20 | 3,107,871.60 | 1.60 | 4,143,828.80 | | 0141 | 806-02-00100 | Deformed Reinforcing Steel (Corrosion Resistant) (Stainless Steel) | 13,502 | LB | 5.00 | 67,510.00 | 4.00 | 54,008.00 | 6.00 | 81,012.00 | 5.50 | 74,261.00 | | 0142 | 807-01-00100 | Structural Metalwork (Grade 36) | 1,241 | LUMP | 10,000.00 | 10,000.00 | 3,500.00 | 3,500.00 | 60,000.00 | 60,000.00 | 23,017.25 | 23,017.25 | | 0143 | 807-01-00400 | Structural Metalwork (Grade 50W) | 4,476,017 | LUMP | 11,561,445.00 | 11,561,445.00 | 12,000,000.00 | 12,000,000.00 | 13,200,000.00 | 13,200,000.00 | 12,920,000.00 | 12,920,000.00 | | 0144 | 807-02-00100 | Structural Metalwork (Anchor Bolts) | 4,093 | LUMP | 90,000.00 | 90,000.00 | 130,000.00 | 130,000.00 | 110,000.00 | 110,000.00 | 85,000.00 | 85,000.00 | | 0145 | 807-03-00100 | Structural Metalwork (Access System) | 14,448 | LUMP | 160,000.00 | 160,000.00 | 145,000.00 | 145,000.00 | 400,000.00 | 400,000.00 | 170,000.00 | 170,000.00 | | 0146 | 810-01-00120 | Concrete Bridge Railing (36 inch Height) | 5,432 | LNFT | 80.00 | 434,560.00 | 100.00 | 543,200.00 | 90.00 | 488,880.00 | 76.00 | 412,832.00 | | 0147 | 810-05-00120 | Concrete Roadway Barrier (36 inch Height) | 285 | LNFT | 80.00 | 22,800.00 | 500.00 | 142,500.00 | 90.00 | 25,650.00 | 74.00 | 21,090.00 | | 0148 | 813-01-00100 | Concrete Approach Slabs (Cast-in-Place) | 4,530 | SQFT | 61.00 | 276,330.00 | 90.00 | 407,700.00 | 85.00 | 385,050.00 | 130.00 | 588,900.00 | | 0149 | 814-02-00100 | Elastomeric Bearing Pads (Reinforced) | 1,156 | SFIN | 190.00 | 219,640.00 | 72.00 | 83,232.00 | 225.00 | 260,100.00 | 100.00 | 115,600.00 | | 0150 | 814-03-00100 | Bearing Assembly (Disc) | 24 | EACH | 16,000.00 | 384,000.00 | 17,500.00 | 420,000.00 | 13,000.00 | 312,000.00 | 20,000.00 | 480,000.00 | | 0151 | 815-02-00100 | Sealed Expansion Joint (End Dams and Preformed Neoprene Seal) | 280 | LNFT | 400.00 | 112,000.00 | 530.00 | 148,400.00 | 325.00 | 91,000.00 | 450.00 | 126,000.00 | | 0152 | 815-02-00300 | Sealed Expansion Joint (Modular) | 112 | LNFT | 1,000.00 | 112,000.00 | 3,000.00 | 336,000.00 | 3,500.00 | 392,000.00 | 3,650.00 | 408,800.00 | | 0153 | 816-01-00100 | Bridge Deck Drainage System (Collection) | 1 | LUMP | 70,000.00 | 70,000.00 | 50,000.00 | 50,000.00 | 80,000.00 | 80,000.00 | 37,000.00 | 37,000.00 | | 0154 | 822-01-00100 | Trenching and Backfilling | 250 | LNFT | 4.00 | 1,000.00 | 4.00 | 1,000.00 | 4.00 | 1,000.00 | 8.00 | 2,000.00 | | 0155 | 822-02-00100 | Conduit w Conductors (PVC/HDPE) (3/4") (3/4") (1#2 BARE STRANDED GROUND) (G) | 20 | LNFT | 12.00 | 240.00 | 13.00 | 260.00 | 12.30 | 246.00 | 8.40 | 168.00 | | 0157 | 822-02-00300 | Conduit w Conductors (PVC/HDPE) (1-1/4") (WITH PULLTAPE) (SCH40) | 7,656 | LNFT | 4.00 | 30,624.00 | 4.25 | 32,538.00 | 4.10 | 31,389.60 | 17.10 | 130,917.60 | | 0159 | 822-02-01500 | Conduit w Conductors (Rigid Alum) (2") , 1#2 GREEN INSUL. GROUND) | 50 | LNFT | 14.00 | 700.00 | 15.00 | 750.00 | 14.40 | 720.00 | 30.00 | 1,500.00 | | 0161 | 822-04-00100 | Jacked or Bored Casing (4" Dia) (PVC/HDPE) | 759 | LNFT | 25.00 | 18,975.00 | 27.00 | 20,493.00 | 26.00 | 19,734.00 | 16.55 | 12,561.45 | | 0162 | 822-04-00200 | Jacked or Bored Casing (6" Dia) (PVC/HDPE) | 1,575 | LNFT | 44.00 | 69,300.00 | 46.00 | 72,450.00 | 46.00 | 72,450.00 | 25.60 | 40,320.00 | | 0163 | 822-08-00200 | Electrical Service Point (Structure) | 1 | EACH | 7,200.00 | 7,200.00 | 7,500.00 | 7,500.00 | 7,360.00 | 7,360.00 | 6,195.00 | 6,195.00 | | 0164 | 822-09-00100 | Electrical System | 1 | LUMP | 72,000.00 | 72,000.00 | 75,000.00 | 75,000.00 | 74,000.00 | 74,000.00 | 115,760.00 | 115,760.00 | | 0165 | 822-11-00100 | Removal and Disposal of Electrical Equipment | 1 | LUMP | 6,000.00 | 6,000.00 | 6,000.00 | 6,000.00 | 6,000.00 | 6,000.00 | 21,775.00 | 21,775.00 | | 0166 | 822-11-00100 | Removal and Disposal of Electrical Equipment (STORAGE OF ELECTRICAL EQUIPMENT) | 1 | LUMP | 6,000.00 | 6,000.00 | 6,000.00 | 6,000.00 | 6,000.00 | 6,000.00 | 4,000.00 | 4,000.00 | | 0167 | 822-12-00100 | Removal and Storage of Light Pole (Ground Mount) (GROUND MOUNT) | 1 | EACH | 600.00 | 600.00 | 600.00 | 600.00 | 600.00 | 600.00 | 7,375.00 | 7,375.00 | | 0168 | 822-13-00100 | Removal and Disposal of Light Pole Foundation (GROUND MOUNT) | 1 | EACH | 800.00 | 800.00 | 800.00 | 800.00 | 800.00 | 800.00 | 750.00 | 750.00 | | 0169 | 822-14-00100 | Removal and Disposal of Luminaire | 6 | EACH | 38.00 | 228.00 | 40.00 | 240.00 | 40.00 | 240.00 | 260.00 | 1,560.00 | | 0170 | 822-16-00200 | Underground Junction Box (11" x 18") | 2 | EACH | 700.00 | 1,400.00 | 725.00 | 1,450.00 | 730.00 | 1,460.00 | 1,200.00 | 2,400.00 | | 0171 | 822-17-00400 | Structure Junction Box (Stainless Steel) | 2 | EACH | 600.00 | 1,200.00 | 700.00 | 1,400.00 | 655.00 | 1,310.00 | 1,220.00 | 2,440.00 | | 0172 | 822-20-00100 | Disconnect (Service) | 1 | EACH | 1,500.00 | 1,500.00 | 1,600.00 | 1,600.00 | 1,525.00 | 1,525.00 | 2,480.00 | 2,480.00 | | 0173 | 822-21-00100 | Duct Marker (Concrete) | 1 | EACH | 1,000.00 | 1,000.00 | 1,200.00 | 1,200.00 | 1,100.00 | 1,100.00 | 550.00 | 550.00 | | 0174 | 822-22-00100 | Underground Marker Tape (3")(Detectable) | 250 | LNFT | 0.35 | 87.50 | 0.40 | 100.00 | 0.40 | 100.00 | 0.65 | 162.50 | | 0175 | NS-203-00100 | Geosynthetic Load Transfer Platform | 13,007 | SQFT | 16.00 | 208,112.00 | 40.00 | 520,280.00 | 24.00 | 312,168.00 | 38.00 | 494,266.00 | | 0176 | NS-500-00300 | Traffic Maintenance Asphalt Concrete | 300 | TON | 138.00 | 41,400.00 | 160.00 | 48,000.00 | 305.00 | 91,500.00 | 166.89 | 50,067.00 | | 0177 | NS-500-00340 | Saw Cutting Asphalt Concrete Pavement | 7,989 | INLF | 0.85 | 6,790.65 | 1.70 | 13,581.30 | 1.25 | 9,986.25 | 0.85 | 6,790.65 | | 0178 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 3,776 | INLF | 1.00 | 3,776.00 | 1.70 | 6,419.20 | 1.25 | 4,720.00 | 1.00 | 3,776.00 | | 0179 | NS-700-00810 | Impact Attenuator (Construction Zone)(Test Level 3) | 5 | EACH | 8,500.00 | 42,500.00 | 9,000.00 | 45,000.00 | 9,000.00 | 45,000.00 | 13,125.86 | 65,629.30 | | 0180 | NS-700-00820 | Impact Attenuator Relocation (Construction Zone) | 4 | EACH | 2,000.00 | 8,000.00 | 2,600.00 | 10,400.00 | 1,000.00 | 4,000.00 | 1,000.00 | 4,000.00 | | 0181 | NS-729-00029 | Breakaway Square Tubing Sign Support w/ Mowing Pad | 3 | EACH | 750.00 | 2,250.00 | 800.00 | 2,400.00 | 1,000.00 | 3,000.00 | 986.04 | 2,958.12 | | 0182 | NS-ITS-01121 | CCTV Camera Assembly, Furnish and Install with PTZ, Digital | 6 | EACH | 7,000.00 | 42,000.00 | 7,000.00 | 42,000.00 | 9,000.00 | 54,000.00 | 8,880.00 | 53,280.00 | | 0183 | NS-ITS-02120 | Dynamic Message Sign, Furnish & Install, LED Full Matrix, Front Access, Pole Mount | 1 | EACH | 140,000.00 | 140,000.00 | 145,000.00 | 145,000.00 | 145,000.00 | 145,000.00 | 135,000.00 | 135,000.00 | | 0184 | NS-ITS-03255 | Bluetooth Data Collection Unit Ethernet POE, Furnish & Install | 4 | EACH | 10,000.00 | 40,000.00 | 11,000.00 | 44,000.00 | 10,000.00 | 40,000.00 | 7,245.00 | 28,980.00 | | 0185 | NS-ITS-03340 | Vehicle Detector, Radar Right Angle, Furnish & Install | 3 | EACH | 6,300.00 | 18,900.00 | 7,000.00 | 21,000.00 | 6,500.00 | 19,500.00 | 6,800.00 | 20,400.00 | | 0186 | NS-ITS-03501 | CCTV Camera Site, Remove | 1 | EACH | 4,500.00 | 4,500.00 | 200.00 | 200.00 | 200.00 | 200.00 | 7,138.00 | 7,138.00 | | 0187 | NS-ITS-03521 | DMS Site, Remove | 1 | EACH | 8,200.00 | 8,200.00 | 4,000.00 | 4,000.00 | 4,000.00 | 4,000.00 | 5,985.00 | 5,985.00 | | 0188 | NS-ITS-04000 | Fiber Optic Marker | 10 | EACH | 200.00 | 2,000.00 | 210.00 | 2,100.00 | 210.00 | 2,100.00 | 300.00 | 3,000.00 | | 0189 | NS-ITS-04020 | Fiber Optic Cable, SM, Furnish & Install, 13-48 Fibers | 14,554 | LNFT | 4.00 | 58,216.00 | 4.00 | 58,216.00 | 3.75 | 54,577.50 | 3.90 | 56,760.60 | | 0190 | NS-ITS-04035 | Fiber Optic Fan Out Kits, SM, 12 Strand, Furnish & Install | 16 | EACH | 100.00 | 1,600.00 | 110.00 | 1,760.00 | 105.00 | 1,680.00 | 98.00 | 1,568.00 | | 0191 | NS-ITS-04180 | Fiber Optic Connection, Install, Splice | 64 | EACH | 95.00 | 6,080.00 | 100.00 | 6,400.00 | 100.00 | 6,400.00 | 92.00 | 5,888.00 | | 0192 | NS-ITS-04200 | Fiber Optic Connection, Termination, Furnish & Install | 192 | EACH | 70.00 | 13,440.00 | 75.00 | 14,400.00 | 75.00 | 14,400.00 | 68.00 | 13,056.00 | | 0193 | NS-ITS-04250 | Fiber Optic Drop Cable, SM, 12 Strand, Furnish & Install | 492 | LNFT | 4.00 | 1,968.00 | 4.00 | 1,968.00 | 4.00 | 1,968.00 | 4.00 | 1,968.00 | | 0194 | NS-ITS-04290 | Fiber Optic Patch Cord, SM, 2 Strand, Furnish & Install | 26 | EACH | 57.00 | 1,482.00 | 60.00 | 1,560.00 | 60.00 | 1,560.00 | 56.00 | 1,456.00 | | 0195 | NS-ITS-04360 | Fiber Optic Connection Splice Tray, Furnish & Install | 20 | EACH | 61.00 | 1,220.00 | 65.00 | 1,300.00 | 65.00 | 1,300.00 | 60.00 | 1,200.00 | | 0196 | NS-ITS-04425 | Fiber Optic Connection Patch Panel, Outdoor, Furnish & Install | 5 | EACH | 600.00 | 3,000.00 | 650.00 | 3,250.00 | 625.00 | 3,125.00 | 588.00 | 2,940.00 | | 0197 | NS-ITS-05025 | Splice Closure, Outdoor, Furnish & Install | 5 | EACH | 1,200.00 | 6,000.00 | 1,300.00 | 6,500.00 | 1,250.00 | 6,250.00 | 1,185.00 | 5,925.00 | | 0198 | NS-ITS-06020 | Pullbox, In-ground, Furnish & Install (TYPE F) | 14 | EACH | 1,200.00 | 16,800.00 | 1,200.00 | 16,800.00 | 1,200.00 | 16,800.00 | 1,295.00 | 18,130.00 | | 0199 | NS-ITS-06020 | Pullbox, In-ground, Furnish & Install (TYPE K) | 20 | EACH | 2,300.00 | 46,000.00 | 2,400.00 | 48,000.00 | 2,400.00 | 48,000.00 | 3,070.00 | 61,400.00 | | 0200 | NS-ITS-06120 | Pullbox, Structure Mount, Furnish & Install - New | 4 | EACH | 650.00 | 2,600.00 | 700.00 | 2,800.00 | 700.00 | 2,800.00 | 2,115.00 | 8,460.00 | | 0201 | NS-ITS-07020 | ITS Controller Cabinet, Pole Mount, Furnish & Install | 4 | EACH | 14,000.00 | 56,000.00 | 15,000.00 | 60,000.00 | 14,500.00 | 58,000.00 | 14,395.00 | 57,580.00 | | 0202 | NS-ITS-07220 | ITS Controller Cabinet, Pad Mount, Furnish & Install | 1 | EACH | 13,000.00 | 13,000.00 | 14,000.00 | 14,000.00 | 13,500.00 | 13,500.00 | 17,300.00 | 17,300.00 | | 0203 | NS-ITS-08061 | Pole, Foundation & Lowering Device, >= 60', Furnish & Install | 1 | EACH | 75,000.00 | 75,000.00 | 80,000.00 | 80,000.00 | 77,000.00 | 77,000.00 | 82,000.00 | 82,000.00 | | 0204 | NS-ITS-08101 | Pole, Foundation & Lowering Device, >= 100', Furnish & Install | 2 | EACH | 87,000.00 | 174,000.00 | 90,000.00 | 180,000.00 | 90,000.00 | 180,000.00 | 128,000.00 | 256,000.00 | | 0205 | NS-ITS-08180 | Lowering Tool, Electric Hoist Assembly & Clutch Adapter, Furnish | 2 | EACH | 4,000.00 | 8,000.00 | 5,000.00 | 10,000.00 | 4,100.00 | 8,200.00 | 3,900.00 | 7,800.00 | | 0206 | NS-ITS-09080 | Local Ethernet Switch, Furnish & Install | 5 | EACH | 1,600.00 | 8,000.00 | 2,000.00 | 10,000.00 | 1,700.00 | 8,500.00 | 1,775.00 | 8,875.00 | | 0207 | NS-ITS-09140 | Gigabit Ethernet Aggregation Switch, Furnish & Install | 1 | EACH | 10,000.00 | 10,000.00 | 11,000.00 | 11,000.00 | 10,500.00 | 10,500.00 | 7,400.00 | 7,400.00 | | 0208 | NS-ITS-09380 | Point-to-Point Microwave Ethernet Data Radio, Install | 1 | EACH | 4,000.00 | 4,000.00 | 4,500.00 | 4,500.00 | 4,250.00 | 4,250.00 | 1,500.00 | 1,500.00 | | 0209 | NS-ITS-09440 | Point-to-Point Microwave Ethernet Data Radio Antenna, Install | 1 | EACH | 3,300.00 | 3,300.00 | 3,400.00 | 3,400.00 | 3,500.00 | 3,500.00 | 1,100.00 | 1,100.00 | | 0210 | NS-ITS-10060 | Electrical Service | 5 | EACH | 5,500.00 | 27,500.00 | 6,000.00 | 30,000.00 | 6,000.00 | 30,000.00 | 6,755.00 | 33,775.00 | | 0211 | NS-ITS-10220 | Power Surge Suppressor, Furnish & Install | 15 | EACH | 250.00 | 3,750.00 | 230.00 | 3,450.00 | 250.00 | 3,750.00 | 322.00 | 4,830.00 | | 0212 | NS-ITS-10340 | Data Surge Suppressor, Furnish & Install | 19 | EACH | 100.00 | 1,900.00 | 110.00 | 2,090.00 | 110.00 | 2,090.00 | 292.00 | 5,548.00 | | 0213 | NS-ITS-10362 | Power Surge Suppressor (ITS Cabinet), Furnish & Install | 5 | EACH | 4,000.00 | 20,000.00 | 4,000.00 | 20,000.00 | 4,000.00 | 20,000.00 | 824.00 | 4,120.00 | | 0214 | NS-ITS-12000 | Communications System Integration | 1 | LUMP | 50,000.00 | 50,000.00 | 55,000.00 | 55,000.00 | 51,000.00 | 51,000.00 | 12,500.00 | 12,500.00 | | 0215 | NS-ITS-12020 | TMC Integration | 1 | LUMP | 21,000.00 | 21,000.00 | 25,000.00 | 25,000.00 | 22,000.00 | 22,000.00 | 10,000.00 | 10,000.00 | | 0216 | NS-ITS-13200 | As-Builts | 1 | LUMP | 2,000.00 | 2,000.00 | 2,000.00 | 2,000.00 | 2,000.00 | 2,000.00 | 2,550.00 | 2,550.00 | | 0217 | NS-ITS-15320 | 2" Rigid Galvanized Steel Conduit | 160 | LNFT | 23.00 | 3,680.00 | 23.00 | 3,680.00 | 24.00 | 3,840.00 | 54.75 | 8,760.00 | | 0218 | NS-ITS-15640 | 4" FRE Conduit | 2,552 | LNFT | 140.00 | 357,280.00 | 145.00 | 370,040.00 | 145.00 | 370,040.00 | 109.00 | 278,168.00 | | 0222 | 804-09-00400 | Static Load Test (Precast Concrete Piles (18")) | 2 | EACH | 90,500.00 | 181,000.00 | 10,000.00 | 20,000.00 | 30,000.00 | 60,000.00 | 84,000.00 | 168,000.00 | | 0223 | 804-09-00600 | Static Load Test (Precast Concrete Piles (24")) | 2 | EACH | 75,000.00 | 150,000.00 | 10,000.00 | 20,000.00 | 30,000.00 | 60,000.00 | 84,000.00 | 168,000.00 | | 0224 | 808-01-00300 | Steel Grid Flooring TYPE W-19-4 (2*3/16) STEEL | 598 | SQFT | 80.00 | 47,840.00 | 60.00 | 35,880.00 | 130.00 | 77,740.00 | 90.00 | 53,820.00 | | | | SUBTOTAL GENERAL | | | | 58,159,268 | | 64,910,688 | | 67,959,873 | | 65,916,028 | | | | | | | | | | | | | | | | | Alternate AA2 | ALTERNATE AA2 (TEMPORARY MSE WALL) | | | | | | | | | | | | | | | | | | | | | | | | | | 0220 | 802-04-00100 | Mechanically Stabilized Earth Wall (TEMPORARY MSE WALL 3) | 1,856 | SQFT | 18.00 | 33,408.00 | 21.00 | 38,976.00 | 25.00 | 46,400.00 | 27.00 | 50,112.00 | | 0221 | 802-05-00100 | MSEW Structural Excavation and Backfill (TEMPORARY MSE WALL 3) | 1 | LUMP | 2,000.00 | 2,000.00 | 12,000.00 | 12,000.00 | 250,000.00 | 250,000.00 | 65,000.00 | 65,000.00 | | | | SUBTOTAL ALT AA2 | | | | 35,408.00 | | 50,976.00 | | 296,400.00 | | 115,112.00 | | | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 58,194,675.58 | | 64,961,663.58 | | 68,256,273.10 | | 66,031,140.24 |
|