Proposal:H.004424.6-R1
Parish:Jefferson
Routes:LA 3152, US 61
Description:AIRLINE AT CLEARVIEW INTERSECTION IMPROV
Type Construction:CLEARING AND GRUBBING, GRADING, DRAINAGE STRUCTURES, MILLING ASPHALT CONCRETE, PAVEMENT PATCHING, CLASS II BASE COURSE, ASPHALT CONCRETE OVERLAY, DRILLED SHAFT FOUNDATIONS, TRAFFIC SIGNALIZATION, AND RELATED WORK.
Estimated Construction Cost:$5,641,545.50
Maximum Number of Days Allowed for Construction:9999
Calculated Daily User Cost:$10,000.00
| Rank | License | Bidder | Construction Bid | Bidder's Proposed Contract Time | Total Bid |
| 1 | 54896 | Magee Excavation & Development LLC | $6,095,000.00 | 330.00 | $9,395,000.00 |
| 2 | 06276 | Barriere Construction Co., LLC | $7,326,326.14 | 365.00 | $10,976,326.14 |
| 3 | 02179 | Boh Bros. Construction Co., LLC. | $8,050,901.02 | 300.00 | $11,050,901.02 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Magee Excavation & Development LLC | - 2 - Barriere Construction Co., LLC | - 3 - Boh Bros. Construction Co., LLC. | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 201-01-00100 | Clearing and Grubbing | 1.063 | LUMP | 215,000.00 | 215,000.00 | 3,500.00 | 3,500.00 | 30,000.00 | 30,000.00 | | 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 285,000.00 | 285,000.00 | 5,000.00 | 5,000.00 | 10,000.00 | 10,000.00 | | 0003 | 202-02-00030 | Removal of Existing PCCP/LJ Waterline (20")(Jefferson Parish) | 395 | LNFT | 12.00 | 4,740.00 | 50.00 | 19,750.00 | 65.00 | 25,675.00 | | 0004 | 202-02-06060 | Removal of Concrete Catch Basin | 6 | EACH | 300.00 | 1,800.00 | 1,000.00 | 6,000.00 | 2,500.00 | 15,000.00 | | 0005 | 202-02-06080 | Removal of Concrete Combination Curb and Gutter | 2,624.4 | LNFT | 15.00 | 39,366.00 | 20.00 | 52,488.00 | 5.00 | 13,122.00 | | 0006 | 202-02-06100 | Removal of Concrete Walks and Drives | 110 | SQYD | 20.00 | 2,200.00 | 50.00 | 5,500.00 | 15.00 | 1,650.00 | | 0007 | 202-02-26300 | Removal of Median / Island | 107 | SQYD | 20.00 | 2,140.00 | 50.00 | 5,350.00 | 80.00 | 8,560.00 | | 0008 | 202-02-32140 | Removal of Pipe (Storm Drain) (21", RCP) | 193 | LNFT | 10.00 | 1,930.00 | 50.00 | 9,650.00 | 60.00 | 11,580.00 | | 0009 | 202-02-38240 | Removal of Signs and Supports | 62 | EACH | 45.00 | 2,790.00 | 11.00 | 682.00 | 10.00 | 620.00 | | 0010 | 202-02-40100 | Removal of Traffic Signal Equipment | 1 | LUMP | 10,400.00 | 10,400.00 | 12,000.00 | 12,000.00 | 10,000.00 | 10,000.00 | | 0011 | 202-03-38000 | Relocation of Sign (See Signing table, Sheet 3) | 20 | EACH | 5.50 | 110.00 | 6.50 | 130.00 | 50.00 | 1,000.00 | | 0012 | 202-03-38020 | Relocation of Sign Pole (See Signing table, Sheet 3) | 11 | EACH | 22.00 | 242.00 | 90.00 | 990.00 | 100.00 | 1,100.00 | | 0013 | 203-01-00100 | General Excavation | 5,454 | CUYD | 25.00 | 136,350.00 | 30.00 | 163,620.00 | 30.00 | 163,620.00 | | 0014 | 203-04-00200 | Nonplastic Embankment (Sand) | 2,693 | CUYD | 30.00 | 80,790.00 | 33.00 | 88,869.00 | 40.00 | 107,720.00 | | 0015 | 203-08-00100 | Geotextile Fabric | 7,010.4 | SQYD | 2.00 | 14,020.80 | 1.50 | 10,515.60 | 2.00 | 14,020.80 | | 0016 | 204-02-00100 | Temporary Hay Bales | 90 | EACH | 15.00 | 1,350.00 | 15.00 | 1,350.00 | 50.00 | 4,500.00 | | 0017 | 204-06-00100 | Temporary Silt Fencing | 4,366 | LNFT | 1.50 | 6,549.00 | 1.50 | 6,549.00 | 4.00 | 17,464.00 | | 0018 | 302-02-10075 | Class II Base Course (10" Thick) (Crushed Stone or Recycled Portland Cement Concrete) | 5,245.7 | SQYD | 40.00 | 209,828.00 | 30.00 | 157,371.00 | 40.00 | 209,828.00 | | 0019 | 402-02-00100 | Mainline Traffic Maintenance Surfacing (Hard) | 500 | SQYD | 110.00 | 55,000.00 | 50.00 | 25,000.00 | 50.00 | 25,000.00 | | 0020 | 502-01-00100 | Asphalt Concrete | 8,112.4 | TON | 125.00 | 1,014,050.00 | 143.00 | 1,160,073.20 | 150.00 | 1,216,860.00 | | 0021 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 673.5 | TON | 160.00 | 107,760.00 | 143.00 | 96,310.50 | 150.00 | 101,025.00 | | 0022 | 509-01-00100 | Milling Asphalt Pavement | 11,790 | SQYD | 8.00 | 94,320.00 | 7.00 | 82,530.00 | 7.00 | 82,530.00 | | 0023 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -818.8 | CUYD | 0.01 | -8.19 | 0.01 | -8.19 | 0.10 | -81.88 | | 0024 | 510-01-00400 | Pavement Patching (24" Minimum Thickness) | 227.3 | SQYD | 268.00 | 60,916.40 | 300.00 | 68,190.00 | 250.00 | 56,825.00 | | 0025 | 701-03-01002 | Storm Drain Pipe (15" RCP/RPVCP) | 1,322 | LNFT | 150.00 | 198,300.00 | 130.00 | 171,860.00 | 165.00 | 218,130.00 | | 0026 | 701-03-01022 | Storm Drain Pipe (18" RCP/RPVCP) | 330 | LNFT | 160.00 | 52,800.00 | 180.00 | 59,400.00 | 175.00 | 57,750.00 | | 0027 | 701-17-00100 | Trench Excavation Safety Protection (Depth >5 feet) | 3,133 | LNFT | 10.00 | 31,330.00 | 0.01 | 31.33 | 12.00 | 37,596.00 | | 0028 | 702-02-00001 | Manhole (Remove and Replace Frame and Cover) | 3 | EACH | 1,650.00 | 4,950.00 | 2,000.00 | 6,000.00 | 1,750.00 | 5,250.00 | | 0029 | 702-02-00100 | Manholes (MH-06) | 3 | EACH | 3,500.00 | 10,500.00 | 8,000.00 | 24,000.00 | 11,000.00 | 33,000.00 | | 0030 | 702-03-00500 | Catch Basins (CB-06) | 16 | EACH | 4,100.00 | 65,600.00 | 9,000.00 | 144,000.00 | 12,500.00 | 200,000.00 | | 0031 | 702-03-00600 | Catch Basins (CB-07) | 2 | EACH | 4,200.00 | 8,400.00 | 11,000.00 | 22,000.00 | 13,500.00 | 27,000.00 | | 0032 | 702-03-00700 | Catch Basins (CB-08) | 3 | EACH | 6,300.00 | 18,900.00 | 20,000.00 | 60,000.00 | 20,000.00 | 60,000.00 | | 0033 | 702-04-00100 | Adjusting Manholes | 6 | EACH | 1,100.00 | 6,600.00 | 3,000.00 | 18,000.00 | 2,000.00 | 12,000.00 | | 0034 | 702-04-00200 | Adjusting Catch Basins | 1 | EACH | 1,100.00 | 1,100.00 | 5,000.00 | 5,000.00 | 10,000.00 | 10,000.00 | | 0035 | 702-04-00210 | Convert Catch Basins to Manholes | 1 | EACH | 3,550.00 | 3,550.00 | 6,000.00 | 6,000.00 | 10,500.00 | 10,500.00 | | 0036 | 706-01-00100 | Concrete Walk (4" Thick) | 204.8 | SQYD | 50.00 | 10,240.00 | 90.00 | 18,432.00 | 100.00 | 20,480.00 | | 0037 | 706-03-00300 | Incidental Concrete Paving (6" Thick) | 2,714.5 | SQYD | 55.00 | 149,297.50 | 106.00 | 287,737.00 | 60.00 | 162,870.00 | | 0038 | 706-03-00500 | Incidental Concrete Paving (8" Thick) | 242.4 | SQYD | 75.00 | 18,180.00 | 116.00 | 28,118.40 | 85.00 | 20,604.00 | | 0039 | 706-04-00100 | Handicapped Curb Ramps | 10 | EACH | 1,350.00 | 13,500.00 | 1,000.00 | 10,000.00 | 4,000.00 | 40,000.00 | | 0040 | 707-03-00100 | Combination Concrete Curb and Gutter | 6,274.3 | LNFT | 25.00 | 156,857.50 | 50.00 | 313,715.00 | 55.00 | 345,086.50 | | 0041 | 710-01-00100 | Flowable Fill | 59.2 | CUYD | 110.00 | 6,512.00 | 600.00 | 35,520.00 | 730.00 | 43,216.00 | | 0042 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 280,000.00 | 280,000.00 | 700,000.00 | 700,000.00 | 775,000.00 | 775,000.00 | | 0043 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 567 | LNFT | 4.50 | 2,551.50 | 2.00 | 1,134.00 | 1.00 | 567.00 | | 0044 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 4.295 | MILE | 250.00 | 1,073.75 | 600.00 | 2,577.00 | 500.00 | 2,147.50 | | 0045 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 1.166 | MILE | 2,450.00 | 2,856.70 | 3,500.00 | 4,081.00 | 2,500.00 | 2,915.00 | | 0046 | 713-05-00220 | Temporary Pavement Legends & Symbols (Arrow - Left Turn) | 20 | EACH | 78.00 | 1,560.00 | 60.00 | 1,200.00 | 45.00 | 900.00 | | 0047 | 713-05-00230 | Temporary Pavement Legends & Symbols (Arrow - Right Turn) | 10 | EACH | 78.00 | 780.00 | 60.00 | 600.00 | 45.00 | 450.00 | | 0048 | 713-11-00100 | Portable Changeable Message Signs | 4 | EACH | 11,790.00 | 47,160.00 | 10,000.00 | 40,000.00 | 17,500.00 | 70,000.00 | | 0049 | 714-01-00600 | Slab Sodding (St. Augustine) | 672 | SQYD | 8.00 | 5,376.00 | 15.00 | 10,080.00 | 11.00 | 7,392.00 | | 0050 | 726-01-00100 | Bedding Material | 349.92 | CUYD | 55.00 | 19,245.60 | 90.00 | 31,492.80 | 95.00 | 33,242.40 | | 0051 | 727-01-00100 | Mobilization | 1 | LUMP | 524,000.00 | 524,000.00 | 730,000.00 | 730,000.00 | 800,000.00 | 800,000.00 | | 0052 | 729-01-00100 | Sign (Type A) | 553.9 | SQFT | 24.50 | 13,570.55 | 40.00 | 22,156.00 | 40.00 | 22,156.00 | | 0053 | 729-08-00100 | Mounting (2 1/2" Size Post) | 1 | EACH | 1,675.00 | 1,675.00 | 2,200.00 | 2,200.00 | 1,450.00 | 1,450.00 | | 0054 | 729-08-00600 | Mounting (W6 x 12 Size Post) | 3 | EACH | 2,500.00 | 7,500.00 | 3,000.00 | 9,000.00 | 2,100.00 | 6,300.00 | | 0055 | 729-22-00100 | Square Tubing Post with 2-1/4" Anchor | 29 | EACH | 150.00 | 4,350.00 | 180.00 | 5,220.00 | 175.00 | 5,075.00 | | 0056 | 731-02-00100 | Reflectorized Raised Pavement Markers | 456 | EACH | 10.00 | 4,560.00 | 24.00 | 10,944.00 | 25.00 | 11,400.00 | | 0057 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 1,848 | LNFT | 3.90 | 7,207.20 | 4.20 | 7,761.60 | 4.25 | 7,854.00 | | 0058 | 732-01-01080 | Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) | 41 | LNFT | 16.00 | 656.00 | 21.00 | 861.00 | 30.00 | 1,230.00 | | 0059 | 732-01-02060 | Plastic Pavement Striping (12" Width) (Thermoplastic 125 mil) | 740 | LNFT | 10.00 | 7,400.00 | 11.00 | 8,140.00 | 12.00 | 8,880.00 | | 0060 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 477 | LNFT | 18.00 | 8,586.00 | 21.00 | 10,017.00 | 21.00 | 10,017.00 | | 0061 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 1.695 | MILE | 5,500.00 | 9,322.50 | 6,000.00 | 10,170.00 | 5,600.00 | 9,492.00 | | 0062 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 1.528 | MILE | 2,790.00 | 4,263.12 | 2,600.00 | 3,972.80 | 2,900.00 | 4,431.20 | | 0063 | 732-03-02010 | Plastic Pavement Striping (Dotted Line)(4" W)(2' L)(Thermo 90 mil) | 0.134 | MILE | 4,465.00 | 598.31 | 2,200.00 | 294.80 | 3,000.00 | 402.00 | | 0064 | 732-03-02012 | Plastic Pavement Striping (Dotted Line)(4" W)(3' L)(Thermo 90 mil) | 0.149 | MILE | 4,465.00 | 665.29 | 2,600.00 | 387.40 | 4,000.00 | 596.00 | | 0065 | 732-03-02030 | Plastic Pavement Striping (Dotted Line)(8" W)(2' L)(Thermo 90 mil) | 0.547 | MILE | 10,000.00 | 5,470.00 | 5,500.00 | 3,008.50 | 5,000.00 | 2,735.00 | | 0066 | 732-04-01020 | Plastic Pavement Legends and Symbols (Arrow - Straight) | 2 | EACH | 440.00 | 880.00 | 400.00 | 800.00 | 360.00 | 720.00 | | 0067 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 18 | EACH | 440.00 | 7,920.00 | 375.00 | 6,750.00 | 360.00 | 6,480.00 | | 0068 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 9 | EACH | 440.00 | 3,960.00 | 375.00 | 3,375.00 | 360.00 | 3,240.00 | | 0069 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 10 | EACH | 500.00 | 5,000.00 | 400.00 | 4,000.00 | 360.00 | 3,600.00 | | 0070 | 736-01-00100 | Trenching and Backfilling | 1,326 | LNFT | 7.00 | 9,282.00 | 7.00 | 9,282.00 | 60.00 | 79,560.00 | | 0071 | 736-03-00100 | Jacking or Boring | 3,162 | LNFT | 22.00 | 69,564.00 | 26.00 | 82,212.00 | 7.00 | 22,134.00 | | 0072 | 736-04-00001 | Signal Pole (Pedestal Pole) | 11 | EACH | 1,570.00 | 17,270.00 | 3,000.00 | 33,000.00 | 2,800.00 | 30,800.00 | | 0073 | 736-04-10450 | Signal Pole (Single Mast Arm, 45ft) | 1 | EACH | 16,500.00 | 16,500.00 | 13,000.00 | 13,000.00 | 13,000.00 | 13,000.00 | | 0074 | 736-04-10600 | Signal Pole (Single Mast Arm, 60ft) | 1 | EACH | 24,250.00 | 24,250.00 | 28,000.00 | 28,000.00 | 27,000.00 | 27,000.00 | | 0075 | 736-04-10650 | Signal Pole (Single Mast Arm, 65ft) | 1 | EACH | 25,700.00 | 25,700.00 | 30,000.00 | 30,000.00 | 28,000.00 | 28,000.00 | | 0076 | 736-04-10700 | Signal Pole (Single Mast Arm, 70ft) | 1 | EACH | 26,150.00 | 26,150.00 | 35,000.00 | 35,000.00 | 31,000.00 | 31,000.00 | | 0077 | 736-04-24540 | Signal Pole (Dual Mast Arm, 45ft-Arm 1, 40ft-Arm 2) | 1 | EACH | 23,200.00 | 23,200.00 | 20,000.00 | 20,000.00 | 17,000.00 | 17,000.00 | | 0078 | 736-04-25035 | Signal Pole (Dual Mast Arm, 50ft-Arm 1, 35ft-Arm 2) | 1 | EACH | 27,500.00 | 27,500.00 | 32,000.00 | 32,000.00 | 28,000.00 | 28,000.00 | | 0079 | 736-05-30000 | Signal Heads (3 Section, 12 inch Led Lens, R, Y, G) | 23 | EACH | 880.00 | 20,240.00 | 1,240.00 | 28,520.00 | 1,200.00 | 27,600.00 | | 0080 | 736-05-31001 | Signal Heads (3 Sec, 12 inch Led Lens, LT. R, LT. Y, LT. G) | 12 | EACH | 880.00 | 10,560.00 | 1,240.00 | 14,880.00 | 1,200.00 | 14,400.00 | | 0081 | 736-05-35000 | Signal Heads (3 Section, 12 inch Led Lens, R, RT. Y, RT. G) | 1 | EACH | 880.00 | 880.00 | 1,240.00 | 1,240.00 | 1,200.00 | 1,200.00 | | 0082 | 736-05-35001 | Signal Heads (3 Sec, 12 inch Led Lens, RT. R, RT. Y, RT. G) | 1 | EACH | 880.00 | 880.00 | 1,500.00 | 1,500.00 | 1,200.00 | 1,200.00 | | 0083 | 736-06-00100 | Signal Service | 2 | EACH | 1,170.00 | 2,340.00 | 2,000.00 | 4,000.00 | 1,500.00 | 3,000.00 | | 0084 | 736-06-00500 | Signal Service Pedestal Disconnect | 2 | EACH | 2,040.00 | 4,080.00 | 3,000.00 | 6,000.00 | 2,600.00 | 5,200.00 | | 0085 | 736-08-00102 | Signal Controller (980 ATC, Type 2)(Furnish & Install) | 2 | EACH | 7,090.00 | 14,180.00 | 9,000.00 | 18,000.00 | 8,200.00 | 16,400.00 | | 0086 | 736-09-00100 | Loop Detector | 3,228 | LNFT | 24.00 | 77,472.00 | 20.00 | 64,560.00 | 20.00 | 64,560.00 | | 0087 | 736-10-00200 | Underground Junction Box (Type E) | 12 | EACH | 820.00 | 9,840.00 | 800.00 | 9,600.00 | 750.00 | 9,000.00 | | 0088 | 736-10-00300 | Underground Junction Box (Type F) | 15 | EACH | 970.00 | 14,550.00 | 900.00 | 13,500.00 | 850.00 | 12,750.00 | | 0089 | 736-10-00400 | Underground Junction Box (Type G) | 2 | EACH | 1,600.00 | 3,200.00 | 1,500.00 | 3,000.00 | 1,400.00 | 2,800.00 | | 0090 | 736-11-00050 | Conduit (1/2" HDPE, Schedule 80) | 95 | LNFT | 2.20 | 209.00 | 3.30 | 313.50 | 3.00 | 285.00 | | 0091 | 736-11-00100 | Conduit (1" HDPE, Schedule 80) | 52 | LNFT | 4.40 | 228.80 | 5.00 | 260.00 | 5.00 | 260.00 | | 0092 | 736-11-00200 | Conduit (2" HDPE, Schedule 80) | 1,242 | LNFT | 4.80 | 5,961.60 | 8.00 | 9,936.00 | 7.00 | 8,694.00 | | 0093 | 736-11-00300 | Conduit (3" HDPE, Schedule 80) | 1,539 | LNFT | 5.30 | 8,156.70 | 10.00 | 15,390.00 | 9.00 | 13,851.00 | | 0094 | 736-12-00000 | Conductor (2c, Loop Lead in, imsa 50-2, #14 awg, Twisted Pair) | 3,955 | LNFT | 1.30 | 5,141.50 | 1.20 | 4,746.00 | 1.25 | 4,943.75 | | 0095 | 736-12-00001 | Conductor (6 pair,Twisted Pair, isma 20-6 / #19 awg) | 2,373 | LNFT | 2.00 | 4,746.00 | 4.00 | 9,492.00 | 3.50 | 8,305.50 | | 0096 | 736-12-02014 | Conductor (2c, #14 awg) | 2,487 | LNFT | 1.25 | 3,108.75 | 1.20 | 2,984.40 | 1.25 | 3,108.75 | | 0097 | 736-12-03006 | Conductor (3c, 6 gauge / #6 awg) | 73 | LNFT | 3.25 | 237.25 | 4.00 | 292.00 | 3.25 | 237.25 | | 0098 | 736-12-06014 | Conductor (6c, #14 awg) | 4,835 | LNFT | 2.10 | 10,153.50 | 1.60 | 7,736.00 | 1.75 | 8,461.25 | | 0099 | 736-12-10014 | Conductor (10c, #14 awg) | 4,346 | LNFT | 3.10 | 13,472.60 | 2.50 | 10,865.00 | 2.75 | 11,951.50 | | 0100 | 736-15-00000 | Signal Support (Foundation, Special Design) | 3 | EACH | 36,350.00 | 109,050.00 | 30,000.00 | 90,000.00 | 28,000.00 | 84,000.00 | | 0101 | 736-15-03600 | Signal Support (Foundation, 36 inch Minimum Diameter) | 2 | EACH | 3,700.00 | 7,400.00 | 4,000.00 | 8,000.00 | 3,750.00 | 7,500.00 | | 0102 | 736-15-05400 | Signal Support (Foundation, 54 inch Minimum Diameter) | 1 | EACH | 17,725.00 | 17,725.00 | 14,000.00 | 14,000.00 | 12,000.00 | 12,000.00 | | 0103 | 736-16-00000 | Temporary Traffic Signal Installation (Intersection) | 2 | EACH | 50,530.00 | 101,060.00 | 80,000.00 | 160,000.00 | 70,000.00 | 140,000.00 | | 0104 | 736-21-00000 | LED Pedestrian Countdown Signal Head | 12 | EACH | 590.00 | 7,080.00 | 800.00 | 9,600.00 | 775.00 | 9,300.00 | | 0105 | 737-04-00001 | Painted Curbs and Islands | 449 | LNFT | 11.00 | 4,939.00 | 12.00 | 5,388.00 | 12.00 | 5,388.00 | | 0106 | 739-01-00100 | Hydro-Seeding | 1.53 | ACRE | 2,800.00 | 4,284.00 | 4,000.00 | 6,120.00 | 4,500.00 | 6,885.00 | | 0107 | 740-01-00100 | Construction Layout | 1 | LUMP | 153,005.47 | 153,005.47 | 140,000.00 | 140,000.00 | 150,000.00 | 150,000.00 | | 0108 | NS-500-00220 | Sawing and Sealing Longitudinal Joints in Asphalt Concrete Overlay | 3,093 | LNFT | 3.25 | 10,052.25 | 2.50 | 7,732.50 | 2.50 | 7,732.50 | | 0109 | NS-500-00240 | Sawing and Sealing Transverse Joints in Asphalt Concrete Overlay | 2,745 | LNFT | 3.25 | 8,921.25 | 3.30 | 9,058.50 | 3.00 | 8,235.00 | | 0110 | NS-500-00260 | Sawcuts in Asphalt Concrete Lifts | 5,838 | LNFT | 1.60 | 9,340.80 | 0.80 | 4,670.40 | 1.00 | 5,838.00 | | 0111 | NS-500-00340 | Saw Cutting Asphalt Concrete Pavement | 13,218 | INLF | 1.60 | 21,148.80 | 0.80 | 10,574.40 | 0.75 | 9,913.50 | | 0112 | NS-500-00360 | Saw Cutting Asphalt Concrete Pavement Over Portland Cement Concrete Composite Pavement | 33,047 | INLF | 1.60 | 52,875.20 | 1.10 | 36,351.70 | 1.00 | 33,047.00 | | 0113 | NS-736-00001 | GPS | 2 | EACH | 490.00 | 980.00 | 800.00 | 1,600.00 | 800.00 | 1,600.00 | | 0114 | NS-736-00130 | TS-2 Traffic Signal Cabinet (Ground Mounted) | 2 | EACH | 21,800.00 | 43,600.00 | 26,000.00 | 52,000.00 | 25,000.00 | 50,000.00 | | 0115 | NS-736-00135 | 2-Wire Accessible Pedestrian Pushbutton Detectors | 12 | EACH | 1,000.00 | 12,000.00 | 1,200.00 | 14,400.00 | 1,100.00 | 13,200.00 | | 0116 | NS-736-00136 | 2-Wire Accessible Pedestrian Pushbutton Cabinet Control | 2 | EACH | 3,500.00 | 7,000.00 | 4,000.00 | 8,000.00 | 3,300.00 | 6,600.00 | | 0117 | TS-P26-00020 | Conduit (4 inch Multiduct) (Jefferson Parish) | 2,313 | EACH | 25.00 | 57,825.00 | 25.00 | 57,825.00 | 22.50 | 52,042.50 | | 0118 | TS-P26-00100 | Fire Hydrant Assembly (Jefferson Parsh) (Jefferson Parish) | 1 | EACH | 5,100.00 | 5,100.00 | 11,000.00 | 11,000.00 | 7,500.00 | 7,500.00 | | 0119 | TS-P26-10206 | Gate Valve and Valve Box (6") (Jefferson Parish) (Jefferson Parish) | 4 | EACH | 1,000.00 | 4,000.00 | 2,200.00 | 8,800.00 | 1,000.00 | 4,000.00 | | 0120 | TS-P26-10208 | Gate Valve and Valve Box (8") (Jefferson Parish) (Jefferson Parish) | 2 | EACH | 1,600.00 | 3,200.00 | 3,300.00 | 6,600.00 | 1,600.00 | 3,200.00 | | 0121 | TS-P26-15006 | Waterline 6" (DI) (Jefferson Parish) | 100 | LNFT | 71.00 | 7,100.00 | 160.00 | 16,000.00 | 215.00 | 21,500.00 | | 0122 | TS-P26-15008 | Waterline (8") (Ductile Iron) (Jefferson Parish) (Jefferson Parish) | 100 | LNFT | 82.00 | 8,200.00 | 180.00 | 18,000.00 | 265.00 | 26,500.00 | | 0123 | TS-P26-15020 | Waterline 20" (DI) (Jefferson Parish) | 1,706 | LNFT | 156.00 | 266,136.00 | 220.00 | 375,320.00 | 330.00 | 562,980.00 | | 0124 | TS-P26-15116 | Waterline 20" (PVC) (Restrained) (Jefferson Parish) | 100 | LNFT | 144.00 | 14,400.00 | 300.00 | 30,000.00 | 300.00 | 30,000.00 | | 0125 | TS-P26-15120 | Waterline 6" (PVC) (Restrained) (Jefferson Parish) | 160 | LNFT | 44.00 | 7,040.00 | 170.00 | 27,200.00 | 200.00 | 32,000.00 | | 0126 | TS-P26-15122 | Waterline (8" PVC) (Restrained) (Jefferson Parish) | 620 | LNFT | 47.00 | 29,140.00 | 180.00 | 111,600.00 | 250.00 | 155,000.00 | | 0127 | TS-P26-15130 | Waterline (36" Steel Casing) (Jack and Bore) (Jefferson Parish) | 385 | LF | 1,150.00 | 442,750.00 | 1,500.00 | 577,500.00 | 1,800.00 | 693,000.00 | | 0128 | TS-P26-70100 | Fittings for Waterlines (DI) (Jefferson Parish) (Jefferson Parish) | 9,500 | LB | 8.50 | 80,750.00 | 8.00 | 76,000.00 | 9.00 | 85,500.00 | | 0129 | TS-P26-70101 | Transitional Coupling (Long Body) (6") (Jefferson Parish) (Long Body) (Jefferson Parish) | 3 | EACH | 935.00 | 2,805.00 | 1,200.00 | 3,600.00 | 350.00 | 1,050.00 | | 0130 | TS-P26-70103 | Removal and Disposal of Existing AC Waterline (6") (Jefferson Parish) | 82 | LNFT | 22.00 | 1,804.00 | 15.00 | 1,230.00 | 50.00 | 4,100.00 | | 0131 | TS-P26-70103 | Removal and Disposal of Existing AC Waterline (8") (Jefferson Parish) | 580 | LNFT | 11.00 | 6,380.00 | 15.00 | 8,700.00 | 40.00 | 23,200.00 | | 0132 | TS-P26-70104 | Transitional Coupling (Long Body) (8") (Jefferson Parish) (Long Body) (Jefferson Parish) | 4 | EACH | 800.00 | 3,200.00 | 1,200.00 | 4,800.00 | 365.00 | 1,460.00 | | 0133 | TS-P26-70109 | Transitional Coupling (Long Body) (20") Jefferson Parish) (Long Body) (Jefferson Parish) | 1 | EACH | 3,700.00 | 3,700.00 | 3,000.00 | 3,000.00 | 2,000.00 | 2,000.00 | | 0134 | TS-P26-70111 | Pipe Restraints (6") (Jefferson Parish) | 17 | EACH | 188.00 | 3,196.00 | 300.00 | 5,100.00 | 165.00 | 2,805.00 | | 0135 | TS-P26-70112 | Pipe Restraints (8") (Jefferson Parish) | 15 | EACH | 234.00 | 3,510.00 | 400.00 | 6,000.00 | 190.00 | 2,850.00 | | 0136 | TS-P26-70118 | Pipe Restraints (20") (Jefferson Parish) | 20 | EACH | 1,130.00 | 22,600.00 | 1,600.00 | 32,000.00 | 950.00 | 19,000.00 | | 0137 | TS-P26-70119 | PCCP Adapter (20") (Jefferson Parish) | 2 | EACH | 7,000.00 | 14,000.00 | 15,000.00 | 30,000.00 | 17,500.00 | 35,000.00 | | 0138 | TS-P26-74101 | Water Service Connections (<1") (Jefferson Parish) | 6 | EACH | 1,200.00 | 7,200.00 | 1,300.00 | 7,800.00 | 1,750.00 | 10,500.00 | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 6,095,000.00 | | 7,326,326.14 | | 8,050,901.02 |
|